Reporting Against Projects Included in Multiple Portfolios

You can designate a percentage of a project to a portfolio (see Associating Portfolio Projects and Sub-Portfolios). You can then run a report that prorates selected aggregate fields to the value of the "% to include" field. Create your report, include the appropriate aggregate fields, such as Actual Hours, Demand Hours, Estimated Hours, Actual Cost, and so on, and choose the Prorate Portfolio Components By % To Include option in the List/Chart Options tab of the report wizard. 

You can disable this setting if you wish to see the whole cost of a project, rather than just those values contributing to the portfolio.