What's New - October 2019
Release Schedule
Click here for an overview of the PPM Pro release process.
The table below lists this month's product release dates.
What | When |
---|---|
Release Notes published | October 4 |
System released to sandbox environments | October 11 |
System released to production environments |
October 25 (note new date) |
Releases are deployed during the standard maintenance windows.
Reminders
- Features that are ready will enter GA status in the first month's release of each calendar quarter: January, April, July, October. There will be an occasional variance from this schedule. You can enter a support request to move a beta feature into your production environment.
- You can request that beta features be enabled in your production environment by entering a support ticket. Please note that any issues you find will be handled during the normal development cycle.
- Planview sends out status emails in advance of planned releases/updates. These alerts include the date and time window of the update, as well as a link to the release notes that include a list of the issues addressed in the update/release. To subscribe to these alerts, please go to https://status.planview.com/ and click the Subscribe button.
- We hold a live product release webinar - typically on the Wednesday before the production release. This webinar will be hosted by PPM Pro product management and consulting personnel, and will include time for Q&A. Click here to register for the October 16th release webinar.
- Inner circles are offered as a way for our interested customers to collaborate with PPM Pro Product Management and each other, provide feedback on PPM Pro product capabilities, and guide new feature development. Click here for more information or to register.
Update 1
Release planned for Friday November 1, 2019, pending QA approval.
Function Area | ID | Release Note Description |
---|---|---|
Project, Staffing | 926230787 | Fixed. Users are no longer receiving a CancellationException message when navigating to the project Staffing page of projects with a large number of allocations that extend for a long period of time. |
Tasks | 925464942 | Fixed. Moving a task by selecting and dragging works as expected. |
Tasks | 918640834 | Fixed. Tasks can be added to the grid using the spreadsheet editor as expected. Previously, if a read-only Category field was included on the grid, the system threw an error when the user attempted to add a task. |
Timesheets | 924800987 | Fixed. Project managers doing timesheet PM approvals can double-click and open a timesheet. Previously, double-clicking threw an error. |
Timesheets | 925031354 | Fixed. Out-of-the-box timesheet filters are working as expected ("Timesheet:+Pending Submit / Reject," "Timesheet:+Pending PM Approval," and "Timesheet:+Pending Final Approval") |
New Feature Matrix
Available |
Notes |
Status |
For more information… |
|
---|---|---|---|---|
New Requests! (aka Requests revamp) This feature will be rolled out over the course of several releases ("rolling beta"). We will update this list every month to indicate when/what additional features will be included. Legacy requests will continue to be supported for the foreseeable future. You can use legacy requests and new requests side-by-side while you set up the new requests to your liking. Since the new model is different from the legacy in several key ways, we are not planning an automated migration at this time. |
Current functionality (rolling beta)
Coming Later
|
Beta |
New: Configuring Gate Skipping User Experience Inner Circle: New Requests - Note that this was recorded earlier this year, and target dates have shifted Gate Approval Examples, Videos Gate Approval Example - Screenshots Transitioning from Legacy to New Requests
|
|
Domain change for PPM Pro! innotas.com -> ppmpro.com
|
In order to align our users' experience with the branding which was rolled out in the beginning of 2018, starting with the October 2019 sandbox release on Oct 11, then the production release on Oct 25th, you will access PPM Pro through a new domain name, ppmpro.com. For example, if you currently access PPM Pro at mycompanyname.innotas.com you will now use mycompanyname.ppmpro.com. To make this transition as smooth as possible, we will redirect connections to innotas.com to ppmpro.com for the foreseeable future. This will give ample time to update links, bookmarks, integrations, and so on. You do not need to take any immediate action. Things you can optionally do now, in preparation for the change:
Things you can optionally do after the October release at your leisure:
Please contact customer care if you have any questions regarding this change and also be sure to check the FAQ.
|
Note the date for the changeover is Oct 25th.
|
||
Deprecate task-level expenses |
Project-level financials was made generally available (GA) for all customers in October 2018. We will begin to enforce the transition away from task-level expenses on the year anniversary. Phase 1 - October 2019: The ability to create new task level expense estimates will be disabled (New button removed). This will prevent the creation of new expense estimates. Phase 2: The task level expense facility will remain visible but view only. This will allow you to run reports on historical data. We will leave this enabled until we are sure that there is no longer any need for this data. As always, if you are already not using this feature and would like it removed so it doesn't confuse anyone, please enter a Customer Care Case and ask to disable the New button or the entire feature for your organization. |
October 2019 | Transitioning to Project-Level Expenses | |
Coming Soon | ||||
Reports Revamp! |
Beta Target - November 2019 |
Release Notes
Function Area | ID | Release Note Description |
---|---|---|
Alerts, Staffing | 808245536 | Fixed. Staffing alerts are sent to the newly staffed resource when the resource is added by typing in the resource name to replace the No Resource placeholder under a role. Previously, an alert was sent only if the resource was added using Add Resource or Staff Resource. |
Calculated Fields | 882481694 | Fixed. GetRelatedEntityValue works as expected for the resource entity. Previously, calculated fields using this function on resources returned no values. |
Display, Rich Text Editor | 903020399 906442436 |
Fixed. When viewing PPM Pro in presentation mode, text in the rich text editor can be formatted as expected. Previously, an issue caused all text to appear bolded when using the Presentation display theme. |
Issues | 906698893 |
Fixed. The Data Import now supports the same permissions as the UI with regard to importing project logs/issues. Resource must be either be:
Previously, an issue caused an error to be thrown when attempting to import members of the project team. |
Permissions, Finance Fields | 745894943 |
Updated: 11/4/19 Fixed. The project-level finances project included bringing financial functionality under the new permissions model ("profile-based permissions"). That is, in order to see the project Financials section and other financial fields, a user needs to have permission to View/Edit project Forecasts and project Actuals. As of the October release, users also need these permission to see the Total Forecast Entries and Total Actual Entries fields on the project. Most likely you already have project Forecasts and Actuals configured using permissions - but if the Total Forecast Entries and Total Actuals Entries fields suddenly disappear from your project, you simply need to give the appropriate users permission to View or Edit project Forecasts and/or project Actuals. If you would like members of the ICV group to be able to view and edit all financial entries, you can easily accomplish this by adding a group rule for the ICV group to an appropriate permission profile. |
Permissions, Financial Entries | 905421602 |
Updated: 11/4/19 Fixed. The project-level finances project included bringing financial functionality under the new permissions model ("profile-based permissions"). That is, in order to see the project Financials section and other financial fields, a user needs to have permission to View/Edit project Forecasts and project Actuals. As of the October release, users also need these permission to see the Total Forecast Entries and Total Actual Entries fields on the project. Most likely you already have project Forecasts and Actuals configured using permissions - but if the Total Forecast Entries and Total Actuals Entries fields suddenly disappear from your project, you simply need to give the appropriate users permission to View or Edit project Forecasts and/or project Actuals. If you would like members of the ICV group to be able to view and edit all financial entries, you can easily accomplish this by adding a group rule for the ICV group to an appropriate permission profile. |
Projects | 894504252 | Improved. When creating a project from a template, the Owner field will now default to the current user. Previously, the value of the template's Owner field was used by default when creating a project from a template, which resulted in the specified resource receiving a large number of email alerts. More often than not, the resource configured as the owner is not actually the appropriate resource, but was left configured as the Owner from a previous use of the template. More likely the current user (who is creating the project) is a better default for project Owner. Note that when using the WS API to create a project from a template, the value of the Owner field WILL be used. |
Projects | 901416655 | Fixed. Project dependencies work as expected. Previously, adding soft dependencies to newly created projects was occasionally throwing an error in certain circumstances. |
Projects | 883648161 889778879 |
Fixed. Project grid settings, such as column fields, field size, and locked fields, are sticky (retained) per category. Previously, an issue was causing these settings to be lost when users switched categories, requiring the user to frequently reconfigure. |
Reports | 888534711 | Fixed. The Department field can be added to a Gantt chart report definition as expected. Previously, in certain scenarios, the use of a UDF that points to a resource list prevented the Department field from being added to the chart definition. |
Reports, Tasks, Gantt | 899944716 | Fixed. Tasks gantt reports run and return expected results. Previously, an issue was preventing the gantt chart report from running. |
Resource Workbench | 839577504 | Fixed. After changing a task schedule - for example, extend the task dates - in a task-level resource planning (bottom-up) project, the Resource Workbench reflects the updated utilization percentage in a minute or so. Previously an issue was causing a delay in refreshing the utilization value. |
SSA, List Fields | 892288997 | Fixed. User-defined lists fields that are based on the Picklist: Active Resources/Active Users works as expected. Previously, when applying the field to a Details panel, the filter value would be limited to resources, while on Available Fields the filter value would be limited to users. Now the filter values for a UDF based on Picklist: All Active Resources/Active Users are consistent. |
Tasks, Scheduling | 874079069 | Fixed. When scheduling a resource to a task, the Find Other dialog displays the correct number of hours. Previously, an issue caused the values to be calculated incorrectly if the resource was staffed multiple times to the project. |
Tasks, Calendars | 885990618 | Fixed. After selecting a task calendar that differs from the project calendar, the task start and target dates are updated to reflect the working hours of the task calendar. Previously, an issue prevented the tasks dates from being update in response to the new task calendar. |
Tasks, Filters | 901817514 | Fixed. Multi-select task filters using Is and Is Not operators work as expected. Previously, multi-select field task filters that used these operators were not producing expected results. |
Tasks, MSP | 882469711 | Improved. MSP tasks that use elapsed days ("edays") will no longer error out upon import. When importing into PPM Pro, use the property "Import All Tasks as Manually Scheduled (MSP controls scheduling)". Note that this simply allows the tasks to be imported without errors using the MSP task start and target dates, but ignores the duration format "edays". As a result, the duration format shown after import will be "days". |