Skip to main content
Planview Customer Success Center

Working with the Task List

The Task List presents a hierarchical list of all tasks that meet your filter criteria, a Gantt chart view of those tasks, as well as a set of task tabs for managing all aspects of a task.

There are two access points to the tasks list:

  • Open a project and click the Tasks link in the left-nav pane. This view presents tasks within the context of the current project.
  • The Home/Tasks page is a filtered view of all the tasks that the you own or or are scheduled to, and which belong to projects whose implied status is not equal to Closed. This page has a subset of the functionality found on the project Tasks page - notably the ability to create and delete tasks is not supported on this page, and there is no Gantt view.

Other helpful task topics:

Anatomy of the Task View

The Task view provides a hierarchical list of tasks on the left-hand side (Task List), including a Gantt chart that can be hidden or shown, and a Task Info pane that houses multiple tabs you can use to manage different aspects of a task. When you select a task in the Task List, the relevant information for that task for whatever tab is active is displayed in the Task Info pane. You can expand/collapse the different panes to display only the Task List, or only the Task Info pane, by clicking any of the collapse tools (shown below), and you can use the splitter to resize the two panes. 

For best results, we recommend limiting the number of tasks per project to 1000.task_view_anatomy.png

The All Tasks record at the top of the Task List displays the rolled-up totals for all the tasks on the project. These totals are informed by the schedules for each task, with the details for each task displayed in the Task Info. When you make changes to the Task Details, the Task List automatically updates after you Save. Note that while you are editing the Task Info, the Task List is inactive until you save your changes.

Refer to Keyboard Shortcuts for a list of keyboard and toolbar shortcuts.

Editing

You can edit fields inline in the Tasks grid, where typically a subset of the Details fields appear. Simply double-click a row to activate. You can use your mouse and/or keyboard navigation. Tab moves you from field to field and to the Save/Cancel Buttons. Use arrow keys to move you through drop lists and suggested matches (for picklists) and use Return/Enter to make your selections. You can also edit fields in the Details panel using the same keyboard gestures, with the addition of Ctrl-S to save. Use Esc to undo an edit that hasn't yet been saved.

inline_edit.png

Newly Created or Edited Records

Note that you might find yourself in a situation where you have set up some filter criteria to populate the grid. Then you create a new record, or modify an existing record in such a way that it does not meet the current criteria (or might fall outside the scroll region). For example, your filter might specify "Status is In Progress," but you updated a task status to "Hold". Because we assume that you still might want to make additional edits, rather than immediately filter the tasks out of the list, PPM Pro keeps the task record in the list and makes it italicized. You can continue to edit until you navigate away from the screen. Any records that don't meet the current filter criteria, will be removed after refreshing the screen.

temporary_task_flag.png

Selecting Records

Select single records by single-clicking; use shift-click to select multiple records (or hold down the shift key and hit the down arrow key repeatedly). When you select more than one record, the message "n items selected" is displayed (temporarily) in the footer of the page. This is useful if you want to select a range of records and want to know the count.

The New Menu

The New menu contains operations for creating tasks. All operations except New Task at End and Bulk New assume that the operation is relative to the currently selected task.

When you create a new task, the task is created using the default category. If your organization uses only one task category (we expect this to be the most common case), then you will simply see a simple New menu, like below:

task_new_menu.png

If your organization has implemented multiple categories, then you will see an addition pull-right menu that contains the additional category(ies). The default category is configured by your administrator, and is the first category in the New Task menu. Note that there is a project setting called Default Task Category that can override the value set by your administrator. If you click the menu without sliding to the right, the default task will be used when creating the task. Otherwise, select the operation you want to use, and slide the cursor to the right and then choose the category.

task_category_menu.png

The Actions Menu

The Actions menu at the top of the list holds all operations that you can perform on tasks in the list. You can also access this menu by right-clicking on a task. Perform bulk actions by selecting multiple records (Shift-click or Ctrl-click) and then choosing an operation from the Actions or right-click menu.

actions_tasks_menu.png

Menu Option

Description

Expand All Expands the entire list of tasks (opens all branches).
Collapse All Closes the list of tasks (collapses all branches)

Edit

Invokes the inline editor for the selected task

Bulk Edit

Opens an editor that allows you to edit multiple tasks. Select the task (Shift-click or Ctrl-click to select multiple rows) and then choose Bulk Edit. See Bulk Editing for more information.

Open in New Tab

Open the selected task in a new tab.

Select All Selects all the tasks in the list.
Copy URL Copies the URL to the current task.

Copy Rows to Clipboard

Copy the selected rows to the clipboard. (Shift-click or Ctrl-click to select multiple rows.)

Associate Selected Tasks Create associations between the selected tasks. For example, if you select Task A and Task B and the choose Actions > Associate Selected Tasks, Task A will appear in Task B's Associations tab, and Task B will appear in Task A's Association tab. This is a shortcut for creating the association as you don't have to search for the task to associate - you can just select it (provided it is in the same project).
Outdent Shifts the selected task(s) to the left. The summary task will be converted to a leaf task if no child tasks remain.
Indent Shifts the selected task(s) to the left. This option is available only if there is a child task above the task(s) to shift that can be converted into a summary task.
Move Moves the selected task(s) to a new parent. See Moving Tasks.
Shift Shifts the start date of the selected task(s). Shifting a task's dates will cause its sub-tasks's dates to shift also, which may cause its parent task dates to adjust accordingly. 

To shift dates one week, use 5 days (Days=work days Mon-Fri). See Shifting Tasks.
Delete Deletes the selected task(s)
Schedule Provides ability to schedule multiple resources to multiple tasks.
Unschedule Provides the ability to remove multiple resources from a task.
Manage Dependencies Invokes the Manage Dependencies dialog, which allows you to create dependencies between tasks within this project or between tasks in this project and tasks in another project. See Creating Dependencies.
Schedule From... Allows you to reset the Schedule From date for the project.
Reschedule This menu option becomes available if there have been changes to the project's base calendar. Use this option to reschedule the project to adjust to the changes. You will see an icon in the task Info column that looks like a calendar. This appears when the project needs to be rescheduled.
MSP Import Provides the ability to import a Microsoft Project. See Importing/exporting tasks.
MSP/XML Export Provides the ability to export a PPM Pro task plan to an XML file which you can then import into Microsoft Project. See Importing/exporting tasks
Export to Excel Export a maximum of 5000 list rows to Microsoft Excel. If you export 5000+ rows, you will be notified that your export will be truncated and encouraged to run a report to accommodate the large number of rows. Reports can handle up to 50,000 rows. See Printing the Tasks List

Run Task Report

Provides a shortcut to access task-level reports.

Print Prints the task list to a PDF. See Printing Task List.

Customizing the Task List Grid

You can determine the columns that appear in the Tasks grid using the Configure Column Settings dialog. Click the Configure Columns gear icon to display the dialog. 

configure_columns_dialog.png

To add/remove columns  

To add columns to the grid, select them in the Available Fields pane and then click the right-arrow. To remove columns, select them in the right-hand panel and click the left-arrow. You can display 20 columns max. The list of fields available in this dialog is determined by the project category, which is configured by a user with PPM Pro administrative privileges.

Lock columns  

You can select one or more columns to remain "locked" to the left of the screen in the non-scrolling region, preventing them from scrolling out of view. The Title field for an entity is locked by default. To lock an additional column, select the field and click the Lock button. To move a column into the scrolling section of the grid, select it and click the Unlock button (on appears once you select a locked column other than Title).

Move Columns  

You can move columns to any position in the grid by simply dragging the column header in the grid. Or, you can change their position by clicking the Configure Settings icon and using the Move Up/Move Down buttons to reorder the columns.

Sorting  

To sort a list, simply click on a header. An arrow pointing up indicates ascending sorting; down indicates descending. Alternatively, click your cursor in the header to display the sort menu and choose the sort order - ascending or descending.

sort_order.png

Out-of-the-Box Task Filters

PPM Pro supplies a set of out-of-the-box (OOTB) filters - OOTB filters always preceded with a + sign :

  • Status: +Proposed
  • Status: +Open
  • Status: +Closed
  • +My Tasks - returns all tasks owned by current user or tasks current user is scheduled to. This filter is also available on Home/Tasks, with an additional criterion: Project:Implied Status is not Closed

You can map the status filters to a custom status. This is called having an implied status. For example, you might have a status called "under review," which maps to Proposed, and thus has an implied status of Proposed.

Filtering Tasks

Use the "ad-hoc" filter just as you would on any on page. See Ad-Hoc Filters for more information.

In addition, the Task filter allows you to search for a leaf node directly. It displays the results along with the parent node(s) that is implicitly used to find the leaf nodes. The parent is displayed in the search results in italics to indicate that it is not an actual result, but provides context for the actual result.

The screenshot below shows the results for Status is Hold. Note that Design Activities and Create Project are the results; Design and Project Initiation - both parent nodes, are just shown for context.

filter_results.png