Set different Billing types in sub-projects
Billing Type behavior in Projects/Programs and valid Sub-Project combinations
Note: Price refers to revenue, not cost.
Parent Project - Billing Type |
Sub Project - Billing Type |
Result |
---|---|---|
Fixed Price |
Fixed Price |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price |
Fixed Price Milestones |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price |
Time and Materials |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price |
Mixed |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price Milestones |
Fixed Price |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price Milestones |
Fixed Price Milestones |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price Milestones |
Time and Materials |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Fixed Price Milestones |
Mixed |
Parent Fixed Price is used. Sub Project amounts are ignored. |
Time and Materials |
Fixed Price |
Sub Project Fixed Price amounts are ignored. |
Time and Materials |
Fixed Price Milestones |
Sub Project Fixed Price amounts are ignored. |
Time and Materials |
Time and Materials |
Sub Project Labor and Non-Labor amounts are calculated and rolled up. |
Time and Materials |
Mixed |
Fixed Price sub-items are not included in revenue calculations for projects where Billing Type is Time And Materials |
Mixed |
Fixed Price |
Sub Project Fixed Price is used |
Mixed |
Fixed Price Milestones |
Sub Project Fixed Price Milestone’s Fixed Price is used |
Mixed |
Time and Materials |
Sub Project Labor and Non-Labor amounts are calculated and rolled up. |
Mixed |
Mixed |
Sub Project Labor and Non-Labor amounts are calculated and rolled up. Sub Projects with Fixed Price are also used and rolled up in Expected and Actual Revenue Sub Project Milestones with Fixed Price are also used and rolled up Expected and Actual Revenue |