;

Skip to main content

 

  • arrow icon

 

Planview Customer Success Center

Understand time-phased data fields

Standard Work Item Fields

The table below describes the fields used in AdaptiveWork for Financial Planning and include manually-entered fields and calculated (‘formula-based’) KPIs. 

Field

Definition

From Financial Plan

Can be Manually Set

Formula-Based

Budgeted Amount

A top-down budget amount total. The amount allocated to the Project.

 

✓

 

Budgeted Cost

A rolling-up cost field. Also known as Budget at Completion. (Planned Work * Hourly Cost Rates) + Non-Labor Budget Costs

✓

✓

 

Budget Variance

Budgeted Amount - Budgeted Cost

 

 

✓

Actual Cost

Work Item progress + Non-Labor Actual Costs

✓

✓

 

% Invested

(Actual Cost / Budgeted Cost) %

 

 

✓

Expected Revenue

(Planned Work * Hourly Billing Rates) + Billable Non-Labor Budget Revenue

✓

✓

 

Actual Revenue

(Timesheets Duration * Hourly Billing Rates) + Billable Non-Labor Actual Revenue + Actual Billed Expenses

✓

✓

 

Remaining Budget

Budgeted Amount - Actual Cost

 

 

✓

Cost Balance

Budgeted Cost - Actual Cost

 

 

✓

CPI

Cost Performance Index. Earned Value / Actual Costs

 

 

✓

SPI

Schedule Performance Index. Earned Value / Planned Value

 

 

✓

Planned Value

Expected Progress * Budgeted Cost. This is not displayed but is calculated on a daily basis.

 

 

✓

Expected Progress

A linear projection of a task’s work distributed over that task’s duration as defined in the Work Plan. It’s affected if you update the Work or the Duration. When assigned to a resource, the work is assigned to that resource’s work load according to that person’s availability (working hours and time off). This is the task’s Resource Load.

Example:

Project 1 has 2 tasks:

Task A is an 8 hour task. And has one resource (let’s call him “Bob”). Bob has an 8 hour work day and full availability to take on new project work, so we expect Bob to complete the task in one day.

Task B is a 3 day task. It has a dependency on task A, so that it is scheduled to start only after A is complete. Again it has only one person, Bob, assigned to do the work. As AdaptiveWork only takes into account working hours, the 3 day task with a single resource is the equivalent of 24 person/hours of work (that is: 8h * 3 = 24h).

 

 

✓

Earned Value

Budgeted Cost of Work Performed (BCWP). Completed Work expressed in terms of the Budgeted Cost.

 

 

✓

Cost Variance

Earned value - Actual Cost

 

 

✓

ETC

(Budgeted Cost - EV)/(CPI*SPI). A forecast of how much more money will need to be spent to complete the project.

 

 

✓

EAC

Estimate at Complete = Actual Cost + Estimate to Complete

 

 

✓

Budget Net Revenue

Budget Net Revenue = Budget Labor Revenue + Budget Revenue of BILLABLE 'internal' Non-Labor Resources + Planned Profit of 3rd Party Non-Labor Resources

 

 

 

Planned Net Margin %

(Planned Profit / Budget Net Revenue) * 100

 

 

 

Suggested Revenue

When Project's Labor Budget = Task Assignment, uses Work x Rates. When Project's Labor Budget = Project Assignment, uses Project Assignment x Rates"" AND Budget Revenue from Non-Labor Resources.

 

 

 

Actual Net Revenue

Actual Revenue of billable 'internal' Non-Labor Resources AND Actual Profit of billable 3rd Party Non-Labor Resources AND (Actual Effort x Rates).

See note below table

 

 

 

Actual Contribution %

(Actual Profit / Actual Net Revenue) * 100

 

 

 

Revenue EV

Labor = Actual Effort * Rates. Non-labor = actual margin of billable non labor

 

 

 

Suggested Net Revenue

When Project's Labor Budget = Task Assignment, uses Work x Rates. When Project's Labor Budget = Project Assignment, uses Project Assignment x Rates. For Non-Labor, Planned Profit of billable of 3rd Party Non Labor Resources, else Budget Revenue

 

 

 

Suggested Actual Net Revenue

Suggested Actual Net Revenue = Suggested Actual Labor Revenue + Actual Revenue of internal Non-Labor Resources + Actual Profit of 3rd Party Non-Labor Resources

 

 

 

 

Actual Net Revenue calculations

Field Fixed Price Time & Materials

Actual Net Revenue

(per month of Fixed price item)

Will not be broken down by Individual resources

Actual Revenue - Actual Cost of Billable 3rd party Costs

 

Straighline Monthly

(current fiscal month/Fiscal Months) * Fixed Price

Straighline Daily

(Working Days in fiscal month/Duration (d)) * Fixed Price

as earned

As we break down per resource:

Labor: Actual Revenue

Non labor, Billable 3rd party costs: Actual revenue - Actual Cost

Non-Labor, Not Billable: 0

Actual Net Revenue 

(Per month of LR/NLR)

If labor resource: Actual revenue

If non labor resource && Billable: Actual Revenue - Actual Cost

Straighline Monthly

(current fiscal month/Fiscal Months) * Fixed Price

Straighline Daily

(Working Days in fiscal month/Duration (d)) * Fixed Price

 

 

Forecasting fields 

For time-phased planning, there are forecasting fields that allow intra-month manual tracking of forecasted amounts that do not alter your work plans.

Financial Planning Fields

Definition

From Financial Plan

Can be Manually Set

Formula-Based

Budget Cost

Rolls up to Work Item Budgeted Cost. Labor Costs are calculated from Resource Planning * Cost Rates

✓

✓

✓

Actual Cost

Rolls up to Work Item Actual Cost. Labor Actuals are calculated from Timesheets.

✓

✓

✓

Forecast Cost

Manually set, does not roll up to work item.

✓

✓

 

Budget Revenue

Rolls up to Work Item Expected Revenue. Labor Revenues are calculated from Resource Planning * Billing Rates

✓

✓

✓

Actual Revenue

Rolls up to Work Item Actual Revenue. Labor Actuals are calculated from Timesheets.

✓

✓

✓

Forecast Revenue

Manually set, does not roll up to work item.

✓

✓