Alerts Summary
Alerts Summary
This page summarizes the Alerts generated by AdaptiveWork.
Some alert are user related and generated when the user perform an action, for example ‘Start date conflict’.
Other alerts are Auto generated after a time interval in days (this parameter is configurable via the ‘ System Settings ’).
Work Item related Alerts:
Alert Type |
Description |
Trigger |
Notification by |
Severity: High |
|||
Budget Exceed Planning Cost |
Alert is activated when the actual cost is lower than total cost of sub items |
Calculated daily |
Alert displayed in alerts module, and daily notification email sent out by midnight sameday |
Budget Exceed Planning Price |
Alert is activated when the budgeted cost is lower than total of sub items |
||
Budget Price Exceeds Cost |
Alert is activated when the budgeted cost is lower than actual cost |
||
Conflict in Planned Start Date |
Alert is activated when there is a conflict with planned start date of sub items |
||
Conflict in Planned End Date of Project |
Alert is activated when there is a conflict with the planned due date of sub items |
||
Conflict in Resource usage |
Alert is activated when the resources assigned to task are not working during the duration of the task |
||
Dependency Loop Between Projects |
Alert is activated when a loop is caused between dependant work items, causing a dependency to be automatically removed |
||
Disable Or Deleted Manager Alert For Project Manager |
Alert is activated when the user set as the project manager or manager is either deleted or deactivated in the system |
||
Impacted Date Conflict |
Alert is activated when there is a scheduling conflict |
||
Project Past Due Date |
Alert is activated when a project is past due |
||
Task Due Soon Has Assigned Resource without License |
Alert is activated when an unlicensed resource is assigned to a task |
||
Task on Critical Path Past Due Date |
Alert is activated when the a task is on the critical path and is past due |
||
Track Status Change to At Risk |
Alert is activated when the status of a work item is set to 'At risk' |
||
Track Status of Task on Critical Path Changed to At Risk |
Alert is activated when a work item is on the critical path and the status is set to 'At risk' |
||
Severity: Medium |
|||
On Past Committed Due Date |
Alert is activated when the customer committed date is past due |
Calculated daily |
Alert displayed in alerts module, and daily notification email sent out by midnight sameday |
Severity: Low |
|||
Task Due Soon Has No Resources Assigned |
Alert is activated when a task has no assigned resources |
Calculated daily |
Alert displayed in alerts module, and daily notification email sent out by midnight sameday |
Administration related Alerts:
Alert Type |
Description |
Trigger |
Notification by |
Severity: High |
|||
License Expiration |
Alert is activated when a user's license is about to expire |
7, 14 and 21 days before end of license |
Alert displayed in alerts module to admin. Additionally, User and admin will receive an email regarding license expiration |
Trial Period Expiration |
Alert is activated when a user's trial period is about to expire |
7 and 14 days before end of trial |
Trial user and admin will receive an email regarding trial expiration |