Planning Series Automation

A Planning Series is the planning calendar used by your board, which is a sequence of Planning Increments you assign to cards to organize and plan work over time.Many organizations nest increments (for example, a PI with sprints inside it). Your series names and structure may differ, but the pattern is the same: cards can be assigned to one or more increments, and sometimes to increments from more than one Planning Series on the board. 

planning increment.png

Assigning a card a Planning Increment

If increment assignments aren’t actively monitored, they can drift and throw off filters and reporting. Card Automation helps by applying your Planning Series calendar on a schedule or at card events so assignments stay current without a weekly manual chore.  

Because planning increments can be nested, you are also asked to specify top-level or sub-level so date rules and actions apply to the increment you intend, not the wrong layer of the calendar. 

Term

Meaning 

Often referred as ... 

Top-level 

The increment at the top of the series hierarchy 

The PI (program/quarter bucket) 

Sub-level 

A nested increment under a top-level increment 

sprint 

Example: One quarterly PI (top-level) with two-week sprints (sub-level) underneath. 

Why this matters

  • Date rules (start/end “days ago” or “from now”) run against increments at the level you specify. Use Sub-level when the use case is about sprints; use Top-level when it is about the PI. 

  • Move to next advances along the Planning Series order at the level you chose. On the last sprint under a PI, “next” can be the next PI or its first nested increment. 

  • A card can have both a PI and a sprint assigned; pick the level that matches what you are automating (sprint rollover vs PI change). 

Card Automation Basics

Every automation has three parts: 

  1. When to run: What event starts the check (for example, a card moves, or a scheduled run). 

  1. Criteria : Which cards qualify (lanes, status, Planning Increment rules, and more). 

  1. Action: What happens next (change increment, move card, clear increment, and so on). 

See below for example use cases, and what criteria and actions to apply.

Example Use Cases

# 

Use Case

When it runs 

What it does 

Sprint rollover 

Scheduled 

Unfinished cards move to the next sprint when the current sprint ends 

Sprint start pull 

Scheduled 

Backlog cards move into an active lane when the sprint starts 

Clear increment when done 

Card moved 

Removes increment assignment when work hits Done 

Assign new cards with current sprint 

Card created 

New cards get today’s sprint automatically 

Use Case 1: Sprint rollover 

Use when: Unfinished work should move to the next sprint when the current sprint’s end date has passed. 

Step 1 — When to run 

  • Event type: Scheduled Time  

  • Recurrence: Weekly  

  • Day/time: Choose a weekday that follows your usual sprint end cadence (for example, Monday after a Friday sprint end), or select every day to evaluate every day. Uses your local desktop’s time zone. 

Step 2 — Criteria 

  • Card lanes: Open/active only (exclude Finished) 

  • Planning Increments: Has an increment assigned 

  • Planning Increment Level (for date rules): Sub-level because you are rolling over to the next sprint, not the next increment. 

  • Planning Increment end date: Is less than this number of days ago → 7 if running once weekly 

Step 3 — Action 

  • Action type: Set Planning Increment  

  • Mode: Move to next planning increment  

  • Level: Sub-level 

  • Shift Mode:  

  • Keep current planning increments and add the adjacent one, to maintain history of all targeted sprints on the card 

  • Replace current planning increments, to represent the latest sprint the card is completed on 

Tips 

  • If the sprint that ended is the last sprint under a PI, cards will be added to the next planning series increment (for example the next PI or the first sprint under it). 

  • For Daily schedule: select all Days of the Week + end date 0 days ago. 

 

Use Case 2: Sprint start pull 

Use when: You use a lane for active sprint work and want backlog cards pulled in when the sprint starts. 

Step 1 — When to run 

  • Event type: Scheduled Time  

  • Recurrence: Weekly  

  • Day/time: Choose a weekday that follows your usual sprint end cadence (for example, Monday after a Friday sprint end), or select every day to evaluate every day. Uses your local desktop’s time zone. 

Step 2 — Criteria 

  • Lanes: Your specified backlog lane 

  • Planning Increments: Has an increment assigned 

  • Planning Increment Level (for date rules): Sub-level because you are pulling cards into a new sprint, not the next increment. 

  • Planning Increment start date: Is less than this number of days ago → 7 if running once weekly 

Step 3 — Action 

  • Action type: Move Card  

  • Destination Board/Lane: Your active work lane (for example, “In Progress”) 

Tips 

  • For Daily schedule: select all Days of the Week + end date 0 days ago. 

 

Use Case 3: Clear increment when done 

Use when: Finished cards should not keep increment assignment on reports and views. 

Step 1 — When to run 

  • Event type: Card Moved to Lane 

Step 2 — Criteria 

  • Lanes: Lane that represents finished 

  • Increment assignment: Has at least one planning increment 

Step 3 — Action 

  • Action type: Set Planning Increment  

  • Mode: Clear planning increments 

  • Level: Select "All levels" to completely remove all series from card. 

 

Use Case 4: Assign new cards with current sprint 

Use when: Every new card should be assigned to whichever sprint is active today. 

Step 1 — When to run 

  • Event type: Card Created 

Step 2 — Criteria 

  • Lanes: Target newly created cards in specific lanes 

  • Planning Increment: No increment assigned 

Step 3 — Action 

  • Action type: Set Planning Increment  

  • Mode: Set to current planning increment  

  • Planning Series: Select the applicable current planning increments defined for the board  

  • Level: Sub-level because you are assigning at the sprint level 

  • Update Mode: Add selection to existing planning increments