Is it possible to set a date constrainst at the project level?

Can I set a date constraint at the project level?


There is currently no way to set a planned start, or finish date constraint at the project level so no tasks can be scheduled before, or after.

Any users with the appropriate permissions can create tasks that start, or end before the original planned finish date of the project.