ETC isn't calculating according to the formula provided in help link

Why isn't ETC calculating according to the help link below?

http://h.daptiv.com/Help/PPM/J5_help...%20calculation


ETC doesn't calculate according to the formula below because the % complete was manually entered. In an order to avoid this to allow ETC to calculate properly, % complete must not be entered manually.

  • If % Complete > 0 and Work to Date = 0

ETC = Planned Work – (Planned Work * % Complete)