Update Forecast – Why and When to Use It
Over the life of a project, actual effort often differs from the original plan. As work progresses, project managers may need to re-forecast workloads to reflect actual work completed and adjust future planning accordingly.
A common example is month locking, where completed periods are finalized and future estimates must be updated without changing historical data.
Once triggered, the system automatically updates task assignments and resource planning based on actual work to date and the selected forecasting method.
What Update Forecast Enables You to Do
Using Update Forecast, project managers can:
-
Plan and adjust future task assignments per resource based on up-to-date effort information
-
Align budgets and forecasts with actual work completed, while planning accurately for upcoming periods
-
Lock historical assignments in completed periods, ensuring past data is preserved for reporting, audits, and financial accuracy
By preventing changes to past periods, Update Forecast helps avoid accidental updates that could distort reports, forecasts, or historical performance analysis.
Update Forecast allows you to keep your project plan accurate and reliable over time—reflecting real progress while protecting historical data and maintaining control over future planning.
Once the user selected 'Update Forecast', the system presents 3 options to choose from:
| Option | Method Name | Description |
|---|---|---|
| 1 | Retain total work estimate and spread future work |
In this method, the total work of the work item remains the same. The future task assignments are changed based on the difference between the total work and the actual work completed. Use this option when:
|
| 2 | Retain future planned work assignments |
Use this option when future task assignments must remain unchanged, even if actual work already performed differs from the original plan. When Option 2 is selected:
Typical Use case: Prepaid or contracted support hours |
| 3 | Update work for the entire task |
Use this option when the remaining work is different than the (planned work minus actual work). When Option 3 is selected:
Typical Use case: In-flight scope changes during implementations |
| Keep Manually Set Effort Values |
available for all Update Forecast methods. When enabled:
Note: If all task assignments were manually entered and were not generated by the system:
|
|