Resource Removal After Actuals Are Reported
Scenario:
1. A resource reported effort on a task.
2. The Update Forecast run and now there is a Preplanning date
3. Remove the resource from the task

Scenario 2:
1. Assign a resource to a task
2. the resource reported effort on a task and timesheet is approved
3. delete a resource
The original statement was: If a resource is removed from a task and Actual Effort exists before the Last Replanning Date, the system presents the following options. But only without running the Update Forecast it's possible
-
Make resource inactive
-
Removes assignment information from the Last Replanning Date onward
-
Retains historical Actuals and Budget/Forecast data
-
-
Delete resource and all related time entries
-
Removes all assignment and time entry data
-
Retains only actual financial information
-