When Tasks Cannot Be Replanned
Overview
During the Update Forecast process, you may receive a message indicating that some tasks cannot be automatically replanned.
This occurs when task constraints prevent the system from adjusting task dates or work distribution.
This document explains why this happens and how to resolve it.
Why This Message Appears
Tasks cannot be automatically replanned when they include manual constraints that conflict with the selected replanning date.
Common constraint scenarios include:
-
Tasks with a Fixed Duration
-
Tasks with a Due Date constraint
-
Tasks using a Fixed Duration work policy
-
The selected replanning date extends beyond the task’s Due Date
When any of these conditions apply, Update Forecast cannot shift task dates or redistribute work automatically.
How To Resolve the Issue
Step 1: Identify the Blocking Constraint
-
Open the task that could not be replanned.
-
Review the task configuration, focusing on:
-
Duration type
-
Work policy
-
Due Date
-
Step 2: Adjust or Remove the Constraint
Depending on the scenario, take one of the following actions:
-
Change the task from Fixed Duration to a flexible duration type.
-
Remove or update the Due Date so it aligns with the new replanning date.
-
Update the task Work Policy if it restricts automatic replanning.
Step 3: Run Update Forecast Again
-
Return to the project or task.
-
Run Update Forecast with the desired replanning date.
-
Verify that the task is successfully replanned.
Key Notes
-
Tasks with strict constraints require manual adjustment before they can be replanned.
-
Update Forecast does not override Fixed Duration or Due Date constraints.
-
Removing or relaxing constraints allows the system to automatically recalculate dates and work.
Decision Table: Task Constraints and Replanning Behavior
| Constraint Type | Configuration | Replanning Date Within Allowed Range | Replanning Date Exceeds Due Date | Automatic Replanning Supported | Required Action |
|---|---|---|---|---|---|
| None | Flexible duration, no Due Date | Supported | Supported | Yes | No action required |
| Due Date Only | Due Date defined | Supported | Not Supported | No | Update or remove the Due Date, then rerun Update Forecast |
| Fixed Duration | Duration is fixed | Not Supported | Not Supported | No | Change duration to a flexible type before replanning |
| Fixed Duration Work Policy | Work policy set to Fixed Duration | Not Supported | Not Supported | No | Change the task work policy to allow replanning |
| Fixed Duration + Due Date | Both constraints applied | Not Supported | Not Supported | No | Remove or adjust all blocking constraints |
| Due Date + Flexible Duration | Due Date defined, flexible duration | Supported | Not Supported | No | Adjust the Due Date or select an earlier replanning date |