Portfolios cost center-based ICP: Get started and optimize usage
Cost center-based investment and capacity planning adoption pathway
1. Understand the basics | 2. Design and set up | 3. Get started and optimize usage | 4. Gain insights with reports and outputs |
Audience |
Portfolio manager, finance manager |
Objective |
Get started by creating a planning portfolio then use ICP to analyze and approve portfolio projects. |
Planview Professional Services is available to support your deployment of Planview Investment and Capacity Planning capabilities. For more details, refer to the Planview Portfolios Capability Adoption Package: Investment and Capacity Planning.
The five principal steps of investment and capacity planning
These steps represent the full usage of investment and capacity planning. However, not every step is required for it to be meaningful and beneficial. Some customers start with simply determining capacity and demand, then ranking and prioritizing investments without using the more advanced scenario analysis and reporting options. Detailed information for each step can be found in the expandable sections below.
Principal stakeholders
Inputs from all participants are required to enable data-driven investment decisions.
Determine capacity
Create a planning portfolio
Step | Role | Description | Resources |
---|---|---|---|
Create a planning portfolio |
Portfolio manager Finance manager |
Create a new planning portfolio or review the planning portfolio that was shared with you. Key actions:
|
About Creating Planning Portfolios as a User Setting Up Investment and Capacity Planning as a User
|
Invite portfolio members |
Portfolio manager Finance manager |
Invite relevant collaborators to the planning portfolio. |
Share and Manage Access to a Planning Portfolio |
Review capacity (cost center) financial plans |
Portfolio manager Finance manager |
The cost center financial plans were loaded directly from the resource information already in Planview Portfolios. To review the data, select the Analyze view, then on the Portfolio Target row select , then Open Financials, then select the cost center to open the financial plan.
|
Updating Capacity and Demand Data by Accessing the Financial Plan Loading, Scheduling, or Deleting Cost Center-Based Financial Plans |
Identify demand
Step | Role | Description | Resources |
---|---|---|---|
Capture work financial demand |
Portfolio manager Finance manager |
The demand data will pull from the work financial plans from both in-flight projects as well as new projects that are being considered for approval. The options to add data to these financial plans are to:
|
Demand Portfolio Manager Screen Basics |
Prioritize and rank
Step | Role | Description | Resources |
---|---|---|---|
Create a scenario |
Portfolio manager Finance manager |
Create a user-defined scenario so you can make edits and evaluate different investment decisions and approaches to balancing demand against capacity in a what-if environment without changing the shared scenario or updating real-time financial data.
|
|
Rank work/projects from 1 to n |
Portfolio manager Finance manager |
Rank investments automatically based on criteria and/or manually by the users of each scenario. Investments are displayed in ranked order within a scenario. If no ranking has been applied, investments are displayed alphabetically. If a scenario includes both ranked and unranked investments, unranked investments will display at the top in alphabetical order, and the ranked investments will display below in ascending rank order. |
Automatically Rank Investments Based on Criteria |
Analyze to move projects above/below the line and set investment approval status |
Portfolio manager Finance manager |
Analyze potential work or projects by moving them above or below the line to see the impact to capacity targets and budgets. The Analyze view is divided into two trays. The upper tray incudes projects with the Accept or Conditional status, while the lower tray includes projects in the Refuse or Analyze status. To change the status of the investment decision, you can either use the action menu to select a new status, or drag and drop the project row to be above or below the line. |
|
Shift work/projects (optional) |
Portfolio manager Finance manager |
Shift project start dates, finish dates, and duration so they will fit within capacity constraints. The Shift view provides visibility into where demand exceeds capacity by period, as well as the ability to shift investments to fit within available capacity. After portfolio investments have been ranked and analyzed, date ranges of approved and conditionally-approved investments are further evaluated. Constraint limitations on specific resource types may be resolved by shifting investment dates, and investments below the line may be approved. |
|
Balance the details (optional) |
Portfolio manager Finance manager |
Balance and model detailed changes to specific time periods. Information on the grid at the lowest level is editable when you are viewing a user-created scenario or the Shared Scenario if it is editable. Use the category menu to decide which information to view and the focus control option to organize the way the data is displayed in the hierarchy. The Balance view allows you to look at investments that have been accepted in the scenario, and the time-profiled impact of those investments against the capacity and budget targets. |
Updating Capacity and Demand Data in Investment and Capacity Planning Updating Demand Data by Editing Cells Adding an Account Line with Attributes in Investment and Capacity Planning Changing Account Line Attributes in Investment and Capacity Planning |
Model alternatives as scenarios
Scenarios represent a more advanced use of investment and capacity planning and allows you to model the impact of changes or different decisions to the portfolio (for example, changes to budgets or staffing).
There are two types of scenarios: the shared scenario and the what-if (or user-defined) scenario.
The key difference is that the shared scenario interacts with real-time financial data. Any financial plan updates made in the shared scenario will automatically update the relevant financial plan versions for the entities. However, rank and investment status changes will not be updated for the entities until the scenario is published.
What-if or user-defined scenarios are created as a copy of another scenario and therefore do not interact with real-time financial data. In these scenarios, financial plan updates and changes to rank and investment status will NOT be reflected in the entities until published.
Planview recommendation: Use what-if or user-defined scenarios to model changes and different decisions for the portfolio.
Step | Role | Description | Resources |
---|---|---|---|
Add a user-defined scenario to model different situations |
Portfolio manager Finance manager |
Add a user-defined scenario to model different delivery approaches. For example, flexing the budget or emphasizing work aligned to different business objectives. Adding a new scenario copies the investment approval status values, priority values, and financial-planning data from the selected scenario to the new scenario. You can then make changes and do what-if planning using the rank, analyze, shift, and pivot views. |
Adding Investment and Capacity Planning Scenarios |
Choose and publish a plan
Step | Role | Description | Resources |
---|---|---|---|
Evaluate and compare multiple scenarios |
Portfolio manager Finance manager |
Use analytics and visual impact analysis tiles to evaluate and compare multiple scenarios before deciding on the optimal plan. |
Understanding Impact Analysis Report Tiles |
Publish scenario |
Portfolio manager Finance manager |
Once the plan is agreed and published to demand, financial data as well as decision status and ranking order are published back to the demand entities.
In addition to investment approval decisions, any amendments to demand data of investments or the capacity/budget targets within the (non-shared) scenario will also be published live and will update the financial planning detail screens accordingly for the investments or capacity in question. |
Publish in Investment and Capacity Planning Publishing a Scenario in Investment and Capacity Planning Publishing the Current Version of an Investment Plan as the Official Plan |
Capture baseline |
Portfolio manager Finance manager |
Once published, capture a baseline of the approved plan. This may be completed as part of a lifecycle, or can be manually captured by making a copy of the demand financial plan and then locking it. | |
Communicate the published plan |
Portfolio manager Finance manager |
Communicate the published plan to all relevant stakeholders. |