Capability usage
Beyond timesheeting: work management adoption pathway
1. Get started | 2. Design and set up | 3. Capability usage | 4. Reports and outputs |
Audience |
PMO, project manager |
Objective | These steps enable project managers to quickly get started with planning, executing, and tracking projects in Portfolios. |
Project planning and scheduling process steps
Step | Description |
Define project/work breakdown structure |
Define the project by building out the work breakdown structure to form the basis of the project schedule. For a simple project schedule, we recommend planning two levels deep at most. The project schedule consists of any elements in the work breakdown structure (WBS) that exist below the project level in the hierarchy, such as phases and tasks. Tip: Never plan to more detail than you are willing to manage. |
Edit WBS with dates, durations, and relationships | |
Add project milestones |
A milestone is a significant event or point in time of a project, strategic plan, or outcome plan. Milestones help users define key future dates before schedules are set. It’s important to note that a milestone task has no duration, and resources cannot be assigned to a work milestone. By creating milestones, users can define key dates and deadlines before detailing out phases of projects. Users responsible for creating a project plan should use the Plan screen to create a milestone for each major step of the project. Most project templates provide suggested milestones, but more can be created when needed. The important thing to remember is to set the appropriate cell in the Milestone Flag column to Yes on the Plan. After a milestone is set, you can schedule the milestone from the Schedule Start column, Schedule Finish column, or Constraint Type column. |
Plan resource requirements |
Plan which resource types will work on tasks and activities and populate the project schedule with an accurate and realistic role-based forecast in the form of resource requirements. |
Baseline schedule |
Take a baseline of the project schedule to capture a snapshot of the project's schedule as it proceeds into execution. This schedule baseline provides a record of the planned work phases, tasks, milestone dates, and durations as of the end of the planning phase to track any variances as the work progresses. Project managers should use baselines to compare current schedule information with an earlier version of the schedule. Such comparisons help project managers perform the following tasks:
|
Execution and tracking process steps
Step | Description |
Do work |
Resources carry out the work that has been assigned to them. |
Capture data on the progress of work |
As work progresses, resources' actual time spent on work is tracked, project managers update milestones and other dates as needed, and the Progressing Engine integrates actual time reported records with all the planning records in the database. Resources' time can be captured in the following ways:
|
Review progress of work |
Track and monitor the progress being made on work using tools such as baselines to compare the current status with the planned progress. For example, project managers can monitor the scheduled and actual dates and track the variance against initial expectations, such as an initial baseline, to obtain a full understanding of the project progress. Then, they can take a new baseline to compare against a baseline taken at the start of the project. This helps project managers have a clear understanding of how a project is progressing in relation to the original baseline and identify where dates have slipped or been brought forward. Any variance from the original project baseline may have financial implications or require the proactive reassignment of resources in order to prevent any negative impact on the project. |
Plan/re-plan remaining scheduled work |
Manage the schedule for the remaining scheduled work, adjusting dates and durations if necessary. |
Manage exceptions and report on project status and progress |
Ensure the project status and work details are correct and current, evaluating and re-prioritizing any items that aren't going to plan. Project managers can review or update the status of work on the Plan screen. Also, project stakeholders can view a summary of work status information on the WRK14 – Project (and Portfolio) Highlight Report, which is a FastTrack analytic. |