When does Viz record changes to an artifact’s state?
Last Updated: | Applicable Viz Versions: All
Last Updated: | Applicable Viz Versions: All
Viz does not use any modification or resolution dates from your tool connections to record an artifact's state, but instead uses the change detection time when the status change is detected.
Here are a few examples to demonstrate when status changes are recorded:
Example 1:
In this example, the Issue would be recorded as Done on Day 1.
Example 2:
In this example, the Issue would be recorded as Done on Day 2.
Example 3:
In this example, the Issue would be recorded as Done on Day 3.