Timeline Chart Configuration

 

When the Timeline chart type is selected, the configuration options displayed on the Chart tab are specific to the Timeline  chart and are described in detail below.

clipboard_e0356dcba4e4a0ff11a689046a0f2e368.png

 

Links: Choose between Links or No Links. Choosing links allows any projects that have been linked using the Project Links feature, enabled in Product Portfolio Management, to be displayed on the Timeline chart.

clipboard_e23db392575341b1367a05d641adf1203.png

 

Identifier: Select a field which uniquely identifies the item to be displayed on the chart

Label: Select a field to be used as a label for the bar on the chart

Start Date: Select a date field to determine the start of the bar

End Date: Select a date field to determine the end of the bar

clipboard_ec9fcf15149bd381488b7ea66cf6319b6.png

Summary Item Indicator: Select a Boolean field which indicates if the item is a summary item. Summary items will be displayed differently to standard items on the chart.

clipboard_eb2442d33c8b0af3cfd5ef30a7a62972b.png

Colour: Select a keyword field to display the Timeline bars in the colour associated with the keyword. This will override the default colour.

Default Colour: Set a colour to display the bars on the chart, if a Colour field is selected it will override this default. 

clipboard_e54331eeee7d317356b146758496509d9.png

Columns: Choose additional fields to display in tabular form at the left of the chart. 

clipboard_e39468e1d9abd82a0ed2441901043cca2.png

 

DISPLAY

 

Bar Height: Choose how wide the bars on the chart are displayed, options are Default, Narrow or Wide.

Initial Display Point: Select either a specific date or a function to automatically scroll the chart to this position when it is initially displayed.

clipboard_eee143733c162813030aca7b5f6a8dcb9.png