Skip to main content
Planview Customer Success Center

FastTrack Power BI Showcase Dashboards - Work

The below content provides examples of interactive Power BI dashboards created using data from Work portfolio column sets. These dashboards showcase a wide range of out-of-the-box Power BI visualizations which present project-level data in an engaging and meaningful way and aid detailed analysis through drill-down functionality. 

Detailed information is provided for each visualization, which highlights the configuration steps required to recreate the visual; examples of the types of Enterprise One Portfolio and Resource Management data that can be used; and the business outcomes supported by each example. 

Tab 1 - Financial Summary

FastTrack Power BI Work Showcase - Tab 1.png

 

Report Level and Page Level Filters
Description Example
Report Level Filters: filters that apply to all pages in the report

Report Level Filters:  Parent Description, 'Depth' =  5. In this example, '5' ensures that data is taken only from project-level within the WBS, not parent levels (the column set tabular model used as a data source will include all data relating to the WBS hierarchy on the portfolio screen, which may potentially include rolled up financial data from higher levels). The correct 'depth' to select will depend upon the customer configuration.

Page Level Filters: filters that apply to all visualizations on a page Page Level Filters: no page level filters have been applied in this report

 

 

Widget 1. Slicer by Portfolio

FastTrack PowerBI Work Showcase - Tab 1, Widget 1.png
  Description Example
Goal Provides a visual element to filter the data on the page Ability to slice data by Portfolio
Fields

Field: One work dimension (project-level attribute e.g. alternate structure, lifecycle role)

Field: Portfolio_Name
Formatting Suggestions

Can be vertical or horizontal, Title can be added, multi-select option can be enabled

Title: On (‘Portfolio’)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-slicers

 

 

Widget 2. Clustered Bar Chart showing Cost Variance and Costs at Complete by Program

FastTrack PowerBI Work Showcase - Tab 1, Widget 2.png

 

Description

Example

Goal

Use Case 1: Visualizes a single dimension against multiple measures

Visualize Strategies against Total Costs at Complete and Cost Variance

Business outcome: Identify strategic initiatives / programs that are at risk of exceeding approved budget

Fields

Axis: Work dimension (project-level attribute e.g. alternate structure, lifecycle role) to group the data in the visual

A further dimension can be added to facilitate drill-down of the data

Axis: Strategies

EntityName could be added as a second dimension, which would enable the user to drill-down and identify the projects that are contributing to the cost variance

Value: Two or more time-phased financial measures or PVE measures (financial subtotal, calculated attribute, numeric field), the data for which will be grouped by the chosen dimension/s Value: Cost Variance (FP FV-BV), Total Costs at Complete (FP FV)

Formatting Suggestions


 

Legend: Adds a legend to the visualization, providing a key for the different data groups

The position of the legend within the visualization can be changed if required

Legend: On (positioned at the top)

X Axis: Adds the category names to the X Axis based on the dimension chosen in the Axis field

Y Axis: Adds the value range to the Y Axis based on the measure chosen in the Value field

X Axis: On

Y Axis: On

Data Colors: Applies color-coding to the data groups Data Colors: Total Costs at Complete (FP FV) = Blue, Cost Variance (FP FV-BV) = Red
Data Labels: Adds data labels to each column in the visualization Data Labels: Off

Title: Adds a title to the visualization

The title is created automatically based on the data being displayed - it is often sensible to amend this to something more meaningful to the report audience

Title: On ('Cost Variance and Costs at Complete by Strategies')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual. 

The dimensions / measures added to the Axis, Legend and Value fields will automatically appear as filter options. If there are lots of categories to be displayed (e.g. if you are using EntityName as your dimension), filters can be applied to only show the top / bottom number of projects for the chosen measure 

Visual Level Filters: Strategies, Cost Variance (FP FV-BV), Total Costs at Complete (FP FV)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-basic-area-chart

 

 

Widget 3. Waterfall Chart showing Total Costs at Complete by Year

FastTrack PowerBI Work Showcase - Tab 1, Widget 3.png
  Description Example
Goal

Displays a running total as values are added or subtracted. It can visualize how an initial value is affected by a series of positive or negative changes

It is able to show the value for each time slice, as well as the cumulative value 

Visualizes how the Total Costs of the selected portfolio/s changes year on year and provides an overall total for the planning horizon
Fields
 

Category: One or more time dimensions (Year, Quarter, Month) by which you want to drill down into the data

Category: Year, Quarter, Month Description
Y Axis: One time-phased financial measure (financial subtotal or calculated attribute). An interesting use case would be to select a measure that could be either positive or negative (e.g. Cost Variance) Y Axis: Total Costs at Complete (FP FV)
Formatting Suggestions Legend: Adds a legend to the visualization, providing a key for the different data groups (the position of the legend within the visualization can be changed if required) Legend: On

X Axis: Adds the category names to the X Axis based on the dimension chosen in the Axis field

Y Axis: Adds the value range to the Y Axis based on the measure chosen in the Value field

X Axis: On

Y Axis: On

Data Labels: Adds data labels to each columns in the visualization Data Labels: Off
Sentiment Colors: Applies color to each sentiment (i.e. Increase, Decrease, Total) Sentiment Colors: Increase = Green, Decrease = Red, Total = Blue
Title: Adds a title to the visualization Title: On ('Total Costs at Complete by Year')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Category and Y Axis fields will automatically appear as filter options

Visual Level Filters: Year, Quarter, Month Description, Total Costs at Complete (FP FV)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-waterfall-charts

 

 

Widgets 4, 5 & 6. Cards showing Actual Cost, Cost Variance & Revenue

FastTrack PowerBI Work Showcase - Tab 1, Widget 4.png
  Example Description
Goal Displays the sum of the chosen measure, based on the filters selected

Widget 4: Shows the sum of the actual costs to date for the portfolio/s selected in the slicer

Widget 5: Shows the sum of the total cost variance (between baseline and forecast / actual costs) for the portfolio/s selected in the slicer

Widget 6: Shows the sum of the total revenue for the portfolio/s selected in the slicer

Business outcome: Identify portfolios that are exceeding approved budget, in relation to the expected revenue

Fields Field: One time-phased financial measure or PVE measure (e.g. financial subtotal, calculated attribute, numeric field) that will be displayed as a single value, determined by the filters applied

Widget 4: Actual Costs to Date (FP FV)

Widget 5: Cost Variance (FP FV-BV)

Widget 6: Total Benefits Revenue (FP FV)

Formatting Suggestions

Data Label: allows you to specify the display units (thousands, millions etc.) and the number of decimal places

These can also be defined automatically based on the data being display 

All: On, Display - Auto

Category Label: this will automatically add the label for the measure being displayed (this will reflect the name of the financial subtotal / calculated attribute / field in PVE and cannot be updated)

All: Off

Title: adds a title to the visualization

It is recommended that this option is chosen over Category Label as the title can be re-named to something more meaningful to the report audience

Widget 4: Actual Costs

Widget 5: Cost Variance

Widget 6: Revenue

Other formatting options: apply border, background, fonts, colors etc.  All: None applied
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-big-number

 

 

Widget 7. Stacked Area Chart showing Cost Profile by Strategic Program

FastTrack PowerBI Work Showcase - Tab 1, Widget 7.png
  Example Description
Goal

Visualizes the magnitude of change for the chosen measure over a period of time Highlights the total value across a trend

Provides a breakdown of the total costs per month by Strategy for the selected portfolio/s

Business outcomes: Identify the trend of costs by Strategy

Compare strategic investment costs over time

Fields

 
Axis: One or more time dimensions (adding further dimensions facilitates drill-down of the data - the level of drill-down should be appropriate for the customer data being displayed) Axis: Time Hierarchy (Year, Quarter, Month Description)
Legend: One work dimension (project-level attribute) to group the data in the visual Legend: Strategies
Values: One time-phased financial measure (e.g. financial subtotal), the data for which will be grouped by the chosen dimension/s Values: Total Costs at Complete
Tooltips: Can be used to display further information for each slice of data. However, this may end up being difficult to read on a stacked area chart if there is a large number of categories for each dimension used Tooltips: None
Formatting Suggestions Legend: Adds a legend to the visualization, providing a key for the different data groups (the position of the legend within the visualization can be changed if required) Legend: On 

X Axis: Adds the category names to the X Axis based on the dimension chosen in the Axis field

Y Axis: Adds the value range to the Y Axis based on the measure chosen in the Value field

X Axis: On

Y Axis: On

Data Colors: Applies color-coding to the data groups Data Colors: Different colors have been applied to each Strategy (e.g. Finance Deployment = Green, IT Deployment = Grey etc.)
Title: Adds a title to the visualization  Title: On ('Strategic Breakdown - Costs by Strategy')
Filters Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Axis, Legend and Values fields will automatically appear as filter options

Visual Level Filters: Month Description, Strategies, Total Costs at Complete
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-basic-area-chart

 

 

Tab 2 - Portfolio Balance Count

FastTrack Power BI Work Showcase - Tab 2.png
 

 

Widget 1. Slicer by Portfolio

FastTrack PowerBI Work Showcase - Tab 1, Widget 1.png
  Description Example
Goal Provides a visual element to filter the data on the page. Ability to slice data by Portfolio
Fields

Field: One work dimension (project-level attribute e.g. alternate structure, lifecycle role)

Field: Portfolio_Name
Formatting Suggestions Can be vertical or horizontal, Title can be added, multi-select option can be enabled Title: On (‘Portfolio’)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-slicers

 

 

Widget 2. Pie Chart showing Overall Status Assessment

FastTrack PowerBI Work Showcase - Tab 2, Widget 2.png
  Description Example
Goal  Illustrates numerical proportion

Provides a count of the projects in the selected portfolio/s by Overall Status Assessment

Business Outcome: Aids analysis of portfolio balance

Fields

 
Legend: Work dimension (project-level attribute e.g. alternate structure, Lifecycle role) to group the data in the visual Legend: Overall Status Assessment
Details: A further work dimension can be displayed as a sub-category Details: None
Values: Time-phased financial measure, PVE measure or count of a dimension, the data for which will be grouped by the chosen dimension/s Values: Count of Work ID
Formatting Suggestions


 
Legend: Adds a legend to the visualization, providing a key for the different data groups Legend: Off
Data Colors: Applies color-coding to the data groups Data Colors: Colors chosen to reflect the Overall Status Assessment categories (i.e. Red, Yellow, Green)
Data Labels: Adds data labels to each slice in the Pie Chart Data Labels: On (showing 'Category' only)
Title: Adds a title to the visualization  Title: On ('Work by Overall Status Assessment')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Legend, Details and Values fields will automatically appear as filter options. 

Visual Level Filters: Overall Status Assessment, Count of Work ID
 

 

Widget 3. Funnel Chart showing Work by Lifecycle Stage

FastTrack PowerBI Work Showcase - Tab 2, Widget 3.png
  Description Example
Goal Funnel charts are similar to a simple bar chart - they are useful to help visualize a dimension for which the categories follow a chronological order (e.g. Lifecycle Stage)

Provides a count of the projects in the selected portfolio/s by Lifecycle Stage

Business Outcome: Track the progress of the portfolio and can help identify any potential bottlenecks within the lifecycle

Aids analysis of portfolio balance

Fields

 

Group: One work dimension (project-level attribute - typically Lifecycle Stage) or time dimension by which to group the data in the visual

Note: if Lifecycle Stage is used, it is recommended that a numerical prefix is used for each of the values to ensure that they display in a logical order

Group: Lifecycle Stage
Values: One time-phased financial measure, PVE measure or count of a dimension, the data for which will be grouped by the attribute selected in the Group field Values: Count of Work ID
Color Saturation: One measure (generally the one used in the Values field) - this can be used to display a gradient of color Color Saturation: None
Formatting Suggestions Category Label: Adds the relevant category name to each column in the chart  Category Label: On (1. Initiation, 2. Scoping etc.)
Data Colors: Applies color-coding to the data groups Data Labels: All data groups = Green

Conversion Rate Label: Applies a conversion rate label to the top and bottom of the visualization which displays the highest and lowest values as percentages (the highest value always equals 100%, with the lowest value being the relevant % thereof) - this demonstrates the conversion rate between stages. 

Hovering over each column will provide further information on this - showing each column as a % of the first and also as a % of the previous column (i.e. the drop rate)

Conversion Rate Label: On
Title: Adds a title to the visualization Title: On ('Work by Lifecycle Stage')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Group, Values and Color Saturation fields will automatically appear as filter options 

Visual Level Filters: Lifecycle Stage, Count of Work ID
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-funnel-charts

 

 

Widget 4. Treemap showing Work by Strategies

FastTrack PowerBI Work Showcase - Tab 2, Widget 4.png
  Description Example
Goal

Illustrates numerical proportion

Each value of the chosen dimension is represented by a colored rectangle- the size of which is determined by the quantitative value being measured

Provides a count of projects in the selected portfolio/s by strategic objective / program

Business outcome: Aids analysis of portfolio balance

Fields Group: Work dimension (project-level attribute e.g. alternate structure) to group the data in the visual Group: Strategies
Details: A further work dimension which can be displayed as a sub-category Details: None

Value: Time-phased financial measure, PVE measure or a count of a dimension, the data for which will be grouped by the attributes chosen in the Group / Details fields

Value: Count of Work ID
Formatting Suggestions Data Colors: Applies color-coding to the data groups (rectangles) Data Colors: Different colors have been applied to each Strategic objective / program (e.g. Finance Deployment = Green, Test Tool Improvement = Red etc.) 
Data Labels: Adds data labels to each rectangle in the visualization Data Labels: Off
Category Labels: Adds the relevant category name to each rectangle in the Treemap Category Labels: On
Title: Adds a title to the visualization Title: On ('Strategic Program')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Group, Details and Value fields will automatically appear as filter options. 

Visual Level Filters: Strategies, Count of Work ID
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-treemaps

 

 

Widget 5. Multi-row Card showing Work by Internal Risk 

FastTrack PowerBI Work Showcase - Tab 2, Widget 5.png
  Description Example
Goal Displays multiple rows of data - one row of data is created for each combination of the different selected dimensions / measures

Provides a count of the projects in the selected portfolio/s by Internal Priority

Business Outcomes: Aids analysis of portfolio balance

Fields

Fields: Preferably one work dimension (e.g. Parent Name) or Time Dimension (e.g. Month Name)

One or more time-phased financial measure or PVE measure. A count of a dimension can also be used. 

Fields: Internal Priority, Count of Work ID
Formatting suggestions

Data Labels: Formats the data labels (color, font etc.)

 

Data Labels: Font and colors have been updated
Category Labels: Adds the relevant category name to each row in the card Category Labels: On
Card Title: Formats the title for each row Card Title: Fonts and colors have been updated
Title: Adds a title to the visualization Title: On ('Internal Risk')
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-big-number

 

 

Widget 6. Table displaying Detailed Information for Tab 2

FastTrack PowerBI Work Showcase - Tab 2, Widget 6.png
  Description Example
Goal

Tabular display of information

Sorting is available on all columns

Provides the detailed information behind each of the visualizations, breaking down the data by project. 

Allows the user to sort the data to better aid the analysis of portfolio balance and make informed decisions on next steps

Fields

Values: Combination of dimensions and measures 

Groups are automatically created based on the values of all selected dimensions. E.g. if the table contains Lifecycle Stage, Project Manager and Total Baseline Effort, there will be a row for each combination of Lifecycle Stage and Project Manager  

Values: EntityName, Work ID, Work Status, Project Manager, Lifecycle Stage, Overall Status Assessment, Internal Priority, Stategies

Formatting Suggestions General > Totals: Adds a row to the bottom of the table showing the totals for each column containing a measure General > Totals: Off
Conditional Formatting: Applies conditional formatting to those columns containing measures - useful for applying a color gradient for financial columns to easily identify the highest / lowest values Conditional Formatting: Applied to cost variance column (Highest value = Red, lowest value = Green)
Title: Adds a title to the visualization  Title: On ('Detailed Information')
Other formatting options: Select desired table style, format column headers, enable vertical and / or horizontal grid lines as needed, update other formats as necessary to improve the readability and impact of the visualization / to reflect a customer's branding Other formatting options: Formatting on column headers (blue background, white font)
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Values field will automatically appear as filter options. 

Visual Level Filters: EntityName, Work ID, Work Status, Project Manager, Lifecycle Stage, Overall Status Assessment, Internal Priority, Stategies
Microsoft Help (will open in new tab)

https://powerbi.microsoft.com/en-us/guided-learning/powerbi-service-tutorial-tables/

 

 

Tab 3 - Portfolio Balance Cost

FastTrack Power BI Work Showcase - Tab 3.png
 

 

Widget 1 - Slicer by Portfolio

FastTrack PowerBI Work Showcase - Tab 1, Widget 1.png
  Description Example
Goal Provides a visual element to filter the data on the page. Ability to slice data by Portfolio
Fields

Field: One work dimension (project-level attribute e.g. alternate structure, lifecycle role)

Field: Portfolio_Name
Formatting Suggestions Can be vertical or horizontal, Title can be added, multi-select option can be enabled Title: On (‘Portfolio’)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-slicers

 

 

Widget 2 - Stacked Column Chart showing Financial Details by Month

FastTrack PowerBI Work Showcase - Tab 3, Widget 2.png
  Description Example
Goal Use Case 1: Visualizes a single dimension with multiple measures 

Visualize the total costs per month (split by Capital, Expense & Labor) for the selected portfolio/s

Business outcome: understand the spend profile for each month

Ensure the costs are smoothed out across the planning horizon

Fields
 

Axis: Work dimension (project-level attribute e.g. alternate structure, lifecycle role) or time dimension (Year, Quarter, Month) to group the data in the visual

A further dimension can be added to facilitate drill-down (e.g. Quarter and Month)

Axis: Time Hierarchy (Year, Quarter, Month Description)

Value: Two or more time-phased financial measures or PVE measures (financial subtotal, calculated attribute, numeric field), the data for which will be grouped by the chosen dimension/s

Note: Time-phased financial measures must be chosen if a time dimension is selected in the Axis field 

Value: Total Capitalized Costs (FP FV), Total Expense Costs (FP FV), Total Labor Costs (FP FV)
Formatting Suggestions

Legend: Adds a legend to the visualization, providing a key for the different data groups

The position of the legend within the visualization can be changed if required

Legend: On

X Axis: Adds the category names to the X Axis based on the dimension chosen in the Axis field

Y Axis: Adds the value range to the Y Axis based on the measure chosen in the Value field

X Axis: On

Y Axis: On 

Data Colors: Applies color-coding to the data groups Data Colors: Total Capitalized Costs = Green, Total Expense Costs = Grey, Total Labor Costs = Red
Data Labels: Adds data labels to each column in the visualization Data Labels: On

Title: Adds a title to the visualization

The title is created automatically based on the data being displayed - it is often sensible to amend this to something more meaningful to the report audience

Title: On ('Financial Details')
Filters: 

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Axis and Value fields will automatically appear as filter options. 

Visual Level Filters: Year, Quarter, Month Description, Total Capitalized Costs (FP FV), Total Expense Costs (FP FV), Total Labor Costs (FP FV)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-basic-area-chart

 

 

Widget 3 - Treemap showing Total Costs at Complete and Actual Costs to Date by Strategies

FastTrack PowerBI Work Showcase - Tab 3, Widget 3.png
  Description Example
Goal Illustrates numerical proportion

Visualizes the proportion of total costs at complete and actual spend to date by strategic objective / program 

Business outcome: Aids analysis of portfolio balance by cost - ensures that investment costs are balanced across strategic initiatives  

Fields Group: Work dimension (project-level attribute e.g. alternate structure) to group the data in the visual Group: Strategies
Details: A further work dimension which can be displayed as a sub-category Details: None
Value: Time-phased financial measure, PVE measure or a count of a dimension, the data for which will be grouped by the attributes chosen in the Group / Details fields Value: Total Costs at Complete (FP FV), Actual Costs to Date (FP FV)

Tooltips: Can be used to display further information for each slice of data

This is useful when displaying financial data (e.g. if the chosen value is 'Total Costs at Complete' then Tooltips could be used to display 'Total Capitalized Costs', 'Total Expense Cost', Total Labor Costs)

Tooltips: None
Formatting Suggestions Data Colors: Applies color-coding to the data groups (rectangles) Data Colors: Different colors have been applied to each Strategic objective / program (e.g. Finance Deployment = Red, Test Tool Improvement = Yellow etc.) 
Data Labels: Adds data labels to each rectangle in the visualization Data Labels: Off
Category Labels: Adds the relevant category name to each rectangle in the Treemap Category Labels: On
Title: Adds a title to the visualization Title: On ('Total Costs at Complete and Actual Costs to Date by Strategies')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Group, Details and Value fields will automatically appear as filter options. 

Visual Level Filters: Strategies, Actual Costs to Date (FP FV), Total Costs at Complete (FP FV)
Microsoft Help (will open in new tab) https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-treemaps
 

 

Widget 4 - Donut Chart showing Actual Costs to Date by Department

FastTrack PowerBI Work Showcase - Tab 3, Widget 4.png
  Description Example
Goal Illustrates numerical proportion

Visualizes the proportion of actual spend to date by Department

Business Outcome: Aids the analysis of portfolio balance by cost - ensures that investment costs are balanced across departments

Fields Legend: Work dimension (project-level attribute e.g. alternate structure, Lifecycle role) to group the data in the visual Legend: Parent Description
Details: A further work dimension can be displayed as a sub-category Details: None
Values: Time-phased financial measure, PVE measure or count of a dimension, the data for which will be grouped by the chosen dimension/s Values: Actual Costs to Date (FP FV)
Formatting Suggestions Legend: Adds a legend to the visualization, providing a key for the different data groups

The position of the legend within the visualization can be changed if required

Legend: Off
Data Colors: Applies color-coding to the data groups Data Colors: Products = Red, Application Development = Green, Infrastructure = Grey
Detail Labels: Adds data labels to each slice in the visualization (label style can also be changed e.g. Category Name, Data Value, Percent of total etc.) Detail Labels: On, Style = Category, percent of total 
Title: Adds a title to the visualization Title: On ('Actual Costs to Date by Department')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Legend, Details and Value fields will automatically appear as filter options. 

Visual Level Filters: Parent Description, Actual Costs to Date (FP FV)
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-doughnut-charts

 

 

Widget 5. Table displaying Detailed Information for Tab 3

FastTrack PowerBI Work Showcase - Tab 3, Widget 5.png
  Description Example
Goal

Tabular display of information

Sorting is available on all columns

Provides the detailed information behind each of the visualizations, breaking down the data by project 

Highlights the projects with the highest Capitalized, Expense, Labor and Actual costs 

Fields

Values: Combination of dimensions and measures 

Groups are automatically created based on the values of all selected dimensions. E.g. if the table contains Lifecycle Stage, Project Manager and Total Baseline Effort, there will be a row for each combination of Lifecycle Stage and Project Manager  

Values: EntityName, Project Manager, Total Capitalized Costs (FP FV), Total Expense Costs (FP FV), Total Labor Costs (FP FV), Actual Costs to Date (FP FV)
Formatting Suggestions General > Totals: Adds a row to the bottom of the table showing the totals for each column containing a measure General > Totals: On
Conditional Formatting: Applies conditional formatting to those columns containing measures - useful for applying a color gradient for financial columns to easily identify the highest / lowest values Conditional Formatting: Applied to all columns containing measures (highest value = Red, lowest value = green)
Title: Adds a title to the visualization  Title: On ('Project Details')
Other formatting options: Select desired table style, format column headers, enable vertical and / or horizontal grid lines as needed, update other formats as necessary to improve the readability and impact of the visualization / to reflect a customer's branding Other formatting options: Formatting on column headers (blue background, white font), horizontal grid lines enabled
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Values field will automatically appear as filter options. 

Visual Level Filters: EntityName, Project Manager, Total Capitalized Costs (FP FV), Total Expense Costs (FP FV), Total Labor Costs (FP FV), Actual Costs to Date (FP FV)
Microsoft Help (will open in new tab)

https://powerbi.microsoft.com/en-us/guided-learning/powerbi-service-tutorial-tables/

 

 

Tabs 4 & 5 - Projects Overbudget & Projects Underbudget

FastTrack Power BI Work Showcase - Tab 4.png FastTrack Power BI Work Showcase - Tab 5.png
 

 

Widget 1. Slicer by Portfolio

FastTrack PowerBI Work Showcase - Tab 1, Widget 1.png
  Description Example
Goal Provides a visual element to filter the data on the page. Ability to slice data by Portfolio
Fields

Field: One work dimension (project-level attribute e.g. alternate structure, lifecycle role)

Field: Portfolio_Name
Formatting Suggestions Can be vertical or horizontal, Title can be added, multi-select option can be enabled Title: On (‘Portfolio’)
Microsoft Help (will open in new tab) https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-slicers
 

 

Widget 2 & 3. Cards showing Actual Costs & Baseline Costs

FastTrack PowerBI Work Showcase - Tab 4&5, Widget 2.png
  Description Example
Goal Displays the sum of the chosen measure, based on the filters selected

Widget 2: Shows the sum of the actual costs to date for those portfolios selected in the slicer, based on the current working versions of the financial plans

Widget 3: Shows the sum of the baseline costs for those portfolios selected in the slicer

Fields Fields: One time-phased financial measure or PVE measure (financial subtotal, calculated attribute, numerical field) that will be displayed as a single value based on the filters applied

Widget 2: Actual Costs to Date (FP FV)

Widget 3: Baseline Costs (FP BV)

Formatting Suggestions

Data Label: allows you to specify the display units (thousands, millions etc.) and the number of decimal places

These can also be defined automatically based on the data being display 

Both: On, Display - Auto
Category Label: this will automatically add the label for the measure being displayed (this will reflect the name of the financial subtotal / calculated attribute / field in PVE and cannot be updated) Both: Off

Title: adds a title to the visualization

It is recommended that this option is chosen over Category Label as the title can be re-named to something more meaningful to the report audience

Widget 2: On ('Actual Cost')

Widget 3: On ('Baseline Cost')

Other formatting options: apply border, background, fonts, colors etc.  Other formatting options: None applied
Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-big-number

 

 

Widget 4 - Stacked Column Chart showing the Top 10 Projects Overbudget / Underbudget

FastTrack PowerBI Work Showcase - Tab 4&5, Widget 4.png
  Description Example
Goal Visualize a single dimension with a single measure (this will produce the same result as a Clustered Bar Chart as only one dimension and one measure is in use)

Shows the top 10 projects over and under-budget. 

Business outcome: Highlights those projects that are due to exceed their baseline costs so that corrective action can take place

Highlights those projects that are due to fall short of their baseline costs, enabling decisions to be made re: cost re-distribution 

Fields

 
Axis: Work dimension (project-level attribute e.g. alternate structure, Lifecycle role). To show individual project information in this visualization, EntityName should be selected Axis: EntityName
Value: One time-phased financial measure or PVE measure (financial subtotal, calculated attribute, numerical field) Value: Cost Variance (FP FV-BV)

Tooltips: Can be used to display further information for each slice of data

This is useful when displaying financial data (e.g. if the chosen value is 'Total Costs at Complete' then Tooltips could be used to display 'Total Capitalized Costs', 'Total Expense Cost', Total Labor Costs)

Tooltips: Total Costs at Complete, Total Capitalized Costs (FP FV), Total Capitalized Costs (FP FV), Total Expense Costs (FP FV), Total Labor Costs (FP FV), Baseline Costs (FP BV)

Formatting Suggestions

X Axis: Adds the category names to the X Axis based on the dimension chosen in the Axis field

Y Axis: Adds the value range to the Y Axis based on the measure chosen in the Value field

X Axis: On

Y Axis: On

Data Colors: Applies color-coding to the data groups Data Colors: All columns are displaying as blue
Data Labels: Adds data labels to each column in the visualization Data Labels: Off
Title: Adds a title to the visualization Title: On ('Top 10 Projects Overbudget', 'Top 10 Projects Underbudget')
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual. 

The dimensions / measures added to the Axis, Legend and Value fields will automatically appear as filter options. If there are lots of categories to be displayed (i.e. if you are using EntityName as your dimension), filters can be applied to only show the top / bottom number of projects for the chosen measure 

Visual Level Filters: Cost Variance (FP FV-BV), Entity Name

A more detailed filter has been applied to Work Description: Filter Type = Top N, Show Items = Top / Bottom 10, By Value = Cost Variance (FP FV-BV)

Microsoft Help (will open in new tab)

https://docs.microsoft.com/en-us/power-bi/power-bi-visualization-basic-area-chart

 

 

Widget 5. Table displaying Detailed Information for Tabs 4 & 5

FastTrack PowerBI Work Showcase - Tab 4&5, Widget 5.png
  Description Example
Goal

Tabular display of information

Sorting is available on all columns

Provides the detailed information behind each of the visualizations, breaking down the data by project 
Fields

Values: Combination of dimensions and measures 

Groups are automatically created based on the values of all selected dimensions. E.g. if the table contains Lifecycle Stage, Project Manager and Total Baseline Effort, there will be a row for each combination of Lifecycle Stage and Project Manager  

Values: EntityName, Work Status, Project Manager, Lifecycle Stage, Internal Priority, Overall Status Assessment, Strategies, Actual Costs to Date (FP FV), Baseline Costs (FP BV), Cost Variance (FP FV-BV)
Formatting Suggestions General > Totals: Adds a row to the bottom of the table showing the totals for each column containing a measure General > Totals: On
Conditional Formatting: Applies conditional formatting to those columns containing measures - useful for applying a color gradient for financial columns to easily identify the highest / lowest values Conditional Formatting: Applied to all columns containing measures (highest value = Red, lowest value = green)
Title: Adds a title to the visualization  Title: On ('Detailed Information')
Other formatting options: Select desired table style, format column headers, enable vertical and / or horizontal grid lines as needed, update other formats as necessary to improve the readability and impact of the visualization / to reflect a customer's branding Other formatting options: Formatting on column headers (blue background, white font), horizontal grid lines enabled
Filters

Visual Level Filters: Filters that can be applied to the data in the individual visual.

The dimensions / measures added to the Values field will automatically appear as filter options. 

Visual Level Filters: EntityName, Work Status, Project Manager, Lifecycle Stage, Internal Priority, Overall Status Assessment, Strategies, Actual Costs to Date (FP FV), Baseline Costs (FP BV), Cost Variance (FP FV-BV)
Microsoft Help (will open in new tab)

https://powerbi.microsoft.com/en-us/guided-learning/powerbi-service-tutorial-tables/