RE-CALCULATES SCHEDULED DATES / DURATIONS relevant to the configured/selected options

 Back to Understanding the Progressing Engine

After having determined the remaining effort for each resource assignment, the Progressing Engine will then determine the Schedule Start and Finish Dates for the remaining effort on each assignment and work item.

Sign in to access this topic. 

The Schedule Start and Schedule Finish dates are the dates planned for remaining work to be completed. For further information on the differences between Schedule and Actual Dates refer to the Schedule vs. Actual Dates and Durations topic.