7.1p
This document describes the enhancements, corrected issues and new features which have been implemented in ProjectAdvantage 7.1p either in the Core product and in the ProjectAdvantage Default Configuration.
ProjectAdvantage 7.1p is a maintenance release of ProjectAdvantage 7.1.
In the Core product, 4 enhancements have been implemented, and 7 issues have been fixed.
In the ProjectAdvantage Default Configuration, 7 enhancements have been provided and 24 issues have been fixed.
Note: Items with nearly identical features are indicated by an asterisk. For instance, if an issue has been corrected for the Project* Center workspace, it means that the correction has been implemented in the Project Center, Business Case Center, Product Center, Program Center, and Template Center workspaces.
In order to access to the different sections, please click on the following links:
Important Reminders for upgrade
Default Configuration Enhancements
Default Configuration Corrected Issues
Important Reminders for upgrade
- Looking forward to strengthening our Unique Technology Stack, we have decided to focus our quality, testing and support to the English version of Tomcat exclusively. While ProjectAdvantage will continue to work on non-English versions of Tomcat, we will no longer test those versions nor offer support in case issues occur. This decision is transparent for SNet and SVA users. IT departments that have deployed ProjectAdvantage on premise using a non-English version of Tomcat are invited to use an English version.
- Config Utility Backup files (CUB zip files) are used as a means to backup a customer's databases into a .zip file so that it could be restored on another system regardless of the database vendor used in the source and target systems. Since January 1st, 2018 ProjectAdvantage exclusively supports Postgres SQL databases and therefore the need for having a capability to exchange data across different database vendors is no longer needed. As a consequence the CUB export capability is now deprecated, it will continue to work but will be removed in a future release. The CUB import capability will continue to be supported as it is a means to “import” databases from customers that are not currently using Postgres.
Core Product Enhancements
Commands
#41603
The Link command now supports linking to a workspace not listed in the appbar. When the link is followed, the workspace will open in a full screen mode on top of the workspace where the Link command was executed.
The newly opened workspace can be closed using the browser’s ‘back’ button or by using a Link command back to the original workspace.
Designer
#40556
There is a new Scheduled Job called “Update UDB Project Reference Field” and, when run, it updates the values (in the User Data Block) of the “managed” Project reference fields for all records in the specified Data Views. This new Scheduled Job was created solely to help users convert Project Data Views into Global Data Views. The Scheduled Job will run automatically when a user converts a Project Data View into a Global Data View, either by manually editing a Project Data View (in the Data View Definition view in the Designer) or by importing a CFG file that updates an existing Project Data View.
When manually editing a Project Data View in the Data View Definition, the
scheduled job will run upon saving the modified Data Views if:
- The Project Data View existed at the moment the user goes into design mode.
- The “Parent category” of the Project Data View is changed to Global.
- A “managed” Project reference field is added to the Data View definition.
Normally, the user will likely:
- Want to keep the Data View “Table name” the same (any other table will typically not have the right data in it)
- Want to keep the “Name” of the Data View the same (so that existing forms that refer to the Data View will continue to work even after export/import)
- Want to answer “No” when asked whether to drop the table because there were primary key modifications (answering “Yes” will drop the table and there will be no records to update).
When importing a CFG file, the scheduled job will run if:
- An existing Project Data View is updated into a Data View whose “Parent category” is Global and has a “managed” Project reference field.
- The user selects the “Update” option in the “Duplicate Data View Options” section (only necessary If not importing/upgrading a Collection).
The status of the “Update UDB Project Reference Field” scheduled job can be viewed in the Scheduled Jobs view of the Designer. Under normal circumstances, this job should not run manually, but if some problem occurs it can be run manually.
Performance
#41597
Many operations in the Resource Management/Commitments workspace can be slow if the customer has thousands of Resource Requests and corresponding data view records (data view records whose “Parent category” is Resource Request). Performance has been improved for some of the typical operations in that workspace.
Scripts/API
#41481
A new method in the Session.java class allows an API program to clear User Defined Category data based on the table name in the database. This new method “clearUserDefinedCategoryCacheWithTableName(String tableName)” should be called from an API program after a data for a User Defined Category is inserted directly to the database. If this method is called, the data that was inserted to the database will be visible in the HTML5 Client immediately.
Core Product Corrected Issues
Commands
#41069
When a user tried to undo changes for a project that was locked in a different
session, they were shown an incorrect error message that stated that the object
was not exclusively locked for editing. This has been fixed.
The users were shown a new error message that stated: “You are attempting to Undo or Redo changes across different sessions. Return to the session where the object was originally locked, or unlock and relock the object in this session. WARNING: This will commit all tracked changes.”In addition to this new error message, there were new behaviors as well.
When a user simply makes an edit to a Project that was locked in a different session, a warning message (with some options) will be shown. A message at the top of the dialog will appear to inform the user: “You are editing a locked project across different sessions. Changes you made will still take effect, but you may not be able to undo them individually.”
The new options that are part of this dialog are: 1) “Continue editing” and 2) “Fully commit current changes and track new changes in the current session.” Option 1 also has a checkbox sub-option that says: “Don't show this message again for this project during this session.”
If the user selects option 1 without checking the “Don't show this message again” sub-option, the edits will take place and subsequent edits to the project will also show this warning. If the sub-option “Don't show…” is selected, this dialog will no longer be shown to the user for that project (for the duration of the session). Other projects that are similarly locked from other sessions will still show the warning message, as well as edits to the same project from a 3rd session.
Selecting option 2 will clear out all previous tracked changes for that project and will start a new UndoStack beginning with the change that was just made. Attempts to undo/redo changes from the original session will result in the error message described above.
Additionally, since we do not support Undo/Redo across different sessions, when a session was terminated (either through a logout or a timeout) all changes that were being tracked for projects (that were locked within those sessions) will be cleared and the projects will be committed as they are at the time the session was terminated.
Designer
#41581
If a command has a command group in the command list, and any of the commands in the conditional group has a condition which references a field, then after the Designer was restarted, the field’s alias would not be recognized. This has been fixed.
Field Edits (Field Types)
#41247
Images taken with an iPad or tablet were being incorrectly rotated when uploaded. This has been fixed.
Localization
#41521
In French and Spanish language, issues could occur when creating formulas and filters using Field Data Operators or Field Boolean Data (as some of their translation were the same). Indeed, in Spanish, “if” and “yes” were translated as “si”. In French, “not” and “no” were translated as “non”. To fix this and avoid future issues, “if” will no longer be translated in Spanish and “not” will no longer be translated in Spanish and French.
Object Edits (Data Categories)
#41265
In a multi-server installation (load balancing), users served by one server (e.g. “server #1”) sometimes continued to see the previous version of the data after that data was changed by another user that is being served by a different server (e.g. “server #2”). Once this happened, all users being served by “server #1” would see data from the previous version of the project. However, once the project was modified again (by any user on any server), it was likely that all users on all servers would see the most recent version of the project data. This has been fixed.
#41454
The “[All]” Global reference field for a hierarchical Data View was not looping through all the records in that Data View. Instead, it was only looping through the top level records. This has been fixed.
Note: The name of the “[All]” Global reference field includes the name of the Data View Definition. For example, if the Data View Definition was named “Budget Items” then the Global reference field would be named “[All Budget Items]”.
Performance
#41412
Memory leaks were discovered in some Project and Task related internal data structures. These have been fixed.
Default Configuration Enhancements
Budget & Cost
This release has been the opportunity to redesign most of the views and screens involved in managing the project finances:
- Macro-estimation: Easily estimate potential project cost and keep track of project ETC
- Budget Automation: Roll-out automatically project cost and budget at the portfolio level
- Financial Snapshots: Build an audit trail of the evolution of the project cost, budget, forecast, and savings
- Improved User Interface throughout the financial views
Tickets that have been resolved with the Budget & Cost rework
| Jira Ticket # | Description |
|---|---|
| MW-2872 | Enhance the relationship between Cost Centers at the Portfolio and Project levels |
| MW-2821 | Add a Time Navigation toolbar to the Portfolio Ranking workspace |
| MW-2028 | Allow users to compare Budget snapshots |
| MW-2025 | Show Actuals and Remaining in Project* Budget and Portfolio Controlling Dashboards |
| MW-1794 | Support the Cost Centers at the Labor Assignment level |
| MW-1754 | Improve the UX of the Project* Budget workspace |
| MW-1520 | Provide a Cost Center column in the Cost Transactions grid |
| MW-1435 | Add a Custom tab in the Project* Finance workspace |
| MW-1434 | Remove the possibility to add several times the same Cost Center for a same Portfolio or Project |
| MW-1345 | Add the ability to capture the state of the Project Adjusted Cost |
| MW-1321 | Enhance the Budget tab at the Program level (especially regarding Contracts) |
| MW-1179 | Display the whole project* time frame in the Budget Overview chart |
| MW-1172 | Clarify Budget vocabulary in the Budget Dashboards |
| MW-1156 | Filter the Cost Centers assignable at the Task level so that only the corresponding project Cost Centers are available |
| MW-1138 | Provide options to add multiple Cost Centers at a time in the Project* Finance workspace |
| MW-1104 | Provide options to import projects Budget at the Portfolio level |
| MW-1101 | Display the Total Direct and Indirect Budget for the entire project |
| MW-1100 | Add the Cost Transactions in the Project* Finance workspace, Costs tab |
| MW-344 | Add a chart to compare the Budget and Cost by Cost Center in the Project* Finance workspace, Costs tab |
| MW-294 | Add a summary section in the Project* Finance workspace, Budget tab |
Milestone Monitoring (Milestone Trend Analysis)
In a project plan, milestones always represent something important: a delivery date, a product gate, a customer meeting, etc. For this reason, Project Managers need to be aware of project milestone slippage, visualize the impact over time, and follow the evolution of my project milestone dates throughout my project lifecycle.
Our new Milestone Monitoring feature and its famous diagram (Milestone Trend Analysis) will help Project Managers keep track of their milestones.
#MW-1471
In order to support the Milestone Trend Analysis chart, we introduced the Milestone Monitoring feature. It consists in identifying the Monitored Milestones, that may then be captured and tracked.
The user will have the opportunity to review these Monitored Milestone snapshots with the Milestone Trend Analysis chart. Milestones planned dates are plotted on the vertical axis against the respective project reporting dates. Each milestone is represented as a Trendline in the chart. Deviations from the planned schedule can then be analyzed as follows:
- If the project runs according to plan, the milestone trendline remains horizontal.
- If the project runs late, the milestone trendline rises.
- If the project is ahead of time, the milestone trendline goes down.
To manage this feature properly, the following has been added:
- In the main toolbar of the Project* Scheduler workspace and the Key Facts section of the Project* Center workspace, the Manage Monitored Milestone command has been added, allowing the user to access the Milestone Monitoring dialog box.
- A new Status Report Preference has been added to include the MTA chart in a Status Report
- New Milestone Trend Analysis Dashboards have been provided, both at the Project* and Portfolio level.
- A set of new Settings has been added in the System Settings workspace, Project Settings folder, Global Options tab to manage the Milestone Monitoring feature options and availability.
General
#MW-3071
Overall Optimization has been done by implementing the Conditional Group Function.
Project*
#MW-3107
In the System Settings workspace, Project Settings folder, Project Scheduler - Roadmap section, when the “Enable Roadmap” setting is activated, the new “Enable Project Center Outcome” setting is displayed, allowing the user to control whether the Outcome section should be displayed in the Project* Center workspace, Definition tab. In addition, this new setting provides an “Enabled Natures” option, allowing the user to define which project Natures should feature this section.
Note: As part of this change, the sub-section "Phases & Gates" of the Definition tab has been moved to the "Other Attributes" section.
#MW-2677
In the Gantt Filters dialog box, there is now a new "Task Chain" filtering option, allowing the user to only display, for a selected Task, the Tasks that belong to the chain of predecessors, successors, or both.
#MW-2547
In the Project* Dashboards workspace, Performance report, a new view mode named “Effort Distribution” has been added. This view is composed of:
- A Task spreadsheet with the time distributed Effort, depending on the selection of the “Effort Values” option.
- A chart displaying the Total Effort and the Baseline values, in a time distributed way (histogram) and cumulative way (series).
In addition, the Time Navigation toolbar is also provided, allowing the user to modify the displayed time period and intervals.
#MW-3107
In the Project Scheduler workspace, Tracking tab, a new "Approve & Apply" command is now available. This command can behave differently depending on the option chosen by the Administrator in the System Settings workspace, Project Settings folder, Time Tracking Options tab.
Administration
#MW-3026
In the System Data workspace, News Page tab, a new "Show Closed" display option is now available. This option allows the user to display or not the Activity Stream notifications and the News Feed articles in the corresponding views.
Default Configuration Corrected Issues
Project*
#MW-3121
In the Project* Brief dialog box, Connections tab, it was not possible to review the content of a Project or Work Package Contract. This issue has been fixed.
Note: To accommodate this need, the former "Contract" buttons have been replaced by a new icon on the right-hand side of the cards. The icon will be blue when a Contract is available and will then be clickable to bring a new popup with the content of the Contract.
#MW-3044
In the Project* Scheduler workspace, Dependencies tab, after a dependency Source was purged, the user could no longer delete the link of the dependency, nor set a new link for the remaining object. This issue has been fixed.
#MW-3023
In the Project* Center workspace, Definition tab, when the project was using the Phases & Gates methodology, the Current Phase value in the Key Fact section was always "N/A". This issue has been fixed.
#MW-3014
In the Project* Scheduler workspace, Roadmap tab, Gate Review view mode, History dialog box, the "Delete" (
) command was not removing the selected gate review. This issue has been fixed.
#MW-3011
In Gate Review Report, Phases & Gates section, the task OTD status colors were not the right ones. This issue has been fixed.
#MW-2964
In the Project* Scheduler workspace, Roadmap tab, Phases/Gates view mode, when a Gate was a parent task, an error message was displayed upon approving it. This was due to the fact that the system was trying to update the % Completed field. This issue has been fixed; from now on, the % Completed will not be updated for parent tasks.
#MW-2963
In the Project* Scheduler workspace, Roadmap tab, Deliverables view mode, when creating or editing a Deliverable, in the Task list popup available upon selecting the "Related to Task" or "Related Gate" fields, the Tasks were not sorted in the same order as in the Gantt view. This issue has been fixed.
Note: This fix has also been applied to the "Define Related Gate" command in the Roadmap tab, Deliverables view mode, and in the Deliverable creation and edition views of Project* Work Management workspace, Work Items tab.
#MW-2883
When creating a Project From Template, if a task was previously selected on another project, the template could be imported in the wrong project. This issue has been fixed.
Resource
#MW-3104
In the Project* Resources workspace, Resource Allocations tab, the Build Allocation Requests (
) command did not take into account the "Closed" attribute. As a consequence, the Closed Allocation Requests could be updated upon using the Build command. This issue has been fixed; from now on, Closed Requests will no longer be taken into account during the "Build" process.
#MW-3098
In the Resource Dashboards workspace, Resource Utilization report, when using the Resources filtering option, the spreadsheet was still displaying all the Job Classifications. This issue has been fixed; from now on, only the Job Classification of the selected resource will be displayed.
#MW-3074
In the Resource Dashboards workspace, when the Display Resources option was set to "With Effort in Period" or “Without Effort in Period”, in some cases, the Total Available Effort displayed did not correspond to the sum of the displayed resources Available Effort. This issue has been fixed.
#MW-3070
In the Resource Commitments workspace, Grid view mode, when changing the time interval to "Year" or “Quarter”, the time distributed columns were not displayed properly. This issue has been fixed.
#MW-3062
In the Resource Allocations workspace, Soft Allocations tab, when fulfilling a soft allocation, in the Fulfill Soft Allocation dialog box, scrollbars could appear on the "Done" button. This issue has been fixed.
#MW-3061
In the Resource Allocation workspace, Soft Allocations tab, when editing a soft allocation, the Organization, Job Classification, and Skills were read-only while they should have been editable. This issue has been fixed.
Portfolio
#MW-3151
In the Portfolio Dashboards workspace, Status Overview report, Details view mode, Planning sub-tab, the Tasks list was not displayed properly. This issue has been fixed.
Note: This fix has also been applied to the Project Status Overview report in the Program and Product Consolidation Dashboards.
#MW-3100
In the Portfolio Simulation workspace, Analytics view mode, Workload sub-tab, when grouping by Resources, the Available Effort was not properly taken into account, which caused the display of invalid colored indicator. This issue has been fixed.
#MW-3095
In the Portfolio Center workspace, the Custom tab position was not correct. This issue has been fixed.
#MW-3042
In the Portfolio Dashboards workspace, Performance tab, the Max Record message could be displayed (indicating that the maximum number of objects displayed by the view has been exceeded), even when fewer projects were shown. This issue has been fixed.
#MW-3040
In the Portfolio Dashboards workspace, Phases & Gates report, upon accessing the Gate Brief dialog box, in some cases, the Deliverables were not displayed. This issue has been fixed.
#MW-3010
In the Portfolio Dashboards workspace, Status Overview tab, Overview view mode, when only Gate Reviews had been created, the Status Report indicators were not displayed. This issue has been fixed; from now on, the Status Report indicators values will take into account the last created Status Report or Gate Review.
Work Package
#MW-3069
In the Work Package Center workspace, in the Notes dialog box, the "Mark all as read" and "Mark all as unread" functions were not available. This issue has been fixed.
#MW-3068
In the Work Package Center workspace, in the Notes dialog box, the notes were marked as unread instead of being marked as read. This issue has been fixed.
Work Management
#MW-3066
In the Project* Work Management workspace, Work Items tab, when opening the Notes dialog box for Deliverables, the “Mark as Unread” label was green instead of grey. This issue has been fixed.
#MW-2973
When creating or editing Deliverables, the modification of the Related to Task and Related Gate fields has been enhanced as follows to avoid emptying the fields by mistake:
- When clicking on the Pen (
) button to update the “Related to Task” field, if a related to task has already been defined the task is selected by default in the prompted Task list. - When clicking on the Pen (
) button to update the “Related Gate” field, if a related gate has already been defined, the task is selected by default in the prompted Task list. - If the defined “Related to Task” is a Gate, the Pen button to update “Related Gate” field will no longer be available.
In the Project* Scheduler workspace, Roadmap tab, Deliverables view mode, the “Define Related Gate” command has also been enhanced as follows:
- If the selected Deliverables have the same value in their respective “Related Gate” fields, the corresponding task will be selected by default in the prompted Task list.
- When updating the “Related Gate” field, the value of the “Related to Task” field will be updated as well if “Related to Task” is a Gate.
Note: A Clear () icon has also been added on the right-hand side of the “Related to Task” and “Related Gate” fields, allowing the user to clear the value.