Skip to main content

 

  • arrow icon

 

Planview Customer Success Center

7.1o

This document describes the enhancements, corrected issues and new features which have been implemented in ProjectAdvantage 7.1o either in the Core product and in the ProjectAdvantage Default Configuration.

ProjectAdvantage 7.1o is a maintenance release of ProjectAdvantage 7.1.

In the Core product, 2 enhancements have been implemented, and 15 issues have been fixed.

In the ProjectAdvantage Default Configuration, 14 enhancements have been provided and 17 issues have been fixed.

Note: Items with nearly identical features are indicated by an asterisk. For instance, if an issue has been corrected for the Project* Center workspace, it means that the correction has been implemented in the Project Center, Business Case Center, Product Center, Program Center, and Template Center workspaces.

In order to access to the different sections, please click on the following links:

Important Reminders for upgrade

Core Product Enhancements

Core Product Corrected Issues

Default Configuration Enhancements

Default Configuration Corrected Issues

Important Reminders for upgrade

  • Looking forward to strengthening our Unique Technology Stack, we have decided to focus our quality, testing and support to the English version of Tomcat exclusively. While ProjectAdvantage will continue to work on non-English versions of Tomcat, we will no longer test those versions nor offer support in case issues occur. This decision is transparent for SNet and SVA users. IT departments that have deployed ProjectAdvantage on premise using a non-English version of Tomcat are invited to use an English version.
  • Config Utility Backup files (CUB zip files) are used as a means to backup a customer's databases into a .zip file so that it could be restored on another system regardless of the database vendor used in the source and target systems. Since January 1st, 2018 ProjectAdvantage exclusively supports Postgres SQL databases and therefore the need for having a capability to exchange data across different database vendors is no longer needed. As a consequence the CUB export capability is now deprecated, it will continue to work but will be removed in a future release. The CUB import capability will continue to be supported as it is a means to “import” databases from customers that are not currently using Postgres.

Core Product Enhancements

Object Edits (Data Categories)

#41345

The Baseline Date and Baseline Cost fields (in the Transaction category) are now editable given that “Include As Cost” field in the Transaction is set to yes and the user has “Write Baseline” permission on the project/work package. Additionally, the logged-in user needs to have “Write Cost” permission to edit the Baseline Cost fields.

Performance

#41442

There is a new command in the System category, called “Conditional Group”. It was noticed across several configurations that there were groups of commands within command lists, that had execution conditions that were mutually exclusive. This means that only one of these commands would be executed during any given run of the command list, but every command needed to make a request to the server to determine whether or not its execution condition was met.

To address this, the new “Conditional Group” command will only require one request to the server (to determine which of the commands in the command list with mutually exclusive conditions) and then execute a command without needing an additional server request.

For example, commands that are able to operate entirely on the server (such as Set Field Values and Calendar Submit), as well as commands that operate entirely on the client (such as Flash Message, Close Popup, and HTML Scriptlet) will be able to execute without the need for an additional request to the server.

One notable exception to this are Named Command Lists, which are marked to execute entirely on the server. These server-side only command lists will still operate entirely on the server, but the “Conditional Group” command will not be able to begin that execution directly on the server; instead it will return to the client before making a separate request to execute on the server.

Those commands that require a mix of Client-Side user interaction and Server-Side execution (such as Auto-Reset Password and Clear Locks) will still require their normal requests. This means that the number of requests for each Conditional Group may still be two or more (depending on the command).

Since this command intended to reduce the number of server calls for those commands in the command list that have mutually exclusive conditions on them, the first command with a filter that evaluated to be true will be executed. Due to this short-circuit evaluation, only one command will be executed. For example, if you have two commands listed in the group that both have the condition “Counter = 1”, only the first command in the group (starting from the top) will be executed (if Counter is equal to 1).

If blank conditions were evaluated to be true, the default command can be the last command in the list that will be evaluated (if other conditions are not met). Also, the command at the top of the list (with no condition) will always be executed regardless if any of the conditions in the group are met.

However, one limitation of this command is that, it will not be available for use on the Server Side Only Command Lists.

1-43_img_0.png

1-43_img_1.png

Core Product Corrected Issues

Commands

#41387

The Filter specified in a Generate View Scheduled Job was not taken into account when the type of the Generate View was a Global Dataview. Also, if a Generate View Schedule Job contained a Dataview Definition where the Parent Category was Global or the parent category was another Dataview, the type was not being displayed correctly when the Generate View Schedule Job was brought up while not in design mode. Both of these problems have been fixed.

#41333

When an imported XML file failed due to fields or objects were locked by another user, the XML file import would be aborted but no message would be communicated or displayed to the user. This has been fixed.

Designer

#41503

The Clear tables Action in a Schedule Job that has a global dataviews does not

clear the table. This has been fixed.

#41455

If a cfg that contained a command list and a command with a condition which used a field from a data view in the formula was imported, the condition on the command list disappeared. This has been fixed.

#41235

FieldSet overwrites would not be applied for languages other than the language set upon log in. This has been fixed.

Field Edits (Field Types)

#41467

When many users were logged in at the same time, it was possible that fields with non-blank permissions (Permissions column of the Fields view in the Designer) were calculated incorrectly. This has been fixed.

#41060

In the HTML5 Client, cells with hamburger buttons that should appear as read-only did not appear as read-only. This has been fixed.

#41289

In 7.1m, a bug was found that caused a “StackOverflowException” error when a dated text field was selected in a grid (Organization History field for User category) or when directly entered in a form as a text field (on its own). This has been fixed.

#41138

It was not possible to create a Transaction Type in the Designer when “Include as Cost” was chosen in the Target field and Data field was set to off. This has been fixed.

Scripts/API

#40883

The API retrieved an incorrect data from a project data view while retrieving a formula field (which had a reference field). This has been fixed.

#41172

When a resource or project based data view was updated via API, the changes made were not visible in the HTML5 client. This has been fixed.

UI Blocks

#41058

In the Designer, if the user enabled auto-size for a grid but gave the column widths low values (below 10), then the selection column for that grid in the HTML5 client was too large. This has been fixed.

#39301

In the Time Axis panel of the Gantt editor in the Designer, if the user edit the column width and immediately clicked the “OK” button to accept, the user input was not accepted. This has been fixed.

#41425

Keyboard navigation was not working for Grids and Gantt Grids in rows beyond row #100. This has been fixed.

#41076

In some fields (e.g. Resource.Availability), an “Unexpected Exception - (TypeError)” error occurred when data was entered and the <TAB> key was used to advance to the next cell. This happened while using the Internet Explorer browser. This has been fixed.

Default Configuration Enhancements

Project*

#MW-2990

In the Project* Scheduler and Project* Work Management workspaces, using the Data Selector, it is now possible to select multiple Portfolio Folders and drill-down to the list of the projects they contain to select multiple projects (previously it was only possible to select one Portfolio Folder at a time).

#MW-2870

In the Project* Scheduler workspace, Billing tab, Purchase Orders mode, Billing Rates sub-tab (for a selected purchase order), a new "Initiate" command is now available when the Project Revenue Rate is set to "Project.Job Classification". This command allows the user to automatically fill in the Billing Rates spreadsheet depending on the option selected:

  • Purchase Order: Allows the user to copy the Job Classification Rates from another Purchase Order.
  • Project Revenue Rate: Allows the user to copy the Job Classification Rates from the project.

General

#MW-2377

A new News Page workspace has been created, which displays articles, notifications, and alerts provided by the Administrator.

The Administrator can manage what is to be displayed in the News Page workspace in the System Data workspace, News Page tab.

1-43_img_2.png

#MW-1314

Across the application, depending on the context, a new "Presets" (1-43_img_3.png) button is available in the Time Navigation toolbar, allowing the user to directly set the displayed timeframe as follows:

Selected Preset ValueTimeframe Displayed
Current YearDisplays the current year in months, from January to December.
(Intervals: Month; Number of Intervals: 12)
Current QuarterDisplays the current quarter in months.
(Intervals: Week; Number of Intervals: 12)
Current WeekDisplays all the current week in days.
(Intervals: Day; Number of Intervals: 7)
6 Months from Project StartDisplays the next six months after the selected project’s Start date.
(Intervals: Month; Number of Intervals: 6)
6 Quarters from Project StartDisplays the next six quarters after the selected project’s Start date.
(Intervals: Quarter; Number of Intervals: 6)
6 Years from Project StartDisplays the next six years after the selected project’s Start date.
(Intervals: Year; Number of Intervals: 6)
6 Months from nowDisplays the next six months from the beginning of the current month.
(Intervals: Month; Number of Intervals: 6)
6 Quarters from nowDisplays the next six quarters from the beginning of the current quarter.
(Intervals: Quarter; Number of Intervals: 6)
6 Years from nowDisplays the next six years from the beginning of the current year.
(Intervals: Year; Number of Intervals: 6)
Note: The options available differ from one view to another.

Resource

#MW-2980

In the Resource Dashboards workspace, Resource Utilization tab, the Soft Assignments of the selected Organizations associated to Job Classifications that are not available in the Organization will now be displayed (assuming the Soft Assignments filter has been enabled).

#MW-2851

In the Resource Dashboards workspace, Time Tracking Statistics tab, a new "Show Non-Project" option has been added to allow users to define whether the Actual Effort entered on the Non-Project Tasks should be considered or not.

#MW-2807

In the Resource Allocations workspace, Hard Allocations tab, when filtering the spreadsheet on Projects, it could be difficult to resolve over-allocations without seeing all the allocations of the resources. A new "All Allocations" display option has been added to allow the user to see all the allocations of the resources corresponding to the filter (when activated).

#MW-2806

In the Resource Allocations workspace, Hard Allocations tab, the new "New Hard Allocations" command allows the user to create multiple Hard Allocations at once for a selected project.

#MW-2799

In the Resource Allocations workspace, Hard Allocations tab, a Resource Manager is now able to create an allocation, even if he/she does not have Write permissions on the corresponding Project.

#MW-2164

In the Resource Validation workspace, Timesheets tab, Overview and Details view modes, the user can now select multiple values in the Status filtering field.

#MW-1836

In the Resource Dashboards workspace, Resource Utilization and Cost Items Utilization tabs, the "Show Business Case" filtering option (available in the Filters popup) has been replaced by a new filter supporting all the available project Natures.

Portfolio

#MW-2879

In the Portfolio Simulation workspace, Analytics view mode, Workload sub-tab, the user has now the ability to group the spreadsheet by Resources.

#MW-2874

In the Portfolio Dashboards workspace, Status Overview tab, new filters are now available to filter the view according to the Status Report indicators (Cost, Time, Scope, Trend, Additionals).

The user will be able to choose the combination rule:

  • AND – When selecting filters from several categories, only projects with the selected combination of indicators will be displayed.
  • OR – When selecting filters from several categories, all projects showing at least one of the selected indicators will be displayed.

Administration

#MW-2448

In the System Settings workspace, from now on, all Custom tabs and tabs-related settings will come with the corresponding "Enabled User Roles" field.

For consistency purposes, the following settings have been modified as well:

  • “Enable Project Center Custom Tab for” became “Enable Project Center Custom Tab”
  • “Enable Scheduler Custom Tab for” became “Enable Scheduler Custom Tab”
  • “Enable Dashboard Custom Tab for” became “Enable Dashboard Custom Tab”
  • “Enable Consolidation Dashboards Custom Tab for” became “Enable Consolidation Dashboards Custom Tab”
Important: Those four settings MUST be updated by the ProjectAdvantage Administrator. Otherwise, the corresponding tabs will no longer be displayed after the 7.1o release.

Default Configuration Corrected Issues

Project*

#MW-3021

In the Project Scheduler workspace, Planner tab, Task Details dialog box, Deliverables sub-tab, if two tasks had the same name, the Deliverables from both Tasks could be merged together. This issue has been fixed.

#MW-2965

In the Project* Scheduler workspace, Roadmap tab, Deliverables view mode, the "Show Only" filters were not working properly when combined. This issue has been fixed.

#MW-2938

The Total Revenues field was not taking into account the Billable Amount of the Tasks whose Billing Date was after Project Finish date. This issue has been fixed.

#MW-2928

In the Project Dashboards workspace, Project Dashboard tab, the title for the "Planning" section was not aligned with the printed version which displayed "Macro-Planning". This issue has been fixed.

#MW-2898

In the Project* Scheduler workspace, Dependencies tab, in some conditions, when a project had been purged, an empty dependency was still displayed. This issue has been fixed.

#MW-2832

In the Project* Resources workspace, Resource Requests tab, Inbox view mode, an error message could be displayed when the Project Manager accepted a request submitted by the Resource Manager. This issue occurred when the request was based on a task belonging to a Work Package as the resource could not be added to the Performing Resources. This issue has been fixed; from now on, any resource belonging to the Work Package Project Team will necessarily belong to the corresponding project Project Team as well.

#MW-2777

In the Project Creation dialog box, the "Use Agile Methodology" switch button could still appear even though the “Activate Agile” meta-setting was deactivated. This issue has been fixed.

General

#MW-2884

In the Notes dialog box, in some cases, the "Mark as Read" and "Mark as Unread" labels were displaying the wrong color. This issue has been fixed.

Note: The Notes dialog boxes related to Backlog Items, Actions, Change Requests, Deliverables, Issues, Work Packages, Resource Allocations, Project Idea, Project Allocations Requests, and Projects have been updated accordingly.

Resource

#MW-2935

In the Resource Allocations workspace, Hard Allocations tab, the colored indicators' tooltips were not aligned with the legend. This issue has been fixed.

Portfolio

#MW-3035

In the Portfolio Center, Supervision tab, the Status Report Indicator did not take into account the Trend value at all. This issue has been fixed; from now on, the system will take into account the descending Trend.

#MW-2957

In the Portfolio Dashboards workspace, Controlling tab, when the user just logged-in, the "Cost Values" or "Effort Values" display options could be empty. This issue has been fixed; the "Total" values are now displayed by default.

#MW-2894

In the Portfolio Dashboards workspace, Status Overview tab, Overview view mode, the More (1-43_img_4.png) button (located in the top right corner of the card) was not appearing, which prevented the user from accessing the project Status Report History dialog box. This issue has been fixed.

Agile

#MW-2914

In the Iteration dialog box, Backlog Items sub-tab, an inaccurate empty state message was displayed when no Backlog Item was attached to the Iteration. This issue has been fixed.

#MW-2793

When logged-in in any language other than English, in the Iteration workspace, Task Board tab and in the Agile workspace, in the swimlane, a Backlog Item Task could disappear after changing its Workflow State. This issue has been fixed.

Work Package

#MW-3005

In the Work Package Scheduler workspace, when the Performing Resources field was empty at the Work Package level, it was not possible to assign any Resource. This issue has been fixed; from now on, in this case, ProjectAdvantage will take into account the Performing Resources at the Project level.

Note: The same issue has been fixed for Work Package Cost Items.

#MW-2934

In the Work Package Scheduler workspace, when assigning a Resource or a Cost Item using the corresponding dialog boxes, it was possible to manage the Project Team. This issue has been fixed.

#MW-2283

In the Work Package Center workspace, the fields could display information regarding another task of the Work Package instead of the Work Package itself. This issue has been fixed.