This document describes the enhancements, corrected issues, and new features that have been implemented in ProjectAdvantage 2020.08 both in the Core product and in the ProjectAdvantage Default Configuration.

ProjectAdvantage 2020.08 is a maintenance release of ProjectAdvantage 2020.

In the Core product, 4 enhancements have been implemented and 28 issues have been fixed.

In the ProjectAdvantage Default Configuration, 18 enhancements have been provided and 48 issues have been fixed.

In order to access the different sections, please click on the following links:

Important Reminders for upgrade

Since 7.1q there is a new way of managing languages in ProjectAdvantage thanks to the Language Packs feature. As a result of this new feature there is a change in the classpath used to launch API programs: we no longer have PSClient_xx.jar files for our translated language strings and now have new Language Pack jar files. So all PSClient_xx.jar files will now need to be replaced by the appropriate Language Packs. Please read carefully #41025 included in the Release Notes for ProjectAdvantage S7.1q.

Core Product Enhancements

Built-in HTML5 Client

Commands

#43255

In the HTML5 Client, the interactive Gear button (1-59_img_0.png) now provides access to two new commands, allowing the user to expand or collapse all the rows of a Grid or a Text Block.

Fields Edits (Field Types)

#43204

ProjectAdvantage's rich text editor, powered by Froala, has been updated to the latest version.

1-59_img_1.png

The following updates have been implemented:

  • Updated user interface styling
  • New buttons: Superscript, Subscript, Change font size, Edit font color, Edit background color, Paragraph style, Special characters, Select all
  • New capabilities: Edit List styles, Edit tables, Insert Emoticons, Insert Horizontal Line, Print rich text data
  • Availability of a new Help dialog box

#43185

The conversion methods that convert text into data (e.g., ToDate, ToDuration, etc.) were expecting the text to be in an internal format (specifically used in formulas). The “ToText” method, however, uses the default format to convert data into text. This could cause formulas like “ToDate(ToText(Now()))” for example to fail.

That is why ProjectAdvantage now provides a new parameter, available on many of the conversion methods that convert text into data. This optional parameter is a “yes/no” value, which is defined as follows:

  • Yes: Uses the internal format
  • No: Uses the default format
Example: If we take our previous formula “ToDate(ToText(Now()))”, it would become “ToDate(ToText(Now()),no)” with this new parameter.

UI Blocks

#42430

In the HTML5 Client, tooltips will now be available for Grid columns when there is not enough space to show the entire column name.

1-59_img_2.png

Core Product Corrected Issues

Built-in HTML5 Client

#43266

In the HTML5 Client About ProjectAdvantage dialog box, About tab, the “Collections” Property Name was being displayed as ^about_collections^ and was not localizable. This issue has been fixed.

Commands

#39040

In some cases, when a project had a large number of tasks, the “Summarize At Level” command did not work. This issue has been fixed.

Data Snapshots

#43207

The following issues were related to Data Snapshot permissions:

  • The “Update Static Report Permissions” Scheduled Job was failing (under rare circumstances where there was an extra “blank” person record in the “Person” table).
  • The RoleID in the database was not properly updated. As a consequence, the permission query could fail which, in turn, resulted in the wrong folder showing up in the HTML5 Client Data Snapshots workspace.

These issues have been fixed.

#42460

Data Snapshot files timestamps systematically took into account the UTC timezone. This issue has been fixed; from now one, these timestamps will honor the server timezone.

Designer

#43264

In Designer Fields view, after a CFG import, some of the Project Filters were incorrectly marked as invalid. This issue has been fixed.

#43254

Under certain conditions, dropping a Data View on an external domain could cause a “NullPointerException” error. This issue has been fixed.

#43231

In the Designer Scheduled Job view, when a running “Generate View” scheduled job (whose type was other than “Project” or “Timesheet”) was manually stopped, the “Status” column displayed “Stopped” while the job was still running in the background to completion. This issue has been fixed.

#43219

If the first two parameters of a “TempSet” formula function were setting a Global “list” field from a “reference” field (e.g., TempSet([Global].TempResList, [Labor Assignment].[Resource],…), the entire TempSet evaluation sometimes failed. This was due to the fact that, under certain conditions, the program was not properly casting the “reference” field into the appropriate type of “list” field. This issue has been fixed.

#43206

In the Designer Collections view, the base field names were not properly sorted. This issue has been fixed; they are now sorted by name.

#43201

In a load-balanced environment, if there were no jobs scheduled when the servers were started, then when scheduling and saving jobs in the Designer Scheduled Jobs view, the jobs did not start unless the servers were restarted. This issue has been fixed.

#43058

If the full path of an Organization was not specified when modifying the Organization History of a Resource, an error message was displayed. This issue has been fixed.

#42549

In the Designer Purge view, some duplicates of resources and cost items could be displayed after upgrading from ProjectAdvantage 6. This was due to the fact that Resources and Cost Items had both working and published versions in ProjectAdvantage 6; during the upgrade, not all references to the working version were properly deleted. This issue has been fixed.

Fields Edits (Field Types)

#43230

When using SSO authentication, the Global fields were not taken into account when using the Link command with the “Open new browser tab” option after a certain period of inactivity. This issue has been fixed.

#42452

Under certain conditions, a Data View field whose Field Type was “View” could return its values in the wrong currency. This caused a mismatch in currencies during the formula evaluation and, therefore, an error message being displayed to the user. This issue has been fixed.

#41942

When a reference field was overwritten with another reference field, upon reopening the corresponding selector (upon clicking on the Hamburger icon), the list displayed lost the previous selection. This issue has been fixed.

Localization

#43210

When the English Language Pack was disabled in the HTML5 Client, Language Packs workspace, it was not possible to log into the Designer in English. This issue has been fixed; from now on, it will always be possible to access the Designer in English.

#43100

Numeric fields with negative values were not displayed correctly in right-to-left languages. This issue has been fixed.

#42199

When only one Language Pack was enabled (other than English) in the HTML5 Client, Language Packs workspace, the Designer login dialog box was only available in English, and the user could not log to the Designer in the activated Language Pack’s language. This issue has been fixed.

Object Edits (Data Categories)

#43271

When a user clicked on a filtering field’s Hamburger icon to access a multi-selection Selector popup, if he/she clicked on the “OK” button without making any selection, then the resulting view was empty and the user could not reset the empty value. This issue has been fixed; from now on, not selecting a value in the Selector popup will have the same behavior as if the user clicked on the “Cancel” button.

#43252

A View Based Field in the Portfolio Folder category that referred to a Global Data View field (which had a Portfolio Folder “managed reference” field) was not calculating correctly. This issue has been fixed.

Performance

#43223

When multiple users are connected to ProjectAdvantage HTM5 Client, and when the “Monitor Workspace Performance” option is activated in the Designer About ProjectAdvantage dialog box, Workspace Performance tab, a lot of memory could be consumed, leading to performance issues. In addition, the aforementioned Workspace Performance tab would display a varying number of entries, instead of the last ten workspaces, as designed. This issue has been fixed.

Script/API

#43212

Global fields modified by an API program were not properly saved. As a consequence, they could be accessed from outside the API program. This issue has been fixed.

#42935

When an API program was used to Rework a Timesheet, some of the fields were not editable until the API called “Session.clearCaches()” or until the API program was restarted. This issue has been fixed.

Security

#43245

Since built-in password salting is now enforced (#43244), users passwords can be invalid if environments were previously not using salted passwords. This issue has now been fixed. Users will be forced to reset their passwords, upon login, for the case that the environment was previously not using salted passwords.

#43244

Internal password salting is not enabled by default for PSServer.properties. Salting is now enabled by default and enforced. This has now been fixed.

#43234

In the HTML5 Client user settings, Profile section, the capability to upload a profile picture was not limited to image file types. This issue has been fixed.

UI Blocks

#43107

In the HTML5 Client swimlanes, it was not possible to drag and drop an object back to the first column, even if the corresponding Workflow allowed it. This issue has been fixed.

#42151

When setting the browser locale to “English (UK)”, the calendar dates were displayed in the US format (MM/dd) rather than the UK format (dd/MM). This issue has been fixed.

Default Configuration Enhancements

Portfolio Budget Simulation

In the Portfolio Center workspace, Budget tab, Portfolio Budget view mode, a new Budget Simulation feature is available, facilitating the process of aligning the Portfolio and Projects Budget for the Portfolio Manager.

The Budget Simulation full screen view allows the user to create as many scenarios as desired to study and propose different strategies. Each scenario will be initialized with the current budgets of the selected Portfolio and its corresponding Projects. From there, the Portfolio Manager will be able to “play” with the numbers, including by defining placeholders (for future initiatives, for example) until everything adds up.

Upon choosing a scenario, ProjectAdvantage will automatically update the Portfolio and the corresponding Projects budget making the entire experience of building budget as seamless as possible.

Administration

#MIL-791

In the System Settings workspace, Project Settings folder, Time Tracking Options tab, the “Timesheet Lock Date” option is now editable. Upon defining a date, no Actual Effort can be entered before or on the specified date in the Timesheet.

In addition, the “Submit” command is now sensitive to the “Timesheet Lock Date” (whether it has been entered in the System Settings or at the Organization level). In other words, the “Submit” button will be disabled in all the time periods prior to the Timesheet Lock Date.

Note: The corresponding buttons for submitting, reworking, reviewing, and approving Timesheets in the Resource Validation workspace and the Planning Scheduler workspace, Tracking tab are now conditioned by the “Timesheet Lock Date” as well.

#MIL-390

In the System Settings workspace, Project Settings folder, Display Preferences tab, Project Scheduler - Planner section, the following settings have been added:

  • Enable Gantt Labels Hard Assignments
  • Enable Gantt Labels Soft Assignments (whose “Scope” can be defined when activated)
  • Enable Gantt Labels Generic Resources

They allow the Administrator to specify whether or not assignments are displayed next to the tasks in the graphic pane of the Gantt chart. When the corresponding setting is activated, each assignment will be displayed as follows:

  • Hard Assignments: “Last Name, First Name”
  • Soft Assignments: “Organization - Job Classification - Skills” (depending on the Scope defined)
  • Generic Assignments: “Generic Resource Name”

In addition, when a task has several assignments, they will now be separated by a pipe “|” character to facilitate the reading.

Note: This enhancement impacts all the Gantt views across the Default Configuration as long as they display the assignments in the graphic pane.

#MIL-23

In the System Settings workspace, Project Settings folder, Display Preferences tab, Project Scheduler - Right Panel section, the new “Enable Assignment Card Custom Section” setting allows the Administrator to add a custom row to the Assignments cards available in the Gantt Task panel, Assignments tab.

In addition, upon activating this setting, the Scope field will allow the Administrator to select which cards are going to have an additional section among the following: Hard Assignment, Soft Assignment, Generic Resource, and Allocation Request.

General

#MIL-771

The Default Configuration now provides a “Shift Data” (1-59_img_3.png) command which allows the user to easily postpone (or bring forward) time-distributed values. Upon clicking on this command, the user will be prompted to define a date from which the selected data will be shifted, as well as the date to which the time-distributed data will be moved (by either selecting a date or a number of intervals).

The “Shift Data” (1-59_img_4.png) command has been implemented in the following views:

  • Planning Resources workspace, Project Allocations tab, Allocation Requests view mode
  • Planning Finance workspace, Budget tab, Details view mode
  • Planning Finance workspace, Costs tab, Forecast view mode
  • Portfolio Center workspace, Budget tab, Portfolio Budget view mode
  • Resources Allocations workspace, Hard Allocations tab
  • Resources Allocations workspace, Soft Allocations tab
  • System Data workspace, Cost Centers tab

Project

#MIL-724

In the Planning Scheduler workspace, Agile tab, Backlog Item dialog box, Checklist section, the Checklist items now display a new set of icons, indicating whether a description has been entered (1-59_img_5.png) or not (1-59_img_6.png) for each Checklist item.

#MIL-660

In the Planning Scheduler workspace, Status Reports tab, Status Report History dialog box, when printing some selected sections, the custom Descriptions are now taking into account the order in which they are sorted in the System Data workspace, Status Reports tab.

Note: This modification has also been implemented for the multi-project Scheduler workspace.

#MIL-592

In the Backlog Item dialog box, when a Custom section has been implemented, the content of the same Custom section will now be available in the printable version of the Backlog Item dialog box.

Note: The aforementioned Custom placeholder can be displayed by the Administrator upon activating the "Enable Agile Backlog Item Custom Section" setting available in the System Settings workspace, Agile Settings folder, Display Preferences tab.

#MIL-591

In the Planning Scheduler workspace, Agile tab, the following views have been updated to include the Backlog Item Notes (1-59_img_7.png) in their spreadsheet, allowing the user to access directly the Notes dialog box:

  • Iteration full screen view, Backlog tab
  • Dashboards full screen view, Backlog tab
  • Backlog full screen view

#MW-4222

In the Planning Center workspace, Definition tab, Stakeholders section, the “Permissions” and “Workflow” fields have been removed. These fields are now available in the Advanced Attributes dialog box, General folder.

Note: The Project Information dialog box has been updated accordingly.

Portfolio

#MIL-785

In the Portfolio Simulation workspace, after playing a scenario, in the Charts sections (Simulation and Analytics view modes), a previous ticket (MIL-423) resulted in breaking down the Total Effort by Hard Assignments vs. Soft Assignments. It was honored even when a Grouping criterion was selected, which could make the data difficult to analyze. This constant breakdown has been removed and is now available only when the “Group by” option is set to “Assignment”.

#MIL-536

In the Portfolio Simulation workspace, after playing a scenario, Simulation view mode, the color representing the Completed portion of the projects in the Gantt view has been changed to the system default green.

#MIL-535

In the Portfolio Dashboards workspace, Roadmap report, the Gantt view graphic pane now displays Today's date; it is represented by a vertical dotted line.

#MIL-344

In the Portfolio Dashboards workspace, the following reports have been updated to support the ability to sort the projects by Leveling Priority: Agile, Billing, Phases & Gates, Forecast, Controlling, Baseline Comparison, Performance, Pipeline, and Status Overview.

#MIL-343

In the Portfolio Dashboards workspace, the following reports have been updated to support the ability to sort the projects by Score: Agile, Billing, Phases & Gates, Forecast, Controlling, Baseline Comparison, Performance, Pipeline, and Status Overview.

#MW-4278

In the Portfolio Dashboards workspace, Status Overview report, accessing the last report information provides now the full report information rather than a summary.

Note: This change has also been applied to all the other Status Overview reports.

Resource

#MIL-657

In the Resource Dashboards workspace, Resource Utilization report, Filters popup, the following options have been added:

  • Utilization > % / Utilization < % – Allows the user to only display Resources whose % Utilization is over / below the entered value.
  • Project Status – Allows the user to display projects depending on the Status (Active, Inactive, or both).

Work Management

#MIL-537

In the Planning Work Management, Portfolio Work Management, and Work Management workspaces, Risks tab, Home Page view, the design of the Project Information panel has been updated for a better emphasis of the buttons allowing the user to open the full screen view and to create a Risk.

#MIL-4647

In the Planning Work Management, Portfolio Work Management, and Work Management workspaces, Risks tab, Dashboards full screen view, Overview tab, the matrix has been enhanced to take into account the reverse display for the Hebrew language.

Default Configuration Corrected Issues

Administration

#MIL-734

In the System Settings workspace, Project Settings folder, Global Options tab, Health Score sub-tab, the “Include Work Objects in Quality Score calculation” setting was still available when the “Activate Work Management” setting was deactivated. This issue has been fixed.

Note: The aforementioned setting can be found in the System Settings workspace, General Settings folder, Meta Settings tab.

Execution

#MIL-735

In the Timesheet workspace, Activity Logs panel, the period range finish displayed for activity logs entered on Work Objects and Backlog Items was ahead of one day. This issue has been fixed.

Planning

#MIL-821

In the Planning Scheduler workspace, Planner tab, Scheduler view mode, in the Gantt Problems panel, Transactions Problems, when a user clicked on the “Jump to Transactions” button for the “Overdue Transaction(s)” alerts, the wrong filter was applied in the Transactions tab. This issue has been fixed.

#MIL-789

In the Planning Finance workspace, Snapshot Details popup (accessible from the Snapshot History dialog box), Comparison tab, the spreadsheet was not displayed properly. This issue has been fixed.

#MIL-780

In the Planning Finance workspace, Budget tab, Details view mode, Direct sub-tab, the Budget values were not editable when the project only had Cost Centers whose Budget Type was set to “Effort”. This issue has been fixed.

#MIL-770

In the Planning Scheduler workspace, Planner tab, Scheduler view mode, Gantt Task panel, Task Comments popup (upon clicking on the “Comments” (1-59_img_8.png) icon), comments from deleted tasks were listed for all the other tasks. This issue has been fixed.

#MIL-741

Across the workspaces available under the Planning and Projects labels, multiple links (i.e., “Jump to” and “Drill-down” buttons) were leading to views without any ProjectAdvantage header. This issue has been fixed.

#MIL-726

In the Planning Scheduler workspace, Tracking tab, Outstanding Timesheets in the past popup, upon clicking on the “Jump To Time Frame” button when the displayed Time Frame was “Month”, the Period was not set correctly; the view was displayed with a “Specific Week” period instead of the “Specific Month”. This issue has been fixed.

#MIL-725

In the Planning Scheduler workspace, Gantt side panel, Work Objects problems, clicking on the “Jump To Risks” and “Jump to Work Items” buttons resulted in a view with no ProjectAdvantage header. This issue has been fixed.

#MIL-713

In the Planning Center workspace, Contracts tab, Work Package contract, when locking a contract, the Deliverables were not captured and were therefore not displayed in the Contract History dialog box (accessible by clicking on the “History” button). This issue has been fixed.

#MIL-693

In the Planning Center workspace, Contracts tab, Deliverables section of the Contract Details, the Deliverables cards design was not compliant with the latest updates. This issue has been fixed.

#MIL-691

In the Planning Finance workspace, Snapshot History dialog box (accessible upon clicking on the “Manage Snapshots” button), Snapshot Details popup (accessible upon clicking on the Details (1-59_img_9.png) icon), Total Cost sub-tab, the time-distributed values did not match the values displayed in the Costs tab when the spreadsheet was grouped by Cost Centers. This issue has been fixed.

#MIL-687

In the Planning Center workspace, Evaluation tab, Scoring sub-tab, clicking on the Question Mark (1-59_img_10.png) icon displayed the Comments popup instead of the additional information regarding the indicator. This issue has been fixed.

#MIL-683

In the Planning Scheduler workspace, Tracking tab, Timesheet Details full screen view, the “Apply” buttons were still available for Timesheets whose Status was not “Reviewed” when the “Review Timesheet Before Apply” option was activated. This issue has been fixed.

Note: The aforementioned option is located in the Advanced Attributes dialog box, Tracking folder. This dialog box can be accessed by clicking on the main toolbar More (1-59_img_11.png) button and selecting the “Manage Advanced Attributes” option.

#MIL-670

In the Planning Center workspace, Evaluation tab, Evaluation Trend dialog box (accessible by clicking on the Manage Evaluation Snapshots (1-59_img_12.png) button), the initial Scoring and Descriptions of the connected Idea were not captured when the Idea resulted in a new Project. This issue has been fixed.

#MIL-654

In the Planning Scheduler workspace, Transactions tab, using filters did not have any impact on the total project values. This issue has been fixed.

#MIL-639

In the Planning Scheduler workspace, Planner tab, Scheduler view mode, Gantt Task panel, Assignments tab, an error occurred when creating an assignment on a Hammock task. This issue has been fixed.

#MIL-625

In the Planning Scheduler workspace, Tracking tab, Timesheet Details full screen view, the Remaining Delta was only considering the current time period. This issue has been fixed.

#MIL-624

In the Planning Finance workspace, Costs tab, Forecast view mode, Transactions sub-tab, when no forecast was entered, the “Cost Center” button was not displayed when the “Enable Forecast Labor Pivot Selection” setting was deactivated. This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, Budget/Finance folder, Global Options tab, Forecast section.

#MIL-606

In the Planning Scheduler workspace, Planner tab, Scheduler view mode, Gantt Problems panel, the Health Score displayed an “N/A” value when a user was not granted at least the “Read Cost” permission on the project. This issue has been fixed; from now on, the Administrator will be able to define which Score values (Cost, Time, and Quality) will be taken into account in the Health Score through a new set of settings.

Note: The aforementioned settings have been added to the System Settings workspace, Project Settings folder, Global Options tab, Health Score sub-tab. These settings can be enabled for specific Natures.

#MIL-596

In the Planning Scheduler workspace, Planner tab, Scheduler view mode, Gantt spreadsheet, converting a task into a Work Package (by clicking on the Cmd. Gear (1-59_img_13.png) icon, and then selecting the “Convert to Work Package” option) did not associate a Workflow to the task. This issue has been fixed.

#MIL-590

In the Planning Finance workspace, Costs tab, Forecast view mode, Transactions sub-tab, Pivot Selection dialog box (accessible upon clicking on the Edit (1-59_img_14.png) icon next to the currently selected pivot in the spreadsheet header), the “Cost Center” button was not correctly highlighted when selected. This issue has been fixed.

Portal

#MIL-698

In the Client Portal workspace, Activity Stream full screen view (accessible upon clicking on the More (1-59_img_15.png) button on the left panel), an empty state was always displayed, even if Activity Stream entries existed. This issue has been fixed.

#MIL-697

In the Project Portal workspace, Agile tab, in the read-only Iteration dialog box (accessible upon clicking on the Details (1-59_img_16.png) button for an Iteration), the user had the opportunity to define the Iteration Team Members while he/she should not. This issue has been fixed.

Portfolio

#MIL-772

In the Portfolio Center workspace, Budget tab, Project Budget view mode, when the view was grouped by Cost Centers (upon activating the Cost Centers (1-59_img_17.png) display option), the Time Navigation toolbar was not accessible and the distribution of the spreadsheet was not conditioned. This issue has been fixed.

#MIL-751

In the Portfolio Center workspace, Project Supervision tab, Closed projects still displayed the Overdue Status Report indicator. This issue has been fixed.

#MIL-684

In the Portfolio Dashboards workspace, Overview report, Filters popup, the “Workflow States” filtering field did not display the Workflow States of Inactive projects when the “Inactive Only” or “Both” options was selected in the “Project Status” field. This issue has been fixed.

#MIL-637

In the Portfolio Dashboards workspace, Performance and Baseline Comparison reports, the “Most Healthy First” and “Least Healthy First” sorting options outcome were inverted. This issue has been fixed.

Projects

#MIL-762

In the Master Planning workspace, the Gantt Preferences (1-59_img_18.png) button was wrongly available. This issue has been fixed.

#MIL-747

In the Home Page workspace, Project News dialog box (accessible upon clicking on the “Details” button), Agile section, clicking on the “Iteration” button opened the Iteration full screen view of the last Iteration created instead of the current Iteration. This issue has been fixed.

#MIL-746

In the Home Page workspace, Project News Feed view, in the Agile section of the project card's header, the Backlog Items and Story Points progress took into account the whole project rather than the ongoing Iteration(s). This issue has been fixed.

#MIL-710

In the Dashboards workspace, Milestone Trend Analysis report, the list of Monitored Tasks was empty when selecting a project’s Working version. This issue has been fixed.

#MIL-716

In the Home Page workspace, Status Reports Critical Alerts Details popup, after opening and then closing the Status Report History dialog box for a specific project, the projects selection could be lost. This issue has been fixed.

#MIL-709

In the Administration workspace, Administration tab, when multiple projects were selected, creating a new project resulted in deselecting the projects; only the newly created project was selected. This issue has been fixed.

#MIL-707

In the Scheduler workspace, in the main toolbar, the buttons' tooltips were not written in the plural form to emphasize the multi-project selection. This issue has been fixed.

#MIL-706

In the Scheduler workspace, in some tabs, the “Workflow” button was still available while multiple projects were selected. This issue has been fixed.

#MIL-614

In the Scheduler workspace, Tracking tab, in multi-project selection, in the Impact Management full screen view, Impacts left panel, the alerts displayed in the project cards (regarding the impacted Finish Date, and the new Finish Date compliance with the project Deadline) were inverted. This issue has been fixed.

Resource

#MIL-792

In the Resource Dashboards workspace, Cost Items Utilization report, the Cost Item “Total” row value was wrong. This has been fixed.

#MIL-695

In the Planning Scheduler workspace, Resources tab, Assignments List view mode, replacing a hard assignment (or fulfilling a soft assignment) resulted in some incorrect behavior in the prompted dialog boxes. This issue has been fixed; the “Replace Hard Assignment” and “Fulfill Soft Assignment” commands have been removed from this view.

Work Management

#MIL-773

In the Portfolio Work Management workspace, Project Monitoring tab, Risks view, when opening the Risks full screen view and then closing it, the previously selected Portfolio Folders were no longer selected. This issue has been fixed.

#MIL-740

In the Portfolio Work Management workspace, Work Items tab, Work Item full screen view using the “Create & Connect” button of a newly created Work Item to add a connected Action resulted in an unexpected error. This issue has been fixed.

#MIL-732

In the Execution Work Items workspace, Work Item full screen view, Grid tab, when copying items, the new items were not displayed in the spreadsheet if the “Created By Me” display option of the left panel was selected. This issue has been fixed.

#MIL-708

In the Work Management workspace, Work Items tab, Home Page view, when the selected projects had only Work Items which were related to a Task, the Name of the first project was missing. This issue has been fixed.

#MIL-669

In the Planning Work Management workspace, Risks tab, Risks full screen view, Inbox tab, when creating a new Risk, and then associating a new Action to the Risk (by clicking on the “Create & Connect” button in the Risk dialog box Actions section), the newly created Risk was not displayed in the Risks list once the dialog box was closed. This issue has been fixed.

#MIL-638

In the Execution Work Items workspace, the user could create a Work Item without selecting any parent object (Portfolio Folder, Project or Work Package). This issue has been fixed.

#MIL-598

In the Planning Work Management workspace, Risks tab, a newly created Risk would not be displayed until the workspace was reloaded. This issue has been fixed.

Work Package

#MIL-653

In the Work package Scheduler workspace, when selecting multiple Work Packages, and then selecting a task, there were several display issues. This issue has been fixed.

#MIL-603

In the Work Package Center workspace, Definition tab, the “Assignable Cost Items” (1-59_img_19.png) button was still available when the “Activate Cost Items” meta setting was deactivated. This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, General Settings folder, Meta Settings tab.