This document describes the enhancements, corrected issues, and new features that have been implemented in ProjectAdvantage 2024.12, both in the Core product and in the ProjectAdvantage Default Configuration, in Vantage and in Deliver.

ProjectAdvantage 2024.12 is a maintenance release of ProjectAdvantage 2024.

In the Core product, 9 enhancements have been implemented and 24 issues have been fixed.

In the ProjectAdvantage Default Configuration, 2 enhancements have been provided and 14 issues have been fixed.

In Vantage, 1 enhancement has been implemented and 1 issue has been fixed.

In Deliver, 1 issue has been fixed.

In order to access the different sections, please click on the following links:

Important Reminders for upgrade

  • To improve the performance of views displaying the Health Score of multiple projects, we are now using a Health Score that is pre-calculated upon publishing a project as opposed to on the fly. Therefore, upon upgrading to 2021.03 (or higher), please make sure you run once the following Scheduled Job to initialize the project Health Score values: Initialize Project Static Health Score.
Important: For systems with an overwritten Publish command, please make sure to add the new dedicated Command List for the Health Score pre-calculation upon publishing a project: “Project - Publish Project - Continue - Capture Health Score”.
  • From the 2023.01 version, to support the implementation of the new Vantage navigation and modules, the Project Dashboards workspace should be added again in the User Roles section of the Designer as the Dashboards workspace doesn't exist anymore.

Core Product Enhancements

Build

#SCI-5155

The concept of Project Hierarchy has been introduced to allow users to easily and intuitively navigate through their projects’ structure in the Projects Center workspace and the Projects selector.

To allow the Projects hierarchy to be managed, a new built-in field has been created in the Designer, Fields view, Project category: the “Parent” field.

1-117_img_0.png

By default, the “Parent” field has been added in the field sets of the view controls in the Projects Center workspace:

  • Filters (Grid and Board views)
  • Columns (Grid view)
  • Group by (Grid view)

To display the Projects hierarchy in the Projects Center workspace, Grid view, administrators will need to ensure the “Use hierarchy display” setting is activated in the Designer, Forms view, Edit Grid Properties dialog box, Loop tab.

1-117_img_4.png

Consequently, the Projects hierarchy is displayed in the Projects Center workspace and the Projects selector, as illustrated below.

1-117_img_5.png

1-117_img_6.png

In addition, a new “Enable Projects Hierarchy” setting has been created in the System Settings workspace, Project Settings folder, Global Options tab, Hierarchy sub-tab:

1-117_img_7.png

  • When this setting is activated, the “Parent” field is displayed in the Default Configuration.
  • When this setting is deactivated, the “Parent” field is hidden in the Default Configuration.
Note: The “Enable Projects Hierarchy” setting is deactivated by default.

When the aforementioned setting is activated, the “Parent” field is displayed in:

  • The Create New popup
  • The Project Card, Overview tab, Definition sub-tab, Identification section
  • The Project Card, Overview tab, Summary sub-tab
  • The Project Brief dialog box, Definition folder
  • The Project Brief dialog box, Overview folder
Important: For legacy customers, it has to be noted that the Projects hierarchy is not related to the connections. It means that the “Parent” field will have to be fulfilled for the hierarchy to be displayed.

#SCI-5109

The OpenJDK 21 Java Runtime Environment (JRE) (Tomcat) is now supported.

Note: For on premise installations, the following java_opts needs to be added:

-Djava.locale.useOldISOCodes=true -Djava.locale.providers=COMPAT,SPI

Built-in Workspaces - Timesheet

#SCI-5343

Previously, administrators were able to set specific lock dates for past and future timesheet entries, ensuring that their teams cannot edit their timesheets outside of defined periods. The modifiable range was either static, i.e. from a specific date and/or to a specific date, or rolling, i.e. a number of days/weeks/months/quarters/years from and/or to the current date.

From now on, administrators can set both a static modifiable range and a rolling modifiable range in the Designer, Time Tracking view, “Timesheet modifiable range” section. The modifiable range will be set from the furthest of the two start dates to the earliest of the two finish dates.

1-117_img_13.png

#SCI-5166

In the Timesheet (built-in) workspace, a warning message now appears when a Timesheet Modifiable Range has been defined, indicating the range in which the timesheet can be modified. Users are not able to enter any actuals outside of the specified range.

1-117_img_14.png

As a reminder, the modifiable range can be defined in the Designer, Time Tracking view, “Timesheet modifiable range” section.

1-117_img_15.png

To set a static modifiable range, administrators will need to enter a start and/or finish date for the “Static Timesheet modifiable range” option.

1-117_img_16.png

Alternatively, it is possible to define a static modifiable range using the “Timesheet Modifiable Start” and/or “Timesheet Modifiable Finish” settings in the System Settings workspace, Project Settings folder, Time Tracking Options tab, Timesheet Options section.

1-117_img_17.png

To set a rolling modifiable date, administrators will need to enter a value preceded by a minus (-) sign as start and/or a value preceded by a plus (+) sign as finish, as well as select the desired interval (Day, Week, Month, Quarter, or Year).

1-117_img_18.png

Important: Rolling modifiable dates cannot be defined in the HTML5 Client, they can only be set in the Designer.
Note: When submitting a timesheet, the process will automatically submit from Monday to Sunday, even if we hide the weekend in the UI. So, if the administrator locks the timesheet in the middle of the week by adding a lock date (whether it’s a start or finish date), the end-user will be able to edit it from or until the date the timesheet is locked. However, the “Submit” button will be greyed out for the entire week since it is not possible to submit a partial timesheet when a lock mechanism is in place. The best practice would be to lock from Sunday to the next Sunday.

Designer

#SCI-4891

The loading of dataviews through the Organization context has been optimized.

Execution - Timesheet

#SCI-5278

In the legacy Timesheet workspace, the warning message appearing at the bottom of the page (which indicates the range in which the timesheet can be modified) has been updated for better clarity, to include the time.

When only a finish date has been fulfilled for the modifiable range, the warning message will appear as follows.

1-117_img_19.png

If both a start and finish date have been fulfilled for the modifiable range, the warning message will appear as follows.

1-117_img_20.png

#SCI-5239

A new setting has been added in the System Settings workspace, General Settings folder, General Options tab, Format Controls section: “Default Time Distribution”, allowing users to either use the “Calendar”, the “Fiscal Period”, or “Both” in all time distributed screens throughout the solution.

1-117_img_21.png

When the “Default Distribution” is set to “Calendar”, the Presets (1-117_img_22.png) button and the Intervals picklist available in the time navigation toolbar allow the user to directly set the displayed timeframe to the built-in presets and intervals.

1-117_img_23.png

1-117_img_24.png

When the “Default Time Distribution” is set to “Fiscal Period”, the Presets (1-117_img_25.png) button and the Intervals picklist available in the time navigation toolbar allow the user to directly set the displayed timeframe to the Fiscal Periods set by the administrator.

Note: Administrators will need to overwrite the built-in Fiscal Periods with their own Fiscal Periods, using the “Intervals Fiscal Calendars Only_Overwritable” and the “Grid Distribution Fiscal Calendars Only_Overwritable” fields in the Designer, Fields view, Global Category, Formatting tab.

1-117_img_26.png

1-117_img_27.png

When the “Default Time Distribution” is set to “Both”, the Presets (1-117_img_28.png) button and the Intervals picklist available in the time navigation toolbar allow the user to directly set the displayed timeframe to the built-in presets and intervals, as well as the Fiscal Periods set by the administrator.

Note: Administrators will need to overwrite the built-in Fiscal Periods with their own Fiscal Periods; using the “Intervals All Calendars” and the “Grid Distribution All Calendars_Overwritable” fields in the Designer, Fields view, Global Category, Formatting tab.

1-117_img_29.png

1-117_img_30.png

Note: Fiscal Periods are set by the administrator in the Designer, Fiscal Periods view.

1-117_img_31.png

Important: The “Default Time Distribution” is set to “Calendar” by default.

When the “Default Time Distribution” is set to either “Fiscal Period” or “Both” in the System Settings workspace, ​General Settings folder, ​General Options tab, ​Format Controls section, a Fiscal Period​ switch button is displayed on the left-hand side of the ​Week and ​Month view modes in the Timesheet (built-in) workspace.

1-117_img_32.png

When activated, clicking on the current Fiscal Period displays a left panel allowing users to select the fiscal period they wish to view.

1-117_img_33.png

It also allows users to view their timesheet according to the Fiscal Periods set by the administrator in the Designer.

1-117_img_34.png

Performance

#SCI-5416

Concurrent handling in project validation has been enhanced in order to improve validation efficiency.

Projects Legacy - Resources - Project Allocations

#SCI-5251

A new setting has been added in the System Settings workspace, Resource Settings folder, Allocations & Commitments tab, Allocations Options section: “Set Allocations Units”, allowing users to display resource allocations as percentage of the Full-time equivalent (FTE %) in all the allocations screens throughout the solution.

1-117_img_35.png

When this setting is set as “FTE %”, data is displayed in percentage of the Full-time equivalent in the following screens:

  • Project Allocations full screen view, Requests tab, Requests Inbox sub-tab
  • Project Allocations full screen view, Requests tab, Requests Overview sub-tab
  • Project Allocations full screen view, Allocations tab, Resources Overview sub-tab
  • Project Allocations full screen view, Allocations tab, My Allocated Resources sub-tab
  • Dashboards tab, Allocations theme: all reports
  • Resource Allocations workspace, Resource Allocations full screen view, Hard Allocations tab, Resources Overview sub-tab
  • Resource Allocations workspace, Resource Allocations full screen view, Hard Allocations tab, Project Allocations sub-tab
  • Resource Allocations workspace, Resource Allocations full screen view, Soft Allocations tab, Overview by Organization sub-tab
  • Resource Allocations workspace, Resource Allocations full screen view, Soft Allocations tab, Overview by Project sub-tab
  • Resource Allocations workspace, Resource Allocations full screen view, Requests tab, Requests Inbox sub-tab
  • Resource Allocations workspace, Resource Allocations full screen view, Requests tab, Requests Overview sub-tab

Core Product Corrected Issues

Authentication

#SCI-5134

An error message was sometimes displayed when users were trying to log in using the SSO. The issue has been fixed.

Build

#SCI-5523 (*Added on 01/31/25)

In some scenarios, due to a connection leak, the server was going down if the “Enable Projects Workflow Changes”, “Enable Ideas Workflow Changes”, “Enable Work Objects Workflow Changes”, “Enable Backlog Items Assignees”, and/or “Enable Work Objects Assignees” settings were enabled and if users were performing some operations, such as changing a workflow. This issue has been fixed.

Note: The aforementioned settings are located in the System Settings workspace, General Settings folder, Notifications tab, Notification settings section.

Built-in Workspaces - Data Snapshots

#SCI-5353

In the Designer, Scheduled Jobs view, the “Generate Static Report” functionality was failing when the output format was set to CSV and the corresponding folder contained no reports in the Data Snapshots workspace. This issue has been fixed.

#SCI-4847

When users were exporting a data snapshot from a generic static report in CSV format and opening the file in Excel or Numbers, some of the data appeared on the same line. This issue has been fixed.

#SCI-2503

In the Designer, Scheduled Jobs view, when users were running the “Generate Static Reports” scheduled job for a specific file, all previously generated reports were incorrectly deleted and their corresponding folder(s) were not visible in the HTML5 Client, Data Snapshots workspace. This issue has been fixed.

Built-in Workspaces - Timesheet

#SCI-4464

In the Timesheet (built-in) workspace and in the legacy Timesheet workspace, “Non-Project Assignments” were incorrectly not visible and they could not be added to timesheets. This issue has been fixed.

Data Visualization

#SCI-5529 (*Added on 01/31/25)

In the Projects Center workspace, Project Card, Gantt tab, Manage Baselines dialog box, when users were saving a new baseline, then were clicking on the Details (1-117_img_36.png) icon, the Baseline Cost data was incorrect, i.e. it was equal to the Remaining Cost instead of the Total Cost. This issue has been fixed.

#SCI-4456

In the Projects Center workspace, Project Card, Work Items tab, Work Items full screen view, Grid tab, in some scenarios, all the work items from all projects were visible. This issue has been fixed.

#SCI-4033

In the HTML5 Client, the built-in currency field was not working properly for new users or for users without a currency set in their profiles. This issue has been fixed.

Execution - Calendar

#SCI-4096

In the Designer, Calendars view, when a day was set as non-working day, the modification was not taken into account and the non-working day was still displayed as working day in the Calendar workspace, in the Timesheet (built-in) workspace, in the legacy Timesheet workspace, and in the Resource Validation workspace, Timesheets and Calendars tabs. This issue has been fixed.

Execution - Timesheet

#SCI-5382

In the legacy Timesheet workspace, when users were clicking on the “+ Assignments” button, an error message was displayed and no new assignment could be added. This issue has been fixed.

#SCI-4668

In the Corporate Data workspace, Resources tab, Resource Identification dialog box, when changes were applied to a resource’s calendar, in some scenarios, the status of certain approved timesheets was impacted and additional Non-Project Assignments (holidays) were added. This issue has been fixed.

Legacy API

#SCI-4924

In certain scenarios, the API Resource Data Update operation was failing for some resources. This issue has been fixed.

#SCI-4680

In some scenarios, an error message was displayed when users were trying to retrieve the existing resource allocations data from the “Global Resource Allocations” view via the API. This issue has been fixed.

Portal - Ideas Center

#SCI-5385

In the Ideas Center workspace, Idea Card, when users were changing the Workflow State Vote to “New Project” then were completing the new project creation process, the relation displayed in the Connections section of the Idea Card was empty. This issue has been fixed.

Project Scheduler

#SCI-5396

In the Projects Center workspace, Project Card, Gantt tab, Manage Baselines dialog box, the Shift command was not working for tasks without assignments. This issue has been fixed.

Projects - Projects Center

#SCI-5224

In the Projects Center workspace, Project Card, when users were selecting the “Deactivate selected version” or “Deactivate all versions” commands in the main toolbar, an incorrect error message was displayed. This issue has been fixed.

#SCI-5061

In the Projects Center workspace, Grid view, an error message was incorrectly displayed when users were clicking on the Save command displayed on the right-hand side of a modified view name. This issue has been fixed.

#SCI-4925

In the Projects Center workspace, Project Card, Gantt tab, when users were performing a drag and drop of one or more tasks, other tasks were also incorrectly selected. This issue has been fixed.

#SCI-4869

In the Projects Center workspace, when users were clicking on the + New project button, then pressing the Esc key while in the Create New popup, the popup was locked and inactive. This issue has been fixed.

#SCI-4829

For fields with Organizations, Portfolio Folders, or Skills types, set field values were sometimes not working on them when the target object was a list of references. This issue has been fixed.

Projects Legacy - Work - Gantt

#SCI-5272

In the Projects Center workspace, Project Card, Task tab, XML Updates sub-tab, when users were updating a project from an XML file, no items were updated. This issue has been fixed.

#SCI-3254

In the Work workspace, Gantt tab, when users were selecting the “Generate Outline Code” command in the Gantt toolbar, the context was lost and they could not do anything anymore in the Gantt. This issue has been fixed.

Scheduled Jobs

#SCI-3904

In the Designer, Scheduled Jobs view, when users were stopping a Cloud scheduled job by unticking the relevant Scheduled checkbox, the scheduled job was still running. This issue has been fixed; from now on, when Cloud scheduled jobs are enabled, disabling a scheduled job while it is still running displays the “Stops after execution” status.

Default Configuration Enhancements

Execution - News Page

#MIL-5158

The loading time of the News Page workspace has been optimized.

Resource - Resource Validation - Timesheets

#MIL-5134

In the Timesheet workspace, when a “Timesheet Modifiable Finish” is fulfilled, the range is better identified with the date and time.

1-117_img_37.png

Note: The aforementioned setting is located in the System Settings workspace, Project Settings folder, Time Tracking Options tab, Timesheet Options section.

Default Configuration Corrected Issues

Execution - My Home Page

#MIL-5177

In the My Home Page workspace, My Pending Approvals block, Time off tab, the “See All” button was visible even though the block was empty. This issue has been fixed.

#MIL-5165

In the My Home Page workspace, Company news block, bookmarked articles were incorrectly not displayed at the top of the list. This issue has been fixed.

Note: Articles were previously sorted by publication date, from the newest to the oldest article. From now on, bookmarked articles will be displayed at the top of the list and the publication date will be used as the second sorting criterion.

Performance

#MIL-5124

In the Overview workspace, the "Allocated Effort by Project (Next 3 Months)" chart could take a long time to load. This issue has been fixed.

Portal - Ideas Center

#MIL-5106

In the Ideas Center workspace, when users were creating a new project from an idea, the process could take some time to complete. This issue has been fixed.

Project Scheduler

#MIL-5150

In the Projects Center workspace, Project Card, Gantt tab, Manage Baselines dialog box, when users were removing a baseline, then were closing the dialog box and reopening it again, the removed baseline was incorrectly still displayed. This issue has been fixed.

Projects - Projects Center

#MIL-5190

In the Projects Center workspace, Project Card, Evaluation tab, Idea Connections sub-tab, the icon allowing users to go to the Idea Center was not correctly displayed. This issue has been fixed.

#MIL-5189

In the Projects Center workspace, Project Card, Evaluation tab, Description sub-tab, the data was not correctly displayed when users were clicking on the “Sync up with a Connected Idea” command. This issue has been fixed.

#MIL-5162

In the Projects Center workspace, the “Publish” operation was not triggered after a project had been created, even if the "Enable Auto Publish After Creation" setting was activated. This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, Project Settings folder, Project Creation Options tab, Project Mode section.

#MIL-5131

In the Projects Center workspace, Project Card, Resources tab, Resources assignments sub-tab, the header was incorrectly spelled when multiple projects were selected. This issue has been fixed.

Resource Management

#MIL-5157

In the Projects Center workspace, Project Card, Resources tab, Project Resources sub-tab, an error message was displayed when users were creating new Allocation Requests, even when they were logged in as the Organization Manager with the required Edit rights on the project. This issue has been fixed.

Resource - Resource Allocations

#MIL-5159

In the Designer, Scheduled Jobs view, a new Scheduled Job has been created to convert all Allocations using the old link mechanism between Request and Allocation objects before the 2023.05 version.

Note: This link mechanism has been changed through the ticket MIL-4123.

Resource - Resource Dashboards

#MIL-5143

In the Resource Dashboards workspace, Team theme, Resource Capacity report, Resource Utilization Overview view mode, the report was not correctly updated when a modification had previously been applied in the Designer on the “Group By” option. This issue has been fixed.

Resource - Resource Validation

#MIL-5141

In the Resource Validation workspace, Timesheets tab, clicking on the “Submit”, “Review” or “Rework” commands to perform bulk actions did not have any effect. This issue has been fixed.

Work Items

#MIL-5119

In the Projects Center workspace, Project Card, Work Items tab, Work Items full screen view, Inbox tab, the Sort By option was not working properly. This issue has been fixed.

Vantage Enhancements

Boards

#VAN-1325

The “Refresh” feature without losing the applied filters, previously only available in Deliver, has been deployed in Vantage. From now on, when users select a board from the Vantage navigation toolbar and apply some filters, clicking on the “refresh” button located on the top right-hand side of the page does not reset the filters anymore.

Vantage Corrected Issues

Data Connector

#VAN-1313

In the Projects Center workspace or in the Project Portal workspace, when users were modifying a project or an action in Plan, the modification was not reflected in Deliver. This issue has been fixed.

Deliver Corrected Issues

Gridboard

#DELIVER-705

In the Gridboards, in some scenarios, there could be a display issue in the Filters popup when multiple values were selected. This issue has been fixed.

System Requirements

There are frequent changes and additions to the set of specific versions of operating systems, application servers and database servers for which ProjectAdvantage has been tested and certified. Please contact our teams for the latest information in this area.

Note: Users' system clocks must be regularly and accurately synchronized with the internet.

Servers

  • Application Server: Apache Tomcat 9 with Oracle Java 8 or OpenJDK
  • Data Server: PostgreSQL 12, PostgreSQL 14

HTML5 Clients

  • Display resolution: 1366 x 768 (technical minimum), 1600 x 1050 (minimum recommended), 1920 x 1080 or higher (generally recommended).
  • Minimum of 4GB RAM allocated (8GB recommended).
  • Browser
    • Microsoft Edge
    • Microsoft Internet Explorer 10 or 11
    • Google Chrome
    • Mozilla Firefox
    • Apple Safari

ProjectAdvantage Designer

  • Recommended language: English
  • Display resolution: 1366 x 768
  • Minimum of 4GB RAM allocated
  • Disk space: 200MB minimum available for ProjectAdvantage.
  • Oracle Java 8 or OpenJDK 8
  • Operating Systems:
    • Windows 7, 8.1, 10 or 11
    • Mac OS X Lion or newer
    • Alpine Linux 3.16.1

REST API

  • Supported language: English

Timesheets Mobile Application

  • Being hosted by ProjectAdvantage
  • Product version: 2022.08 and upper versions

Vantage platform

Users will need to enable third-party cookies to work within Vantage. For more information regarding third-party cookies, please refer to the “How to allow third-party cookies” documentation.

For customers who subscribed only to Plan

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • Product version: 2023.01 and upper versions

For customers who subscribed to Plan and Deliver

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • HPV2 activated on Deliver modules (activated by default for all new Deliver Clients after 2021 Q3)
  • Product version: 2023.01 and upper versions
  • Users will need to allow third-party cookies in their browser

Limitations

The data connector:

  • Does not work in load balanced environments.
  • Is not compatible with Cloud Scheduled Jobs.
  • Is not compatible with dedicated API servers.
  • Is not compatible with the Java API.