Skip to main content

 

  • arrow icon

 

Planview Customer Success Center

2023.09

This document describes the enhancements, corrected issues, and new features that have been implemented in Vantage and in ProjectAdvantage 2023.09 both in the Core product and in the ProjectAdvantage Default Configuration.

ProjectAdvantage 2023.09 is a maintenance release of ProjectAdvantage 2023.

In Vantage, 2 enhancements have been implemented and 9 issues have been fixed.

In the Core product, 3 enhancements have been implemented and 29 issues have been fixed.

In the ProjectAdvantage Default Configuration, 1 enhancement has been provided and 9 issues have been fixed.

In order to access the different sections, please click on the following links:

Important Reminders for upgrade

  • To improve the performance of views displaying the Health Score of multiple projects, we are now using a Health Score that is pre-calculated upon publishing a project as opposed to on the fly. Therefore, upon upgrading to 2021.03 (or higher), please make sure you run once the following Scheduled Job to initialize the project Health Score values: Initialize Project Static Health Score.
Important: For systems with an overwritten Publish command, please make sure to add the new dedicated Command List for the Health Score pre-calculation upon publishing a project: “Project - Publish Project - Continue - Capture Health Score”.
  • From the 2023.01 version, to support the implementation of the new Vantage navigation and modules, the Project Dashboards workspace should be added again in the User Roles section of the Designer as the Dashboards workspace doesn't exist anymore.

Vantage Enhancements

Vantage SSO

#VAN-303

A Plan hidden workspace has been implemented to maintain the user’s session in the browser while using Deliver as the default workspace.

#VAN-301

A Ping Graphql API endpoint has been implemented to update the user’s session timeout.

Vantage Corrected Issues

Data Connector

#VAN-413

A “NullPointerException” could occur when users were removing assignments using the Legacy API. This issue has been fixed.

Project Definition

#VAN-435

In the Work workspace, Gantt tab, Project Brief dialog box, Definition folder, Description section, it was not possible to upload an image in the Description section anymore. This issue has been fixed.

Resource Assignments

#VAN-196

In the Resources workspace, Resources tab, dates were incorrectly displayed in the Assignments spreadsheet. This issue has been fixed.

Talend

#VAN-342

The Talend component was not able to handle the “projectSelector_Overwritable” field for the Project category due to the underscore. This issue has been fixed.

Timesheet (built-in)

#VAN-243

In the Timesheet (built-in) workspace, Week view, when users were adding tasks to their timesheets, the Remaining effort cell was not appearing correctly. This issue has been fixed.

Vantage SSO

#VAN-202

In Vantage, an "unexpected error" message was displayed when users were logging out. This issue has been fixed.

#VAN-201

In Vantage, users were not able to logout successfully in different tabs. This issue has been fixed.

#VAN-200

In Vantage, the “keep me logged in” button was not working. This issue has been fixed; from now on, the “keep me logged in“ checkbox will be hidden when the Vantage platform is enabled.

#VAN-149

Vantage users were experiencing a session timeout when working on a single platform for a long period of time. This issue has been fixed by handling the “keep alive” for both platforms.

Core Product Enhancements

Authentication

#SCI-2801

The login time has been optimized, resulting in a significant reduction in milliseconds and improved overall performance.

Performance

#SCI-2815

The login has been optimized by eliminating unnecessary loads.

#SCI-2787

A loading optimization has been made across the application.

Core Product Corrected Issues

Commands

#SCI-1178

In the Designer, Forms view, after an email template was deleted in a command list, the email template was no longer available elsewhere. This issue has been fixed; a warning message has been added and will be displayed from now on to avoid any mistakes.

Data Snapshots

#SCI-2821

In the Designer, Scheduled Jobs view, Data Snapshot reports could not be generated. This issue has been fixed.

Data Visualization

#SCI-2791

In the Corporate Data workspace, Resources, Users or Cost items tabs, no data was displayed if users were selecting the Entire Organization in the selector. This issue has been fixed.

#SCI-2758

When users were updating their environment, the operation “Create/Update Tables” was failing for User Defined categories which had large data sets while executing the database conversion. This issue has been fixed.

#SCI-2750

In the Work workspace, Gantt tab, in some rare cases, the tasks’ float was incorrect when the calendar was defined as “All Period”. This issue has been fixed.

Note: The Calendar is defined in the Project Brief dialog box, Definition folder, Dates section.

#SCI-2736

Inside a Text Block, if we had a Timesheet/Assignments loop under a Project loop, it might not return the correct data without adding additional loops. This issue has been fixed.

#SCI-2717

In some cases, when resetting a field that had a default formula field, the values were not taken into account after the cache reset. This issue has been fixed.

#SCI-2522

After upgrading to ProjectAdvantage 2023.01, some forms were not displayed anymore in the Designer, Forms view. This issue has been fixed; a new entry has been added in the log to mention that there are some UI commands in the config (“UI commands are not supported in S7”).

#SCI-2278

Under certain conditions, when the user changed calendars, the wrong calendar was still taken into account. This issue has been fixed.

#SCI-1528

In the Designer, User Roles view, Workspaces tab, when users were adding a new Static Report to a user role, it was not displayed straight away in the HTML5 Client and a reboot was necessary. This issue has been fixed.

Legacy API

#SCI-2805

In ProjectAdvantage build versions subsequent to 2023.05, some performance issues could occur when users were submitting events in their timesheets. This issue has been fixed; the cache has been optimized to avoid an unnecessary reload on fields.

Object/Field Edits

#SCI-2661

When users were typing “Timesheet” in the search bar then selecting the first option corresponding to the Timesheet workspace, an error message was displayed and the workspace was not properly loaded. This issue has been fixed.

#SCI-2543

In the Designer, Workflows view, Global Change Requests Category, when two email templates had the same internal Id, the first template was still used even when the second one was selected. This issue has been fixed; a check based on the email template’s name and internal Id has been added.

Performance

#SCI-2785

An unnecessary reloading was occurring after logout when a user did not have any project locks. This issue has been fixed.

REST API

#SCI-2774

For /labor-assignments REST API POST endpoints, an incorrect error message was returned in the response message. This issue has been fixed.

#SCI-2772

For /cost-item-assignments REST API POST endpoints, an incorrect error message was returned in the response message. This issue has been fixed.

#SCI-2771

For “post new task with invalid project id” requests, an incorrect 500 status code was returned in the response message instead of a 404 status code. This issue has been fixed.

#SCI-2770

For /projects/1007435/tasks REST API GET endpoints, an incorrect 200 status code was returned in the response message instead of a 404 status code. This issue has been fixed.

#SCI-2768

For “Get all Cost item assignments with invalid project id and invalid task id” requests, an incorrect error message was returned in the response message. This issue has been fixed.

#SCI-2555

Filters were not working for Portfolio Folder GET API requests due to an incorrect filter logic. This issue has been fixed.

Scheduled Jobs

#SCI-2423

In some cases, when users were running a Cloud Scheduled Jobs generating a data snapshot with a large data set, the Scheduled Job could not properly finish. This issue has been fixed.

#SCI-1906

Date Fields that were stored directly in the database were not displayed by default in the server timezone. This issue has been fixed.

Security

#SCI-2619

Previously, rich text fields could pose XSS security issues. This issue has been fixed.

Talend

#SCI-2763

In Talend Studio, an exception was thrown when an empty "Query" field was passed. This issue has been fixed.

#SCI-2732

In the Talend component, double quotes were removed from the end of filter query values. This issue has been fixed; from now on, if there are no double quotes at the end of the filter query, they will be added.

#SCI-2706

In the Talend component, for labor assignments, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore to differentiate them from field names having an underscore by default and from field names having an underscore which replaced an empty space.

#SCI-2705

In the Talend component, for cost item assignments, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore to differentiate them from field names having an underscore by default and from field names having an underscore which replaced an empty space.

#SCI-2703

In the Talend component, for users, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore to differentiate them from field names having an underscore by default and from field names having an underscore which replaced an empty space.

#SCI-2700

In the Talend component, for resources, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore to differentiate them from field names having an underscore by default and from field names having an underscore which replaced an empty space.

Default Configuration Enhancements

Project Scheduler

#MIL-4360

In the Work workspace, Gantt tab, Scheduler view mode, Task panel, Transactions & Cost Items tab, Cost Item Assignment dialog box, a new Cost display option has been added to the Time Distribution section.

Default Configuration Corrected Issues

Budget/Finance

#MIL-4423

In the Finance workspace, Cost Transactions dialog box, the “Spreadsheet” button was still displayed for Distributed Transactions even when the Transactions feature was deactivated in the Administration workspace, Setup tab, Finance section. This issue has been fixed.

#MIL-4419

In the Work workspace, Billing tab, Purchase Orders view mode, when a purchase order did not have a name, incorrect information was displayed in the Purchase Order Details view. This issue has been fixed.

Execution

#MIL-4343

In the Work workspace, Tracking tab, By Tasks view mode, Timesheet data coming from the New Assignment mechanism was not displayed. This issue has been fixed.

Portfolio Dashboards

#MIL-4415

In the Portfolio Dashboards workspace, Phases & Gates theme, Supervision report, Filters dialog box, when the user was selecting one or several “Workflow State” filter(s), the selection was not correctly applied in the other reports under the same theme.

#MIL-4323

In the Portfolio Dashboards workspace, Controlling theme, Budget Controlling report, Cost Breakdown dialog box, Distributed Transactions were not correctly displayed in the chart. This issue has been fixed.

Project Dashboards

#MIL-4413

In the Project Dashboards workspace, for built-in and custom themes, the Reports navigation bar was not properly working. This issue has been fixed.

Resource Allocations

#MIL-4346

In the Resources workspace, Resources tab, when a Resource was Allocated, the Total Effort row was not matching the total from all the combined detailed Tasks and Other Published Projects rows. This issue has been fixed.

Resource Assignments

#MIL-3945

In the Resources workspace, Resources tab, the "Total Selected Projects" row was not matching the expected total for the Resources selected in the Filters dialog box. This issue has been fixed.

Resource Management

#MIL-4407

In the Resource Fulfillment workspace, when the user was grouping the view by Organization and selecting the Soft Assignments display option, data related to Hard Assignments were still displayed. This issue has been fixed.

System Requirements

There are frequent changes and additions to the set of specific versions of operating systems, application servers and database servers for which ProjectAdvantage has been tested and certified. Please contact our teams for the latest information in this area.

Servers

  • Application Server: Apache Tomcat 9 with Oracle Java 8 or OpenJDK
  • Data Server: PostgreSQL 12

HTML5 Clients

  • Display resolution: 1366 x 768 (technical minimum), 1600 x 1050 (minimum recommended), 1920 x 1080 or higher (generally recommended).
  • Minimum of 4GB RAM allocated (8GB recommended).
  • Browser
    • Microsoft Edge
    • Microsoft Internet Explorer 10 or 11
    • Google Chrome
    • Mozilla Firefox
    • Apple Safari

ProjectAdvantage Designer

  • Display resolution: 1366 x 768
  • Minimum of 4GB RAM allocated
  • Disk space: 200MB minimum available for ProjectAdvantage.
  • Oracle Java 8 or OpenJDK 8
  • Operating Systems:
    • Windows 7, 8.1, 10 or 11
    • Mac OS X Lion or newer
    • Alpine Linux 3.16.1

Timesheets Mobile Application

  • Being hosted by ProjectAdvantage
  • Product version: 2022.08 and upper versions

Vantage platform

For customers who subscribed only to Plan

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • Product version: 2023.01 and upper versions

For customers who subscribed to Plan and Deliver

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • HPV2 activated on Deliver modules (activated by default for all new Deliver Clients after 2021 Q3)
  • Product version: 2023.01 and upper versions
  • Users will need to allow third-party cookies in their browser

Limitations

The data connector does not work in load balanced environments.