2023.08
This document describes the enhancements, corrected issues, and new features that have been implemented in Vantage and in ProjectAdvantage 2023.08 both in the Core product and in the ProjectAdvantage Default Configuration.
ProjectAdvantage 2023.08 is a maintenance release of ProjectAdvantage 2023.
In Vantage, 3 enhancements have been implemented and 12 issues have been fixed.
In the Core product, 7 enhancements have been implemented and 24 issues have been fixed.
In the ProjectAdvantage Default Configuration, 10 enhancements have been provided and 16 issues have been fixed.
In order to access the different sections, please click on the following links:
- Important Reminders for upgrade
- Vantage Enhancements
- Vantage Corrected Issues
- Core Product Enhancements
- Core Product Corrected Issues
- Default Configuration Enhancements
- Default Configuration Corrected Issues
- System Requirements
Important Reminders for upgrade
- To improve the performance of views displaying the Health Score of multiple projects, we are now using a Health Score that is pre-calculated upon publishing a project as opposed to on the fly. Therefore, upon upgrading to 2021.03 (or higher), please make sure you run once the following Scheduled Job to initialize the project Health Score values: Initialize Project Static Health Score.
Important: For systems with an overwritten Publish command, please make sure to add the new dedicated Command List for the Health Score pre-calculation upon publishing a project: “Project - Publish Project - Continue - Capture Health Score”.
- From the 2023.01 version, to support the implementation of the new Vantage navigation and modules, the Project Dashboards workspace should be added again in the User Roles section of the Designer as the Dashboards workspace doesn't exist anymore.
Vantage Enhancements
Navigation
#VAN-222
In the Designer, Forms section, users set the Deliver environment’s URL when they want to use Vantage. This URL is now synchronized with any URL set in the “boardID”, “cockpitID”, or “planningID” fields. If the Deliver environment’s URL is modified, this will be reflected in all the URLs set in the above-mentioned fields. For instance, an administrator can copy and paste the configuration from a sandbox to a production environment. In this case, all of the “boardID”, “cockpitID”, or “planningID” fields will automatically be modified to the correct Deliver environment’s URL.
Timesheet (built-in)
#VAN-241 (*Added on 02/01/2024)
In the Timesheet (built-in) workspace, the Remaining Effort was displayed in hours even when it was set to be displayed in days. This issue has been fixed.
#VAN-232
In the Timesheet (built-in) workspace, team members now have the opportunity to import projects and tasks from the previous week or month in their timesheets.
Note : Users can no longer access the Timesheet cards panel by clicking on the “Previous week” or “Previous month” label, but on the button displaying the date in the Time Navigation panel.
#VAN-74
In the Timesheet (built-in) workspace, Week view, from now on, when tasks from the same project are imported into the timesheet then closed, the “Closed” label is shown for the tasks but not the project which they belong to.
Vantage Corrected Issues
Data Connector
#VAN-192
When users were setting a date in Plan, the date was shown as one day earlier in Deliver. The issue was caused by the timezone, which was different in Plan and Deliver. This issue has been fixed.
Navigation
#VAN-370
In Vantage, an extra “//” was added to the BoardsID/PlanningsID/CockpitsID field when users were updating the URL with an extra value in the Designer, Forms section. This issue has been fixed.
#VAN-143
In the Administration workspace, Team tab, Project Team sub-tab, when the user wanted to add resources to the Project Team, the arrow displayed in the Resource selection popup was not correctly oriented. This issue has been fixed.
Timesheet (built-in)
#VAN-334
In the Timesheet (built-in) workspace, in some cases, the “Recall” button was not displayed. This was caused by remaining non-submitted assignments on deactivated projects. This issue has been fixed; from now on, only active projects will be filtered.
#VAN-332
In the Timesheet (built-in) workspace, Month view, Task popup, when the user was entering a value containing a comma in the Suggested remaining effort cell, the value was incorrectly converted. This issue has been fixed.
#VAN-331
In the Timesheet (built-in) workspace, Week view, when the user was clicking on the blue clock at the tasks level, the planned value was not automatically applied. This issue has been fixed.
#VAN-306
In the Designer, Forms section, when the user was modifying a Board ID, the value was not updated after saving the change. This issue has been fixed; from now on, when users modify the value of a Board ID, workspace type or module name, the value is properly saved and displayed.
#VAN-244
In the Timesheet (built-in) workspace, Week view, tasks could not be removed from timesheets. This issue has been fixed.
#VAN-179
In the Timesheet (built-in) workspace, Week view, users were not able to modify the Total Effort on tasks for which the Planned Effort had already been applied. This issue has been fixed.
#VAN-163
In the Timesheet (built-in) workspace, Month view, when the user was selecting a custom period then clicking on the white clock to apply the planned effort, the planned effort was applied to the whole month instead of the selected custom period. This issue has been fixed.
#VAN-162
In the Timesheet (built-in) workspace, Month view, when a task’s name was too long, it could overlap the Remaining effort cell. This issue has been fixed.
Core Product Enhancements
Data Visualization
#SCI-2582
In the Work workspace, Gantt tab, it is now possible to see the gaps when resources are absent through the "Hammock Assignment Mode”.
#SCI-1255
From now on, built-in and user-defined “parent” Summary fields will behave the same way as a “Unique” field instead of as a list. This will help to make most of the “Group By” data views more user-friendly.
#SCI-2364
In the Corporate Data workspace, Users tab, User Identification dialog box, a new field has been introduced for setting the currency. When users modify their currency within their settings, the corresponding field is automatically updated in the Users tab.
Designer
#SCI-2309
In the Designer, Fields view, Fields tab, Global Category, User Defined sub-tab, users can now select the “Workflow State” and “Workflow State Vote” options in the Pick List column.
Object/Field Edits
#SCI-2636
In the Administration workspace, Documents tab, the maximum size when importing a document is now 30 MB (it was 10MB previously).
REST API
#SCI-2046
In the REST API, the “SHA-256” hash key has been added to the data snapshots in order to control their integrity. The key is also present in the “getDatasnapshots” endpoint response.
Security
#SCI-2439
In order to track which user has modified critical data in the product, a security login has been introduced in multiple areas such as User Roles, User, Passwords, and Login. In the Designer, all changes applied in the Email, Login, Purge and Organizations will now also be tracked.
Core Product Corrected Issues
Authentication
#SCI-1318
Some users were experiencing a session timeout earlier than the configured time in load-balanced environment setups. This issue has been fixed.
Commands
#SCI-2253
In the Home Page workspace, Status Reports tab, status reports were sometimes created twice after the user had clicked on the “Submit” button. This issue has been fixed.
Data Visualization
#SCI-2615
In the Resource Validation workspace, Timesheets tab, the “Status Num” and “Summary Status Num” fields were incorrectly displayed when only a non-working day was set. This issue has been fixed.
#SCI-2278
Under certain conditions, when the user changed calendars, the wrong calendar was still taken into account. This issue has been fixed.
#SCI-1791
In the HTML5 Client, modifying a time zone while setting a due date using the date picker calendar resulted in an incorrect calculation due to daylight saving. This issue has been fixed.
Designer
#SCI-2664
In the Designer, Permissions and Workflows sections, the scrollbar was missing in the Category dropdown list. This issue has been fixed; a scrollbar has been added.
#SCI-2123
In the Designer, some users were experiencing a session timeout earlier than the configured time in load-balanced environment setups. This issue has been fixed.
Domain Config
#SCI-2622
When users were updating their environment, the operation “Create/Update Tables” was failing when the Cost Items names were empty. This issue has been fixed.
Legacy API
#SCI-2630
In ProjectAdvantage build versions subsequent to 2023.05, some slowdown could happen when retrieving the Resources’ timesheets. This issue has been fixed.
Object/Field Edits
#SCI-2675
In the Talend component, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore.
#SCI-2000
In the Corporate Data workspace, Resources tab, Availability column, when the user was editing the “Date” field, an incorrect error message was displayed if an identical date was selected. This issue has been fixed.
#SCI-1234
In the HTML5 Client, the search field filter was not cleared when the user was navigating to the workspace via a link. This issue has been fixed.
Performance
#SCI-2325
In the Portfolio Dashboards workspace, Phases & Gates theme, when the user was launching the Gantt report, an error message was displayed. This issue has been fixed.
REST API
#SCI-2497
In the REST API, the data types required for the same fields were different for the Get and Post requests for Portfolio folders. This issue has been fixed.
#SCI-2494
In the REST API, the data types required for the same fields were different for the Get and Post requests for Organization folders. This issue has been fixed.
#SCI-2449
In the REST API, the endpoint for modifying the calendar’s work ranges was not properly working. This issue has been fixed.
Security
#SCI-2651
There was a SQL Vulnerability in the Data Snapshots workspace. This issue has been fixed.
Talend
#SCI-2707
In the Talend component, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore to differentiate them from field names having an underscore by default.
#SCI-2674
A “NullPointerException” could occur when users were running the Talend job for the Timesheet category. This issue has been fixed.
#SCI-2672
In the Talend component, empty spaces were automatically replaced with a single underscore, which was causing an issue while calling the ProjectAdvantage APIs with guess schema fields. This issue has been fixed; empty spaces are now replaced with a double underscore.
#SCI-2649
The Talend component was not able to handle the “projectSelector_Overwritable” field for the Project category due to the underscore. This issue has been fixed.
Timesheet (built-in)
#SCI-2686
In the Designer, User Roles section, Team Member User Role, Workspaces tab, when the Timesheet (built-in) workspace was set as the default workspace, the workspace was blank upon login. This issue has been fixed.
#SCI-2673
In the Timesheet (built-in) workspace, Week view, when users were entering a value in the “Suggested remaining effort” cell in the Task popup, the “Remaining effort” value was incorrectly displayed in days instead of hours in the Tasks panel. This issue has been fixed.
#SCI-2652
In the Timesheet (built-in) workspace, Week view, an error message was sometimes displayed when the user was clicking on the Remaining effort cell in the Tasks panel. This issue has been fixed.
Default Configuration Enhancements
Administration
#MIL-4405
In the Corporate Data workspace, Users tab, User Identification dialog box, Identification section, a new field has been added to set the currency.
#MIL-4395
In the Data Snapshots workspace, Data Snapshot - Objects Statistics folder, new sections have been added to provide more details about the Resources data.
#MIL-4225
In the System Settings workspace, General Settings folder, General Options tab, Display Controls section, maximum values have been increased from 150 to 500.
Project Scheduler
#MIL-4040
In the project filters, there is now a new overwritable exposed filter called "Project Selector_Overwritable". This filter has been added to the filters of the different project-based selectors used for workspaces and can be overwritten for any customization purposes.
Strategy Execution
#MIL-4366
In the Administration workspace, Setup tab, Home Page Features section, a new attribute is available to include the Project’s Benefits in the Dashboards for valuation.
#MIL-4365
In the Home Page workspace, Benefits tab, as soon as a Benefit is attached to the Project, the Project Manager is now able to select directly its corresponding Unit and Value Type.
Note: All legacy Benefits Attachments already created at the Project level will preserve the settings that were defined in the System Data workspace, Benefits tab, Global Benefits sub-tab.
#MIL-4364
In the Home Page workspace, Benefits tab, Add a Benefit command, a new "Type" column has been added.
Note: The "Type" column has also been added for the Add multiple Benefits command.
#MIL-4322
In the Project Dashboards and Portfolio Dashboards workspaces, a new Benefits report has been added under the Finance theme.
Note: A set of corresponding settings has been implemented alongside the reports in the System Settings workspace, Projects Settings and Portfolio Settings folders, Dashboards tabs.
#MIL-4320
In the Finance workspace, Savings dialog box, a new Benefits tab has been added. The content of the view displays the Benefits attached to the selected project of “Cost” Unit and “Distributed” Value Type. It includes a Charts section with the "Benefits vs. Costs" and "Benefits by Type" charts available, as well as a spreadsheet that lists the Benefits with their distributed values. Those Benefits contribute to the Savings of a project and therefore allow project managers to get a quick overview.
Styling
#MIL-4387
To be consistent with the new platform, a new set of icons and a CSS update have been rolled out in the entire Solution.
Default Configuration Corrected Issues
Administration
#MIL-4410
In the Designer, Scheduled Jobs section, an incorrect filter was applied for the “Project Logs - Deactivate” and “Project Logs - Publish & Reset” scheduled jobs. This issue has been fixed.
Budget/Finance
#MIL-4402
In the Finance workspace, Home Page view mode, Cost Transactions dialog box, Distributed Transactions spreadsheet, when multiple projects were selected, only one project was displayed. This issue has been fixed.
#MIL-4091
In the Portfolio Center workspace, Budget tab, Portfolio Budget view mode, the Total Budget row was not correctly filtered when a specific Cost Center was selected. This issue has been fixed.
#MIL-3615
In the Portfolio Center workspace, Budget tab, Portfolio Budget view mode, the Cost Center Brief dialog box displayed incorrect information about the budget. This issue has been fixed.
Execution
#MIL-4373
In the Resource Validation workspace, Timesheet Details full screen view, the colors displayed were different than shown in the Legend popup. This issue has been fixed.
Integration
#MIL-4368
In the Home Page workspace, Home tab, Notes dialog box, when a new note was added, no notification was sent in Teams. This issue has been fixed.
Project Management
#MIL-4406
In the Home Page workspace, Home tab, the landing screen took a very long time to load. This issue has been fixed.
#MIL-4258
In the Home Page workspace, when the user was creating a new project from an existing one without switching the “Import Baselines” button on, some baselines from the source project were still imported. This issue has been fixed.
#MIL-4153
In the Project Brief dialog box, Resources folder, the Total Effort was not accounted for for Soft Assignments. This issue has been fixed.
Project Scheduler
#MIL-4264
In the Work workspace, when the user was fulfilling a soft assignment on a hammock task with a resource that had non-working days defined in its calendar within the assignment’s range, the original effort was not completely fulfilled. This issue has been fixed.
Resource Management
#MIL-4380
In the Organization Center workspace, Resource Details tab, when several organization branches were selected, resources from other organization branches could be selected in the Resources List panel. This issue has been fixed.
#MIL-4363
In the Resources workspace, Resources tab, the “Total Selected Project” row was not reflecting the “Contract Type” filter applied in the Filters dialog box. This issue has been fixed.
Status Report
#MIL-4350
In the Home Page workspace, Status Reports tab, Last Submitted panel, when the user was selecting the “Print Specific Sections” command, an error message was displayed in the Print Selection popup. This issue has been fixed.
Strategy Execution
#MIL-4396
In the Home Page workspace, Benefits tab, Track Values dialog box, the date was not displayed according to the default format set in the Designer. This issue has been fixed.
Work Items
#MIL-4382
In the Client Portal workspace, Deliverables full screen view, Inbox tab, the Group By feature was not properly working. This issue has been fixed.
#MIL-4268
In the Client Portal workspace, Create a New Deliverable dialog box, it was not possible to create a deliverable at the Project level when the “Enable Portfolio Work Items” setting (located in the System Settings workspace, Work Management Settings folder, Display Preferences tab, Portfolio Work Management section) was deactivated. This issue has been fixed.
System Requirements
There are frequent changes and additions to the set of specific versions of operating systems, application servers and database servers for which ProjectAdvantage has been tested and certified. Please contact our teams for the latest information in this area.
Servers
- Application Server: Apache Tomcat 9 with Oracle Java 8 or OpenJDK
- Data Server: PostgreSQL 12
HTML5 Clients
- Display resolution: 1366 x 768 (technical minimum), 1600 x 1050 (minimum recommended), 1920 x 1080 or higher (generally recommended).
- Minimum of 4GB RAM allocated (8GB recommended).
- Browser
- Microsoft Edge
- Microsoft Internet Explorer 10 or 11
- Google Chrome
- Mozilla Firefox
- Apple Safari
ProjectAdvantage Designer
- Display resolution: 1366 x 768
- Minimum of 4GB RAM allocated
- Disk space: 200MB minimum available for ProjectAdvantage.
- Oracle Java 8 or OpenJDK 8
- Operating Systems:
- Windows 7, 8.1, 10 or 11
- Mac OS X Lion or newer
- Alpine Linux 3.16.1
Timesheets Mobile Application
- Being hosted by ProjectAdvantage
- Product version: 2022.08 and upper versions
Vantage platform
For customers who subscribed only to Plan
- Installation:
- POD 11 is required if hosted by ProjectAdvantage
- An Hydra server is required if on premise
- Product version: 2023.01 and upper versions
For customers who subscribed to Plan and Deliver
- Installation:
- POD 11 is required if hosted by ProjectAdvantage
- An Hydra server is required if on premise
- HPV2 activated on Deliver modules (activated by default for all new Deliver Clients after 2021 Q3)
- Product version: 2023.01 and upper versions
- Users will need to allow third-party cookies in their browser
Limitations
The data connector does not work in load balanced environments.