Planview ProjectAdvantage 2026.08 is a maintenance release of Planview ProjectAdvantage 2026.

In the Core product, 1 enhancement has been implemented and 17 issues have been fixed.

In the Default Configuration, 13 issues have been fixed.

In Deliver, 3 issues have been fixed.

In order to access the different sections, please click on the following links:

Important Reminders for upgrade

  • From the 2023.01 version, the Project Dashboards workspace should be added again in the User Roles section of the Designer as the Dashboards workspace doesn't exist anymore.
  • In order to complete the upgrade to newer Planview ProjectAdvantage versions, administrators must update the “Popup” column with the correct Forms in the Designer, Search view, as follows:
  • “Global Actions” Category → Popup - Action Card (Briefs)
  • “Global Change Requests” Category → Popup - Change Request Card (Briefs)
  • “Global Deliverables” Category → Popup - Deliverable Card (Briefs)
  • “Global Issues” Category → Popup - Issue Card (Briefs)
  • “Global Risks” Category → Popup - Risk Card
  • From the 2025.12 version, OpenJDK21 is required to launch the Planview ProjectAdvantage Designer and the Java Legacy APIs. For more information, please refer to the “Move to Java 21” product notice.

Core Product Enhancements

Security

#SCI-9242 - Enhanced protection of session data in the browser

As part of an ongoing security audit, session identifiers are no longer stored in the browser's sessionStorage. This reduces exposure of session data in the browser and strengthens overall session security.

Core Product Corrected Issues

Administration Calendar

#SCI-9746

In some scenarios, when users were navigating to the Calendar (Administration) workspace, an error message was displayed and the workspace could fail to open. This issue has been fixed.

Build

#SCI-9835

In the Projects Center workspace, Project Card, Task tab, Task List tab, Task Card, Definition tab, the “Finish Date” and “Duration” fields could incorrectly be changed after upgrading to a newer version. This issue has been fixed.

Built-in Timesheet

#SCI-8484

In the Timesheet (built-in) workspace, daily notes entered on a timesheet could fail to appear on the resource's own Timesheet, even though the notes were saved correctly and remained visible in the legacy Timesheet workspace and in the Resource Validation workspace, Timesheets tab, Timesheet Details full screen view. This affected timesheet periods after a certain date for impacted assignments. This issue has been fixed.

Corporate Data

#SCI-8587

In the Corporate Data workspace, Resources tab, Resource Identification dialog box, Definition tab, Cost & Availability section, when users were copying an End Date set to a year ending in "0" using a two-digit century offset (e.g., January 1, 2070 or January 1, 2050) and pasting it, either into another Resource's “End Date” field or into an external application such as Excel, the year was incorrectly converted by 100 years (e.g., 2070 became 1970, 2050 became 1950). This could also trigger a validation error message when pasting the truncated date into another Resource. This issue has been fixed.

Data Snapshots

#SCI-8538

In the Data Snapshots workspace, When a scheduled "Generate Data Snapshots" job was configured with a specific locale (e.g., fr_FR), the generated file's headings and localized values (such as project nature) were still produced in English instead of the selected language. This issue has been fixed.

Data Visualization

#SCI-9759

In multiple views, when a fiscal calendar was used for the time intervals, the period headers showed an incorrect value instead of the actual period date. This issue has been fixed.

Ideas Center

#SCI-9639

In the Ideas Center workspace, Grid view, the names of ideas previously created with a read-only workflow were displayed as “N/A”, even though they were not supposed to be visible to users with read-only permissions. This issue has been fixed.

Performance

#SCI-9692

In some scenarios, users could experience intermittent 502, 503, and 504 type errors affecting the application availability after upgrading to a newer version. This issue has been fixed.

#SCI-8218

In the HTML5 Client, when users were using the global Search function, results from an earlier, broader search could replace results for the most recently typed search. This could cause the correct result to appear briefly and then disappear, particularly in environments with a large number of records. This issue has been fixed.

Project Dashboards

#SCI-9769

In the Project Dashboards workspace, Project Monitoring theme, the context could be lost when users were opening the Status Overview report in a new browser tab. This issue has been fixed.

Projects Center - Project Card - Status Report

#SCI-9703

In the Projects Center workspace, Project Card, Overview tab, Status Reports sub-tab, when filtering by a custom tag, the applied filter value was lost after refreshing the screen (whether refreshed via the in-app Refresh button or the browser refresh. The Resources tab, Resources assignments sub-tab, was also affected when filtering by job classification. These issues have been fixed.

Projects Legacy - Finance

#SCI-8347

In the legacy Finance workspace, Budget dialog box, when users were attempting to create a new Cost Center, an error message could be displayed when the associated project name contained a special character, preventing the Cost Center popup from opening. This issue has been fixed.

Reports

#SCI-9732

In the Reports workspace, an error message could be displayed when users were trying to launch a report. This issue has been fixed.

Resource Forecast

#SCI-9776

In the Resource Forecast workspace, when the “Set Requested/Committed Effort Format” setting was set to “FTE%”, fulfilling a request with a nominative resource using a commitment rate would freeze the page. After completing the fulfillment, users could no longer change the time range, adjust the distribution, or add columns. This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, Resource Settings folder, Allocations & Commitments tab, Requests & Commitments Options section.

REST API

#SCI-9247

In some scenarios, the Work Ranges REST API could return work start/end times that were off by an extra hour during Daylight Saving Time periods (e.g. British Summer Time), even though timestamps were marked as UTC. This issue has been fixed.

#SCI-8436

In some scenarios, API requests could fail with a 400 status "not a known currency code" error if data referenced a currency that had been removed from the system. This issue has been fixed.

System Data

#SCI-9736

In the System Data workspace, More button, the menu options no longer showed a highlight on hover or an arrow indicator for selection. This issue has been fixed.

Default Configuration Corrected Issues

Projects Center

#MIL-6315

In the Projects Center workspace, Board view, main toolbar, the default view preferences were not displayed. This issue has been fixed.

#MIL-6282

In the Projects Center workspace, Grid view, when users were selecting several projects, the Open selection (1-137_img_0.png) button was sometimes not visible in the main toolbar, This issue has been fixed.

Projects Center - Project Card - Finance

#MIL-6305

In the Projects Center workspace, Project Card, Finance tab, Budget dialog box, when the Project Manager used the "Update from Total Cost" command, the transactions linked to a task with an inherited Cost Center were not taken into account. This issue has been fixed.

Projects Center - Project Card - Phases & Gates

#MIL-6309

In the Projects Center workspace, Project Card (multi project), Phases & Gates tab, Gates Review Management section, the “Group By” button was incorrectly available in the main toolbar. This issue has been fixed.

Projects - Projects Center - Risks

#MIL-6302

In the Risks Center workspace, Risk Card, the “Other Assignees” field was missing. This issue has been fixed.

#MIL-6295

In the Projects Center workspace, Project Card, Risks tab, Risk Card, when users were clicking on the More (1-137_img_1.png) button, then selecting the Copy command, the Name, Owner, and Cause were not copied in the new risk. This issue has been fixed.

Resource Forecast

#MIL-6319

In the Resource Forecast workspace, when users were selecting the “Grouped by project” view in the main toolbar, no resource requests were displayed in the grid. This issue has been fixed.

#MIL-6318

In the Resource Forecast workspace, Fulfill request dialog box, when users were fulfilling a second request using the With commitment rate option during the same user session, commitments could be created with incorrect start/finish dates, sometimes extending past the request's end date, or in some cases starting before the request's start date. This issue has been fixed.

#MIL-6317

In the Resource Forecast workspace, the Actual Effort column displayed FTE% values using a ceiling function instead of standard rounding, overstating the actual utilization. For instance, an underlying value of 0.26 FTE% was displayed as 1% instead of 0%, and values like 0.3 or 0.5 FTE% were also rounded up to 1%. This created inconsistent results compared to other effort units (days, hours, FTE) and could mislead capacity and forecast decisions. This issue has been fixed.

#MIL-6312

In the Resource Forecast workspace, Fulfill request dialog box, when resource managers were fulfilling requests with nominative resources using the With commitment rate option, commitments were created in a uniform way and were not editable. This issue has been fixed.

#MIL-6310

In the Resource Forecast workspace, Organization, Job Classification, and Skills were not visible for Resource Commitment rows. This issue has been fixed.

Status Report

#MIL-6313

In the Projects Center workspace, Project Card, Overview tab, Status Reports sub-tab, when users were selecting the View Details command to prompt the full report popup, Phases & Gates and Macro-Planning sections, some information was truncated and not entirely visible. This issue has been fixed.

Template Center

#MIL-6306

In the Templates Center workspace, Template Card, the Phases & Gates tab was not displaying the correct user interface. This issue has been fixed.

Deliver Corrected Issues

APM

#DELIVER-1435

In the APM, after adding or modifying a field in an object model, the data model could remain locked with the "Update in progress" status indefinitely if the background update task failed. This issue has been fixed; from now on, the lock is always released when the update ends, even in case of error.

Gridboard

#DELIVER-1908

In the Gridboard API, numerous “NoSuchFieldException” errors ("No field ag-Grid-AutoColumn in schema") were being logged during grid queries, affecting request-time performance and log volume. This issue has been fixed.

Other

#DELIVER-1759

In some scenarios, when deleting a custom field that was referenced by a formula field, the configuration could be published without any warning or error, silently leaving the formula field broken. This issue has been fixed.

System Requirements

There are frequent changes and additions to the set of specific versions of operating systems, application servers and database servers for which Planview ProjectAdvantage has been tested and certified. Please contact our teams for the latest information in this area.

Note: Users' system clocks must be regularly and accurately synchronized with the internet.

Servers

  • Application Server: Apache Tomcat 10.1, or 11 with Oracle Java 21 or OpenJDK21

Important: The use of OpenWebStart is mandatory to open the Designer.

  • Data Server: PostgreSQL 14, PostgreSQL16

HTML5 Clients

  • Display resolution: 1366 x 768 (technical minimum), 1600 x 1050 (minimum recommended), 1920 x 1080 or higher (generally recommended).
  • Minimum of 4GB RAM allocated (8GB recommended).
  • Browser
    • Microsoft Edge
    • Google Chrome
    • Mozilla Firefox
    • Apple Safari

Planview ProjectAdvantage Designer

  • Recommended language: English
  • Display resolution: 1366 x 768
  • Minimum of 4GB RAM allocated
  • Disk space: 200MB minimum available for Planview ProjectAdvantage.
  • Oracle Java 21 or OpenJDK 21
  • Operating Systems:
    • Windows 7, 8.1, 10 or 11
    • Mac OS X Lion or newer
    • Alpine Linux 3.16.1

REST API

  • Supported language: English

Timesheets Mobile Application

  • Being hosted by Planview ProjectAdvantage
  • Product version: 2022.08 and upper versions

Planview ProjectAdvantage platform

Users will need to enable third-party cookies to work within Planview ProjectAdvantage. For more information regarding third-party cookies, please refer to the “How to allow third-party cookies” documentation.

For customers who subscribed only to ProjectAdvantage

  • Installation:
    • POD 11 is required if hosted by Planview ProjectAdvantage
    • An Hydra server is required if on premise
  • Product version: 2023.01 and upper versions

For customers who subscribed to ProjectAdvantage and Deliver

  • Installation:
    • POD 11 is required if hosted by Planview ProjectAdvantage
    • An Hydra server is required if on premise
  • HPV2 activated on Deliver modules (activated by default for all new Deliver Clients after 2021 Q3)
  • Product version: 2023.01 and upper versions
  • Users will need to allow third-party cookies in their browser

Limitations

The data connector:

  • Does not work in load balanced environments.
  • Is not compatible with Cloud Scheduled Jobs.
  • Is not compatible with dedicated API servers.