Skip to main content

 

  • arrow icon

 

Planview Customer Success Center

2023.02

This document describes the enhancements, corrected issues, and new features that have been implemented in Vantage and in ProjectAdvantage 2023.02 both in the Core product and in the ProjectAdvantage Default Configuration.

ProjectAdvantage 2023.02 is a maintenance release of ProjectAdvantage 2023.

In Vantage, 5 issues have been fixed.

In the Core product, 15 issues have been fixed.

In the ProjectAdvantage Default Configuration, 5 enhancements have been provided and 22 issues have been fixed.

In order to access the different sections, please click on the following links:

Important Reminders for upgrade

  • To improve the performance of views displaying the Health Score of multiple projects, we are now using a Health Score that is pre-calculated upon publishing a project as opposed to on the fly. Therefore, upon upgrading to 2021.03 (or higher), please make sure you run once the following Scheduled Job to initialize the project Health Score values: Initialize Project Static Health Score.
Important: For systems with an overwritten Publish command, please make sure to add the new dedicated Command List for the Health Score pre-calculation upon publishing a project: “Project - Publish Project - Continue - Capture Health Score”.
  • From the 2023.01 version, to support the implementation of the new Vantage navigation and modules, the Project Dashboards workspace should be added again in the User Roles section of the Designer as the Dashboards workspace doesn't exist anymore.

Vantage Corrected Issues

Timesheet (built-in)

#VAN-53

In the Timesheet (built-in) workspace, Month view, users could not input time then submit their timesheet without seeing a “Rule violations” message appear on screen. This issue has been fixed.

#VAN-51

In the Timesheet (built-in) workspace, no “Data format error” message was appearing when non allowed characters were entered in the daily effort cells. This issue has been fixed.

#VAN-48

In the Timesheet (built-in) workspace, Week view, if the Project Manager had sent back the timesheet with a rework comment, the dates range shown for the rework comment was different than the timesheet’s dates range. This issue has been fixed.

#VAN-47

In the Timesheet (built-in) workspace, Week view, if a value had been entered for the week’s total, the distributed Effort was not removed at the day level when the user was deleting it. This issue has been fixed.

#VAN-39

In the Timesheet (built-in) workspace, when the user was clicking on “About ProjectAdvantage”, the About ProjectAdvantage popup was not displaying correctly. It was also not possible to click on the “License” tab, or on the “Close” and “Save” buttons. This issue has been fixed.

Core Product Corrected Issues

REST API

#SCI-2249

When resources/users were updated via a PATCH endpoint, they could either disappear or be deleted and some data synchronization issues could occur. This issue has been fixed.

#SCI-2168

A 204 Status code response was returned when the user attempted to delete a currency format with an invalid ID. This issue has been fixed.

Data Visualization

#SCI-2275 (*Added on 7th April 2023)

In the Resource Dashboards workspace, Time Tracking theme, Timesheets report, an error message was displayed when the user was changing the zoom value. This issue occurred when the Date Default Format was set to the European Date Format (dd/mm/yy) in the Designer, Fields section, Default Format tab, which caused partial submits of the timesheet to fail when the week was split over two months. This issue has been fixed.

#SCI-2240

In the Administration workspace, clicking on a table in a form was causing the entire form to jump to the right when the user was connected in Hebrew. This issue has been fixed.

#SCI-2117

In the Work workspace, when the user was creating a new project from an existing one, an “Unable to save project” error message was displayed and the new project was not created. This was due to a “NullPointerException” error that was occurring while saving the project. This issue has been fixed.

#SCI-2223

In smart grids, Effort columns were displayed in round up values instead of the correct precision value a “<No Override>” or “(hidden)” Time Scale was chosen in the Designer, Forms section, Edit Grid Properties popup, Columns tab. This issue has been fixed.

#SCI-2287

In load balanced environments, projects were no longer displayed on a server after they had been published on another server. This was due to project cache issues which caused an inconsistency between session data. This issue has been fixed.

#SCI-2190

In the Portfolio Dashboards workspace, some projects could be missing in the Excel download of custom Portfolio reports. This issue has been fixed.

#SCI-2194

In some cases, even though a command was functioning correctly, users could encounter a message when they attempted to log out, warning them that an action was still running in the background. This issue has been fixed.

Object/Field Edits

#SCI-2201

In the Work workspace, Task List tab, an error was displayed when the user was clicking on any of the “Insert tasks” command options and the error message displayed was incorrect. This issue has been fixed.

#SCI-2185

In the Timesheet workspace, after switching languages, some intervals available in the drop-down list that seemed to be properly translated were not correctly recognized when selected. This issue has been fixed.

#SCI-2236

In the Work workspace, Gantt tab, when the user was deleting a hard assignment on a task that had a baseline, the Baseline Start and Baseline Finish were also deleted. This issue has been fixed.

Commands

#SCI-2089

In the Timesheet workspace, it was not possible to submit timesheets with 0h on days which had Planned Effort. This issue has been fixed.

#SCI-175

After rolling back a document to a version associated with a different file, the “File” field was not displaying the correct name unless the server was restarted. This issue has been fixed.

Data Snapshots

#SCI-1678

In the Data Snapshots workspace, when the user downloaded data in CSV format, the numbers in the “Project_IID” column were displayed in an incorrect decimal format. This issue has been fixed.

Default Configuration Enhancements

Project Scheduler

#MIL-4159

The Replace Generic Resource feature has been rolled out to the "Assign, Replace or Fulfill on the selected Task(s)" Gantt toolbar button in the Work workspace, Gantt tab, as well as the Resources workspace, Resources and Tasks tabs.

#MIL-3031

In the Work workspace, Gantt tab, Theater view mode, a new Presets feature has been implemented. This feature allows each user to save both filters and display options set in the right panel, and load them to be applied later or to other projects.

#MIL-2534

A new "Task New Comment" webhook setup and feature have been added to allow chat notifications when a new comment is created on a task.

Project Dashboards

#MIL-4114

In the Designer, Fields section, Project Category, Formatting tab, two new fields have been created to be used through the API, to connect Plan with Deliver.

Idea/Business Case

#MIL-2694

In the Idea Center workspace, ideas can now be filtered by “Type”.

Note: This new mechanism has been applied for all view modes: Overview, Details, and Analytics.

Default Configuration Corrected Issues

Styling

#MIL-4155

In the Project Administration workspace, Nature column, the options in the drop-down list were not correctly displayed when the Vantage UI was enabled. This issue has been fixed.

Status Report

#MIL-4135

In the Home Page workspace, Status Reports tab, the Phases & Gates header was displayed, even when the corresponding preferences were set off. This issue has been fixed.

#MIL-4044

In the Home Page workspace, Status Reports tab, the "Edit Submitted Status Report" command was not available and Status Reports could not be edited after they had been created. This issue has been fixed.

Project Management

#MIL-4132

In the Work workspace, Tracking tab, Timesheet Details full screen view, if external resources had long names, they were not properly displayed in the left panel cards. This issue has been fixed.

#MIL-3246

In the Finance workspace, Forecast popup, the Cost Items tab was always displayed regardless of whether the corresponding setting was selected or not in the Administration workspace, Setup tab, Resource Management section. The Transactions tab was also always displayed regardless of whether the corresponding setting was selected in the Administration workspace, Setup tab, Finance section. This issue has been fixed.

Resource Dashboards

#MIL-4122

In the Resource Dashboards workspace, Workload theme, Organization Statistics report, Resources sub-tab, when several Organizations were selected, the report only displayed data from the selector’s last selection if the report had been launched in a new browser tab. This issue has been fixed.

#MIL-4117

In the Resource Dashboards workspace, Workload theme, Effort Distribution report, when the report was grouped by Organization or Contract Type, the Baseline figures were not correctly calculated. This issue has been fixed.

#MIL-4077

In the Resource Dashboards workspace, Time Tracking theme, Project Actuals report, the indicators were incorrect when no actual effort was applied to the project. This issue has been fixed.

Portfolio Dashboards

#MIL-4119

In the Portfolio Dashboards workspace, Project Monitoring theme, Overview report, when several Portfolio Folders were selected, the report only displayed data from the selector’s last selection if the report had been launched in a new browser tab. This issue has been fixed.

#MIL-2652

In the Portfolio Dashboards workspace, Controlling theme, Capacity Planning report, projects with no effort in the period were still displayed in the legend of the "Detailed Workload" chart. This issue has been fixed.

Budget/Finance

#MIL-4111

In the Finance workspace, Budget popup, Cost Center brief dialog box, the “Presets” button was overlapping the time distribution navigation. This issue has been fixed.

#MIL-4080

In the Home Page workspace, Connections tab, when viewing a contract from a Parent connection, the “Budget” section was empty if the “Enable Mixed Budget Type” setting was activated. This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, Budget/Finance Settings folder, Global Options tab, Budget section.

Portfolio Simulation

#MIL-4110

In the Portfolio Simulation workspace, after playing a scenario, Analytics view mode, Workload sub-tab, when the Portfolio Manager was grouping the view by Resource, no resource’s name was displayed in the header. This issue has been fixed.

Resource Allocations

#MIL-4100

In the Work workspace, Gantt tab, Fulfill Soft Assignment popup, the Allocated Effort was not respected when a resource that had been directly allocated to a project was selected. This issue has been fixed.

Note: A new "Enable Assignment From Direct Allocation Mono Fulfill Option" setting has been implemented. Once activated, if the resource corresponds to a direct allocation made on the project, and if the allocated effort spans over the task ranges, two options are prompted: "Honor Allocated Effort" or "Use Resource Default Rate". These options are also available when creating a hard assignment and in the Resource workspace, Project Allocations tab, Project Allocations full screen view, Allocations tab.
Note: The aforementioned setting is located in the System Settings workspace, Resource Settings folder, Allocations & Commitments tab, Allocations Options section.

Resource Management

#MIL-4086

In the Resources workspace, Resources and Tasks tabs, the time distribution option shifted when fulfilling a soft or generic assignment. This issue has been fixed.

Resource Validation

#MIL-4063

In the Work workspace, Tracking tab, Timesheet Details full screen view, some tasks could be missing if the "Set "Show Parent Task" Scope" setting was set to "All WBS Hierarchy". This issue has been fixed.

Note: The aforementioned setting is located in the System Settings workspace, Project Settings folder, Time Tracking Options tab, Timesheet Options section.

Template

#MIL-3899

In the Home Page workspace, Home tab, when a Project Manager was creating a new project from a template, an error message was appearing if the new project’s name was identical to the template’s name. This issue has been fixed.

Portfolio Center

#MIL-3880

In the Portfolio Center workspace, Project Supervision tab, Health Score Details popup, the score was sometimes different than the one displayed in the spreadsheet. This issue has been fixed.

Administration

#MIL-3449

In the Administration workspace, when several projects were selected, Supervision tab, the “Print all reports” button was wrapped when the user was connected in German. This issue has been fixed.

Work Items

#MIL-3401

In the Client Portal workspace, Actions full screen view, Board tab, an unwanted "yes" column was displayed. This issue has been fixed.

Phases & Gates

#MIL-3254

In the Work workspace, Phases & Gates tab, under certain conditions, the names of the Gates were not fully readable. This issue has been fixed.

Note: A tooltip is now available to display the Gates’ full names when hovering them.

Risk Management

#MIL-3161

In the Work workspace, Risks tab, Dashboards full screen view, Full List tab, risks were listed twice if the sorting option was set to "Impact Time”, "Impact Cost" or "Created Date". This issue has been fixed.

System Requirements

There are frequent changes and additions to the set of specific versions of operating systems, application servers and database servers for which ProjectAdvantage has been tested and certified. Please contact our teams for the latest information in this area.

Servers

  • Application Server: Apache Tomcat 8.5 with Oracle Java 8 or OpenJDK
  • Data Server: PostgreSQL 10 to 12

HTML5 Clients

  • Display resolution: 1366 x 768 (technical minimum), 1600 x 1050 (minimum recommended), 1920 x 1080 or higher (generally recommended).
  • Minimum of 4GB RAM allocated (8GB recommended).
  • Browser
    • Microsoft Edge
    • Microsoft Internet Explorer 10 or 11
    • Google Chrome
    • Mozilla Firefox
    • Apple Safari

ProjectAdvantage Designer

  • Display resolution: 1366 x 768
  • Disk space: 200MB minimum available for ProjectAdvantage.
  • Oracle Java 8 or OpenJDK 8
  • Operating Systems:
    • Windows 7, 8.1 or 10
    • Mac OS X Lion or newer
    • Alpine Linux 3.16.1

Timesheets Mobile Application

  • Being hosted by ProjectAdvantage
  • Product version: 2022.08 and upper versions

Vantage platform

For customers who subscribed only to Plan

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • Product version: 2023.01 and upper versions

For customers who subscribed to Plan and Deliver

  • Installation:
    • POD 11 is required if hosted by ProjectAdvantage
    • An Hydra server is required if on premise
  • HPV2 activated on Deliver modules (activated by default for all new Deliver Clients after 2021 Q3)
  • Product version: 2023.01 and upper versions
  • Users will need to allow third-party cookies in their browser