The Plan tool has two key components:
Learn more about projectplanning.
You can change dates and the duration of activities and milestones by entering the dates in the WBS, or by using drag and drop functionality in the Gantt.
NOTE
Changing the date of an activity or milestone might affect its parent activities, sub-activities, or dependencies, if any. Undoing a date change will restore all of the affected activities or milestones to their previous state.
When displaying and editing activities and milestones, the Plan tool follows the working and non-working days defined in the Working days settings.
NOTE
If new working or non-working days are added in the Working days settings, the plan might be affected:
Use milestones to describe the important target dates, such as delivery dates.
Add activities to group and visualize the work needed to reach your goals.
To create an activity or milestone:
NOTE
Activities and milestones are initially created on the current day's date. If the current day is a non-working day, activities are automatically moved to the next working day available.
TIP
If you have the need to describe certain activities that cannot start until others have been completed, you can add dependencies to activities.
TIP
Have you already started on a project plan in Microsoft Project? You can easily import it to ProjectPlace.
NOTE
If you’re using the Planview Portfolios – ProjectPlace connector or the PPM Pro – ProjectPlace connector, the project schedule is synced to your ProjectPlace workspace, and you will not be able to add activities and milestones in ProjectPlace.
You can create a hierarchy of activities in a WBS (Work Breakdown Structure) if needed. There are two methods to do this.
To add activities and milestones, then create the hierarchy:
To create an activity directly in the correct position within the hierarchy:
NOTE
Parent activities are only regarded as containers and not work to be done. Therefore, you can not estimate and report time on the parent activities. Cards can only be added to the activities on the lowest level in the hierarchy.
TIP
If the activity already has a sub-activity, you can also go to the activity detail pane and add sub-activities in the Break down the activity into sub-activities section.
NOTE
If you’re using the Portfolios – ProjectPlace connector or the PPM Pro – ProjectPlace connector, the project schedule is synced to your ProjectPlace workspace, and you will not be able to create sub-activities in ProjectPlace.
Click an activity, either in the Work Breakdown Structure or in the Gantt, to open the detail pane where you can see and change all related information.
NOTE
Parent activities cannot be set to Done. However, the parent activities status is inherited from the status of all its sub-activities and milestones.
TIP
Select multiple activities to edit their label, which board they are connected to, locked/unlocked status, and done/not done status. You can also convert multiple activities to milestones (but remember that certain types of activities, such as parent activities or activities that are connected to boards, cannot be converted into milestones.)
NOTE
If you’re using the Planview Portfolios – ProjectPlace connector or the PPM Pro – ProjectPlace connector, the project schedule is synced to your ProjectPlace workspace and cannot be edited.
When it is time to involve the team that is going to do the work, connect the activity to a Board. If you need to prepare by breaking down the work into actionable cards, this is where you do it. You can also connect existing cards to the activity.
To connect the activity to a board:
TIP
Select more than one activity and repeat the steps above to quickly connect multiple activities to the same board. (Parent activities cannot be connected to boards.)
To break down the activity into cards:
NOTE
Cards can only be added to activities on the lowest level in the hierarchy since the parent activities are only regarded as containers and not work to be done.
To connect existing cards to the activity:
NOTE
If you select a card that is visible on a Board, and the activity is not connected to that board and the card will no longer be visible on the board.
You can duplicate an activity in the current Plan, or copy it to another workspace that you have Read and write access to.
When an activity is duplicated or copied, the date range, label, attachments, estimated time, and custom fields will be copied over to the new activity. However, the reported time, dependencies, previous history, and comments are not included on the new activity. Locked activities that are duplicated or copied will become unlocked and activities that are set to Done will be changed to the Not done setting.
Duplicating or copying a parent activity will include all child activities and milestones within the parent activity hierarchy.
When activities and sub-activities are connected to boards and cards are duplicated or copied, cards will be duplicated but connections to boards are removed. For duplicated cards, all settings such as due date, labels, attachments, checklist items, points, estimated time, and customized fields will remain the same. Assignee, reported time, dependencies, and comments are not included in the duplication.
To duplicate an activity:
To copy an activity to another workspace:
NOTE
The Copy to another workspace option is present only if there is at least one workspace in which you have Read and write access to the Plan tool.
Click a milestone in the Gantt or the WBS to open the detail pane where you can see and change all related information.
NOTE
Converting a milestone into an activity causes dates recalculations if the milestone's original date is set on a non-working day. In this case, the newly converted activity's dates are automatically moved to the next working day available.
TIP
Select multiple milestones to edit their label, locked/unlocked status, and done/not done status. You can also convert multiple milestones to activities.
You can duplicate a milestone in the current Plan, or copy it to another workspace that you have Read and write access to.
When a milestone is duplicated or copied, the due date, label, attachments, and custom fields will be copied over to the new milestone. The dependencies, previous history, and comments are not included on the new milestone. Milestones set to Done will be changed to Not done on the new milestone.
To duplicate a milestone:
To copy a milestone to another workspace:
NOTE
The Copy to another workspace option is present only if there is at least one workspace in which you have Read and write access to the Plan tool.
You can filter the activities and milestones within the plan based on attributes such as status, plan items, date range, warnings, labels, boards, cards, risks & issues, and custom fields. Click the Filter icon in the toolbar to display the filter options on the left side of the window.
Once you have started to apply the filter you can alternate between Show Only or Highlight view found at the top of the filter options.
Clicking on the Show Only icon will display a filtered view of the plan in which activities and milestones that you are not filtering for will be hidden entirely from the plan.
Clicking on the Highlight icon will display a filtered view of the plan in which activities and milestones that you are not filtering for will be dimmed.
Use labels to categorize different cards. Each label is represented by a specific color. Labels can be used, for example, to define what role or competence the person that performs the work should have, or the type of work the card represents.
You can group cards on a board by labels to get an overview, and to focus on the cards with a specified label.
To customize labels:
If your organization uses ProjectPlace where a workspace Plan is connected to a Portfolios or PPM Pro project schedule, the ProjectPlace Workspace Plan is not editable and is available with a read-only status. The only operations available in this case are:
If you’re using the Portfolios – ProjectPlace connector, you’ll build out the project schedule (consisting of phases, activities, and milestones) in the Portfolio Resource Management application and sync it to your ProjectPlace workspace. ProjectPlace cards flow back into Portfolios as action items, capturing team member progress in the project schedule. Learn more here.
If you’re using the PPM Pro – ProjectPlace connector, tasks are synced from the PPM Pro project to your ProjectPlace workspace. Creating new tasks in PPM Pro results in the creation of corresponding ProjectPlace activities, and resources on the project Staffing screen are added automatically to the ProjectPlace workspace Members tab. Learn more here.