Work Items (Projects, Milestones, Tasks, etc.) are displayed in detailed modular views. This section describes the different panels and elements in the modular view.
Go to:
AdaptiveWork's default view options vary from module to module.
The figure below shows the Work Items module default view options.
The Work Items module supports adding AdaptiveWork's Team Panel to the view.
The addition of the Team Panel creates a team-centric view to better assist with team collaboration on all deliverables.
The grid is AdaptiveWork's standard data table display for viewing, managing and editing data and items in most modules.
A grid display is one of three display type options used to configure several of the out-of-the-box view options available in the View Navigator for most modules.
Using the Time Range Filter enables filtering the grid to show items and events occurring during the actual period/date(s) defined.
Clicking the icon, located above the ribbon enables managing grid column sets which can then be further filtered and sorted.
The Work Items module can be searched and filtered for items and data using the Contextual Search and the Time Range Filter.
The Results Format can be customized to return specific type of results.
NOTE
You can search globally in AdaptiveWork by using the Global Search tool.
The Work Items module ribbon, located under the masthead (at the top-left) provides controls for performing actions on selected items.
The Work Items module grid displays include the Relations Panel, located on the right-hand side of the screen.
The Relations Panel displays any related items, such as assigned resources, files, and discussions, etc.) of a selected item type in the grid, and enables working with the related items while staying in context of your original view.
You can also view cases including bugs, issues and requests as separate relation items in the Related Items Panel.
The panel is blank when multiple items are selected.
The Scheduling Status of work items is displayed with either a Green, Orange or Red colored button, representing a status of On Track, At Risk or Off Track respectively.
The scheduling status is calculated by looking at the Actual Percent Completed versus the Expected Percent Completed.
The scheduling status of leaf tasks (tasks that have no sub tasks) is as follows:
Hammock Work Items are calculated in the same way as Leaf Work Items, unless one or more of the hammock's sub-Work Items are on the critical path. In such cases, the status of the hammock is calculated as a combination of Status fields for active Sub-Work Items on the critical path, and the summary Status of the hammock.
If the hammock's Due Date has passed, its Status overrides any other calculations and becomes Off Track (red).
Example 1
The Status of the hammock is On Track (same or less than 10% different from the expected progress), based on the aggregated Status of its sub-Work Items; some of which are Off Track. In this case, the aggregated status is the same as the expected progress (96%), and the sub-Work Item that is Off Track does not affect the hammock Status as its not on a critical path.
Example 2
The Status of Sub-Items on the critical path can be Green, but the 85% complete rate of the hammock vs. the expected progress of 96% turns the Status to At Risk (orange).
Example 3
In this case, the actual and expected progress are both 96%, however, a Sub-Work Item on the critical path is Off Track, and therefore the hammock Status is At Risk.
Example 4
In this case, the Due Date of the hammock is in the past and therefore its Status overrides all other calculations.
Properties cards can be accessed from the Work Items, Projects, Milestones and Tasks modules by selecting items in the grid, and clicking located in the Relations Panel.
This page describes work item schedule settings and includes the following sections:
For more about Work Policies, click here.
TIP
The option to click the Restore link restores the setting to its previous setting.
Only Financial users can define Finance Settings.
This page describes work item finance settings and includes the following sections:
The financial settings of work items can only be defined by your organization's AdaptiveWork Financial users.
This section enables setting work items as billable project items, rolling up financial and effort data from shortcuts and setting cost and revenue currency types.
This page describes Time Report settings and includes the following sections:
TIP
The option to click the Restore link restores the setting to its previous setting.
The Reportable Start Date field represents the item's Start Date or Reporting Start Date, whichever is earlier. The Show Future Work Items filter is based on this field.
TIP
The option to click the Restore link restores the setting to its previous setting.
To exclude the whole project or a specific branch in the project tree, milestone or hammock task, disable both the Reportable and Allow Reporting on sub-items switches.
NOTE
For Admin users only.
TIP
The option to click the Restore link restores the setting to its previous setting.
Using the Overview standard field in Property Cards, you can add detailed descriptions using rich text formatting options (such as font size, color, and so on), images, and tables.
The Overview field can be found in Portfolios, Work Items, Customers, and Cases.
For each object, you can add up to five additional fields that function the same as Overview fields. The field labels are Overview1 to Overview 5, but you can customize them to suit your organization's requirement. You can use these fields in Configurations and Customizations.
NOTE
You can only edit the label for the field labels that are numbered Overview1 to Overview5. The label for the Overview standard field cannot be edited.