The ‘Activities’ feature enables you to add and manage Activities and Criteria in a Release.
An Activity is a defined action with an output. Activities are assigned against a Phase within a Project and are assigned to individuals with due dates and measurable KPIs. Whereas, Criteria are an exit or entry decision point. Criteria are assigned against a Gate within a project and are assigned to individuals with due dates and measurable KPIs.
To manage Activities/Criteria, you must have the following user permissions:
Release > Manager
To access the Activities tab:
The existing Activities/Criteria (if any) are displayed here.

Activities are represented by
and Criteria are represented by
.
The progress bar shows the total number of Activities/Criteria available in the Release and % of completion.

Hide or unhide Activities (Phases) and Criteria (Gates) by clicking
and
. To hide Activities and Criteria belonging to the child Releases click
.
Click on the status link to filter by status.

Select a name from the Filter by Assignee drop-down menu to show only the Activities and Criteria assigned to that entity.

The Phases/Gates, that are added to the Release, are listed on top of the Activities grid. Clicking on a Phase/Gate displays Activities/Criteria that belong to the respective Phase/Gate.

The first Phase/Gate from Release, which is not marked as complete, will display
to indicate that it is in progress.
To add a new Activity/Criterion:
.| Fields | Description |
|---|---|
| Id | Enter an Id for the Activity/Criterion. |
| Title | Mandatory; Enter a title. |
| Description | Free text; Enter Activity/Criterion description. |
Add and manage dependency between the Activities/Criteria in this section. For details, see Add Dependency.
This section contains custom fields and tabs, which administrators have added using the Release Activity Custom Fields and the Release Activity Custom Lists Customizations.
These fields vary between each Release & Verify installation. Please consult your administrator for the procedure for filling in these fields.
| Fields | Description |
|---|---|
| Type | Select a type. |
| Status | Select the status from the drop-down. |
| Release Framework | Visible only in Enterprise Release Activity/Criterion;
For further details, see Release Framework |
Select a Stakeholder from the Assigned To drop-down menu. Only Stakeholders selected under the Stakeholders tab appear here.
| Fields | Description |
|---|---|
| Assigned to Phase/Assigned to Gate | Select a Phase (for Activity) or Gate (for Criterion) from the drop-down. |
| Forcast Date | Select a forecast date. |
| Start Date | Select the Activity/Criterion start date. |
| Due Date | Mandatory; Select the due date. |
| Completed Date | Completed Date will fill automatically once the Status ‘Completed’ is selected. |
| Actual Completed Date | Select the Actual Completed Date if it is different from the Completed Date. This field is disabled if the ‘Enable Actual Completed Date’ is not selected in Release Setup Customization. |
You can attach URLs and/or Files. To add a new attachment:
.
. In the case of a File, select an attachment file and click Open.The selected URL or file display in the ‘Attachment’ section.
next to the attachment.
next to the attachment.After making all the entries on this pop-up, click
. The Activity/Criterion will be saved and available on the grid.
NOTE
To continue adding more Activities/Criteria, click
.

You can add dependency between the Activities/Criteria using the ‘Dependency’ feature. The Activities/Criteria can have dependencies on the other Activities/Criteria within the same or different Release that belong to the same parent Release.
Using this feature, Release & Verify restricts you from changing the status of the successor Activity/Criterion to ‘In Progress’ or ‘Completed’ unless all the preceding Activities/Criteria are resolved (i.e have a status Completed or N/A).
In case of unresolved dependencies, the options ‘In Progress’ and ‘Completed’ in the Status drop-down will be disabled. It allows you to manage the status of the Activities/Criteria by ensuring that the preceding Activity/Criterion has been finished (with status Completed or N/A) before you start working on the succeeding Activity/Criterion.

To add a dependency:
.
| Fields | Description |
|---|---|
| Release | Select a Release from the drop-down to create a dependency. Only the Releases that belong to the same parent Release will be available for selection. |
| Dependency Type | Disabled; Only ‘Finish to Start’ dependency is available. |
| Phase / Gate | Select a Phase/Gate to filter the relevant Activities/Criteria |
| Activity / Criterion | Select one or more Activities/Criteria from the drop-down. |
. The ‘View/Edit Activity’ (or ‘View/Edit Criterion’) pop-up will be back to display and the selected Activity/Criterion will be added to the ‘Dependency’ section. The count next to the ‘Dependency’ title represents the total number of dependencies added to this Activity/Criterion.
NOTE
If you are adding the dependency to a new Activity/Criterion,
will be disabled. In that case, click
on the pop-up. This will enable the button

To remove a dependency, hover and click X
next to the dependency. A pop-up displays for your confirmation. Click
.

NOTE
You can track the added and removed dependencies in the Audit.
Edit the following fields directly from the grid:
Click on the Title to open the Activity/Criterion ‘View/Edit’ pop-up. Here, you can update the fields as per your requirements. Refer to the above section for details.
Updating the Due Date of an Activity/Criterion, that has one or more successor Activity/Criterion, to a future date enables you to shift the Start Date, Due Date, and Forecast Date of all the successor Activities/Criteria. In this case, a pop-up displays the list of the successor Activities/Criteria. Clicking
shifts all the dates to the same period.

The Comments tab allows you to add a comment and answer other users’ comments.
.
.
on the confirmation prompt.
.After making the required changes, click
.
To bulk update Activities/Criteria:
.
.
The Activities/Criteria will appear on the grid with the updated details.
During Bulk Update, if the selected Activities/Criteria have a dependency and the dependent Activities/Criteria are not included as part of the Bulk Update, then on selecting
, Release & Verify will display a notification to confirm your actions with the details about the dependent Activities/Criteria.
In this case, the status of the Activities/Criteria with resolved dependency (or no dependency) will be updated, and the status update of those with unresolved dependency will be aborted.

You can create a new Activity/Criterion using the ‘Duplicate’ feature. To duplicate:
.
.
The Activities/Criteria are duplicated and available on the grid.
To delete Activity/Criterion:
.
on the confirmation prompt.
Release & Verify will delete the Activity/Criterion and won’t be available on the grid.
.
and select Import from XLS.Common error messages:
.
.Common error message:
To export the Activities/Criteria, Click
and select Export to XLS from the drop-down menu. Your Excel file should start downloading immediately. If it doesn’t, check your pop-up blocker settings.
Save the file to your hard drive if prompted.
Child Push functionality is available in Enterprise Release only. This functionality enables you to push (copy) the Activity/Criterion to the child Releases. If the child Release already consists of the Activity/Criterion that you want to push, its data will be updated, and you will lose the edits made.
button is visible only on a saved Activity/Criterion. So, once you have finished adding an Activity/Criteria, reopen it again to push (copy) to the child Releases.
button is disabled.To do a Child Push:
is enabled. Click
.
.
A pop-up with a list of Child Push updates displays stating the updated and new content.

NOTE
NoteYou cannot push an Activity/Criteria to the child Release if the ‘Ignore Child’ checkbox is selected for the associated Phase/Gate in the ‘Phases and Gates’ panel. If you select
in this case, Release & Verify displays a pop-up stating the Phase/Gate has been ignored from the Enterprise level. You need to uncheck the 'Ignore Child' checkbox to be able to Child Push.

| Enterprise | Child | Enterprise & Child | |
|---|---|---|---|
| Applicable | Meant for the Enterprise Releases only. | Meant for the child Releases only. | Meant for the Enterprise and child Releases. |
| Child Push | Cannot push to a child Release. will be disabled. |
Can push to child Releases if the Enable Enterprise Activities Child Push functionality is selected in Release Setup Customization. | Can push to child Releases if the Enable Enterprise Activities Child Push functionality is selected in Release Setup Customization. |
| View/Edit | Visible and editable only in the Enterprise Release. | Can edit in the Enterprise Release (the Status will be N/A). Can edit in the child Release if the Release Dependency Association is not selected in Release Setup Customization. |