You can save time by bulk updating Release information, stakeholders, and activities. When bulk updating a field or a tab, data will either be replaced (in the case of text fields and drop-down menus) or added (in the case of Stakeholders and combo boxes).
The steps overlayed in this article is applicable to:
You must have the relevant ‘Update’ user permission for the Release type. For example, ‘Update Enterprise Release’.
Release > Manager
To bulk update Release
.
On the ‘Bulk Update’ pop-up, update the following:
| Fields | Description |
|---|---|
| Release Type | Select a release type from the drop-down. |
| Status | Select a status from the drop-down. |
| Portfolio Association | Select a Portfolio Association from the drop down. |
| Risk Level | Select the risk level. |
| Release Location | Enter a location |
| Implementation Date | Select an Implementation Date. |
| Phases | Select a phase. The Start Date and End Date fields will be grayed out until a Phase is selected |
| Gates | Select a gate. The Start Date and End Date fields will be grayed out until a Gate is selected |

If you have selected a Status with an End State, Please confirm deployment status for each system section displays at the bottom of the pop-up and you need to confirm the deployment status for each system.
Select the System from the list and click Completed, Rejected, or Rollback.

The Additional Information tab contains custom fields, which administrators have added using Release Custom Fields Customization. These fields will vary between each Release & Verify installation. Please consult your administrator for the procedure for filling in these fields.
Live Search for Systems or Portfolio Associations and then drag and drop Systems from the ‘Systems Available’ panel into:

When users are added as stakeholders more than once, they will appear as a stakeholder only once with all their Roles and Stakeholder RACI Roles merged.
For example, if a stakeholder with Role A and all the RACI Roles was added again with Role B and no RACI Roles, the stakeholder would appear only once with Roles A and B and all the RACI Roles.
To add a stakeholder, click
and proceed with filling up the fields. For more information, see Manage Release Stakeholder.
You can bulk update the Activities and Criteria on this tab. Filter the Activities and Criteria using the Activities and Criteria checkboxes.
After doing the required updates on this pop-up, click
. The selected Releases (or Templates) will display with the updates on the grid.