Product Funding

Product Funding

The Product Funding capability supports defining financial targets for products for the organization. Each capability within the Planview Capability Framework has a distinct set of features and functionality, business processes, best practices, and analytics and reports that deliver value to customers in the form of specific business outcomes.

Processes and Reports

conceptual image_product funding.jpg

Product funding supports the ability to set financial targets (benefits and revenue) for each product. A product financial plan is created then baselined to track variances between the forecasted product benefits and revenue and actual costs. This capability supports strategic investment planning by allowing In-flight and potential investments to be analyzed against product financial targets.

           

Video: Product Funding Demo

 

Financial Targets Process Steps

           

Funding Capabilities - Financial Targets Process Flow.png

Financial targets process flow

           

Process Step Description
Define labor costs

Enter the cost targets for labor into the outcome financial plan.

Budgets may be created at any level of the Outcome structure on the Financial Planning Detail screen then spread down to lower levels or rolled up to higher levels. Alternatively, data may be loaded using an outcome financial load, then rolled up and edited.

For more information:

Define non-labor costs

Enter the non-labor costs into the outcome financial plan. These costs should be divided into the appropriate non-labor categories.

Non-labor data is often entered manually, then spread down to lower levels or rolled up to higher levels as part of the larger budgeting process.
Define expected benefits and revenue Enter the revenue targets and benefits for launching the product. These targets and benefits can be manually entered into the outcome financial plan.
Baseline financial plan Following the input or roll-up of the financial plan budget and target data, a financial baseline for the financial plan should be taken to compare and track variances of the product financials over time.

           

           

Financial Targets Reports

How are we able to see our financial targets for benefits and costs?

OUT31 – Outcome Portfolio Revenue and Cost Analysis Analytic This report analyzes program data and summarized portfolio financial plan data, with effort represented as FTEs, days, and hours, and financials as cost, benefits, and revenue. The report uses a single version of the financial plan and a data type based on project attributes, account structure levels, or line attributes of selected accounts. You can configure the report to run against each level in the strategy structure.

OUT33 – Outcome Portfolio Revenue Prioritization Bubble

Analytic

This report can select cost or revenue-based measures from the financial planning data to drive bubble size and visualize the outcome pipeline. You can configure the report to run against each level in the outcome structure.

OUT34 – Outcome Portfolio Risk and Reward Matrix

Analytic This report analyzes the risk and reward balance across the outcome portfolio. You can select revenue measures for the x-axis, risk-based attributes for the y-axis, and cost-based measures for the bubble size.

How are we able to understand how changing demand impacts our financial targets?

Outcome Portfolio – Portfolio Manager – Financial Variance Column Set Tile This column set allows you to compare financial variances between an outcome's forecasted and actual costs.

OUT32 – Outcome Revenue/Cost Forecast Performance

Analytic This report allows you to compare versions of the outcome and summarized portfolio financial plan data, with effort represented as FTEs, days, and hours, and financials as cost and revenue. A burndown chart is included for the whole portfolio and each initiative. You can configure the report to run against each level in the strategy structure.