Add Columns for Planview Enterprise One – PRM Reserves
Summary
This article shows how to add columns in a Microsoft Project plan so that Planview reserve information is visible.
Sign in to access this How-to topic.
You are viewing content for Planview® Enterprise One release 16 – Portfolio and Resource Management and greater.
Reserve Mappings |
|||||
MSP to E1 sync |
|
Create In E1 |
Read from E1 |
Update in E1 |
Comments |
MSP Field |
PVE Field |
|
|
|
|
Date1 |
Start |
Y |
Y |
Y |
|
Date2 |
Finish |
Y |
Y |
Y |
|
Number6 |
Effort |
Y |
Y |
Y |
|
Text6 |
ToleranceDuration |
Y |
Y |
Y |
For Create/Update—if value is null, then set it as -1. This would set the default value in E1. |
Text5 |
TolerancePercent |
Y |
Y |
Y |
For Create/Update—if value is null, then set it as -1. This would set the default value in E1. |
Text4 |
State |
Y |
Y |
Y |
|
Figure 1: Reserve Mappings
Figure 2: Field Settings