WRK05 - Schedule and Effort Variance

Overview

Portfolio exception based analytic that compares the schedule baseline effort and duration to the forecast (scheduled) effort and duration and identifies projects that are forecasting to deliver late or require additional resource to complete.

           

clipboard_ef86b69ecda5cba85be9923662475775b.png

WRK05 example

           

           

Business Outcomes

  • Improved ability to address project time and effort shifts early and drive towards more projects delivered on time and on budget.
  • Relevant information that can be used to improve the processes for estimation, there by improving reliability and confidence on schedule and effort forecasts.
  • Ability to informed decisions based on organizational KPIs – time to market (schedule) or resource constraints (effort).

           

           

Supporting Capabilities

  • Project Monitoring and Status
  • Project Planning and Scheduling

           

           

Report Details

This analytic uses the detailed data from the project schedule to summarize and report on variances between the current project schedule and a selected schedule baseline for the project schedule.
  • The first chart analyzes the date variances between the current scheduled/actual dates of the project and the dates in the selected baseline
  • The second chart analyzes the effort variances between the total effort (requirements, reserves, allocations and actuals) on the project and the total effort in the selected baseline
  • The Detail Table below the charts downs the dates, effort values and variance values calculated and visualized in the charts

The Y axis is the count of the number of projects in the portfolio that have variances within some predefined tolerance bands. These tolerance bands are not configurable.

Projects are classified into bands for both positive and negative variances;

  • 0%
  • 0 - 5%
  • 5 - 10%
  • 10 - 25%
  • Greater than 25%

These groupings are then color classified based upon the following groupings. These groupings are not configurable.

  • Any variance greater than or equal to 0% is classified as Green.
  • Any variance less than -10% is classified as Red.
  • Otherwise the variance is classified as Yellow.
  • All projects that have a positive variance are classified as Green.

A positive variance for Schedule means that a project will be delivered early (ahead of the selected baseline).
A positive variance for Effort means a project will be delivered with less effort than planned in the selected baseline.

A project must have an active schedule baseline for it to be analyzed fully in this report. Projects without a baseline will show in the 0% category.

The Schedule Baseline user parameter allows the user to select which baseline is used for analysis in the report. The available options in the parameter drop down are:

  • **Active Baseline** - this is the baseline for each project that is marked as the Active baseline in the baseline management screens.
  • Any Master Baselines that are being used in governance lifecycles to capture a schedule baseline at a specific point in the governance process for the project.
Colors are determined by these non-configurable thresholds:
  • Any schedule variance greater than or equal to 0% = Green
  • Any schedule variance less than -10% = Red
  • Otherwise = Yellow

           

           

User Parameter Configuration (for Administrators)

Parameters Description Configuration Options Default/Example Settings
Schedule Baseline
(from master list):
Allows the user to choose which schedule baseline is used.
Since each project can have custom baselines created, a portfolio report can’t use these as a selection, so the list comes from the master baseline list that’s typically used in lifecycles. 
Options are any of the master baselines created in System Options/Baseline Administration/Master Baseline Descriptions. To get the master baseline id: edit the master baseline and in the window that opens you’ll see in the URL: “blmid=xyz” where xyz is the value to use in the configuration. The default baseline is identified as Active.
The list of entries in the user parameters is not sorted alphabetically – it’s sorted according to the sort in the management screen referenced above. 
master_baseline_id=active
Effort Unit Unit of measure used for effort Hours or days
Conversion is based on the standard calendar

effort_unit=hours
effort_unit=day
effort_unit=hours
Detail Table Format: Determines whether table is formatted with groups and sub totals or plain for export to Excel Possible values are:
  • grouped
  • plain
table_format=grouped

           

           

Hidden Parameter Configuration (for Administrators)

Parameters Description Configuration Options Default/Example Settings
Table Columns Two grouped columns before the project name.
Three optional columns after the project name.
  wbs_level_3_plan
wbs_level_4_plan
wbs20_plan
lc_role_3_plan
wbs709_plan|Center|bgc 
Report Title Configurable report title that appears at the top of the report. If a longer report title is required, create additional report_title=xxx entries. These will be concatenated together based on the order in which they are listed in the configuration structure. report_title=Project Schedule and Effort Variance

           

           

Technical/Data Information

Report (RDL) Location …/Reports/FastTrack/Work/WRK05-ScheduleEffortVariance/WRK05.rdl
Database This report uses the transactional database and updates will be real-time.