Skip to main content
Planview Customer Success Center

Why Schedule Percent Complete in Project Status Doesn't Reflect Accurately?

Schedule Percent Complete in Project Status Doesn't Reflect Accurately


If the project status field schedule percent complete field is not correct, make sure that the project is not checked out and attempt a project status update. Alternatively, in reporting, the main project percent complete will always be correct, no matter how 'behind' project updates are.