What is the criteria to send out emails saying that a resource is overbooked? (2010)

Changepoint checks the task assignment forecast hours for the next week. If this is more than the resources capacity, the email will be sent. Planned hours or data from the project team are not taken into account. Also, only assignments having the flag 'Include in Resource Demand' enabled are taken into account.