Skip to main content
Planview Customer Success Center

Can calendar entries be shown in the resource management worksheet? (2014)

Project Worksheet (PW) and Resource Management Worksheet (RMW) referenced in this article are based on Silverlight technology and are no longer available as of Changepoint 2020

 

QUESTION

Is it possible to show calendar entries in the resource management worksheet?

 


 

ANSWER

Yes this is possible. In the filter settings, select to show committed or uncommitted demand in the line 'calendar'.

Note: Calendar entries flagged as 'non working day' do not appear as a separate appointment/line in the calendar category. Instead, the effect is that the column for that day is shown as a non-working day (grey and disabled).