Tasks appear in project worksheet but not PPW, even after running WBS utility

f you recently restored the databases, try recreating the CPTempDB.

  1. Set tempDB in ServerSettings table to empty.
  2. Execute DBM_SetupCPTempDB against the Changepoint database. This will reset the CPTempDB.