Scheduling Work Items

 

This page describes AdaptiveWork work item scheduling and includes the following sections:

Work Item Status Display

 

The Scheduling Status of work items is displayed with either a Green, Orange or Red colored button, representing a status of
On Track, At Risk or Off Track respectively :

202028407_at_risk.jpg

202071618_not_active.jpg

202071628_off_track.jpg

202028417_on_track-2-.jpg

Scheduling Status Calculation

AdaptiveWork calculates the scheduling status by analyzing a work item's current Actual Percent Completed versus the defined Expected Percent Completed.

Click here to learn more about how %Completed is calculated in AdaptiveWork (scroll to the relevant section)

Leaf Tasks

The scheduling status of leaf tasks (tasks that have no sub tasks) is as follows:

  • 202028427_on_track-2-.jpg — If the Actual Percent Completed is under 10% less than the Expected Percent Completed or
    Actual Percent Completed is greater than the Expected Percent Completed
  • 202071638_at_risk.jpg — If the Actual Percent Completed is 10% or more below the Expected Percent Completed
  • 202028437_off_track.jpg — The due date of the task has passed and the Actual Percent Completed is less than 100%

 

Hammock Work Items

Hammock Work Items are calculated in the same way as Leaf Work Items, unless one or more of the hammock's sub-Work Items are on the critical path. In such cases, the status of the hammock is calculated as a combination of Status fields for active Sub-Work Items on the critical path, and the summary Status of the hammock.

If the hammock's Due Date has passed, its Status overrides any other calculations and becomes Off Track (red).

 

 

Example 1

The Status of the hammock is On Track (same or less than 10% different from the expected progress), based on the aggregated Status of its sub-Work Items; some of which are Off Track. In this case, the aggregated status is the same as the expected progress (96%), and the sub-Work Item that is Off Track does not affect the hammock Status as its not on a critical path.

mceclip0.png

 

 

Example 2

The Status of Sub-Items on the critical path can be Green, but the 85% complete rate of the hammock vs. the expected progress of 96% turns the Status to At Risk (orange).

mceclip1.png

 

 

Example 3

In this case, the actual and expected progress are both 96%, however, a Sub-Work Item on the critical path is Off Track, and therefore the hammock Status is At Risk.

mceclip2.png

 

 

Example 4

In this case, the Due Date of the hammock is in the past and therefore its Status overrides all other calculations.

mceclip3.png

 

Scheduling Considerations

These fields can be calculated or manually set.
If calculated, a work item’s Start Date / End Date have a time frame. (Refer to Earliest and Latest Dates below.)

The decision on which actual date to use will depend on the factors listed above.